Project Procurement Plan. Contractor shall produce a Project Procurement Plan at NTP for review by Owner. Owner will provide review comments within ten (10) Business Days after receipt. The Project Procurement Plan will address, at a minimum: a. Inspection; b. Expediting; c. Supplier quality reports; d. Technical requirement compliance; e. Material control, marking, and certification; f. Packing, consolidation, importing; g. Transportation, handling, and storage; h. Warranties and guarantees; and