Protest; Statement of General Claim; Time of Submission. No protest of a claim decision of the Program Manager by the Design-Builder, whether said claim shall be accrued or prospective, shall be valid unless a "Statement of Claim" in writing and accompanied by vouchers and other supporting data shall have been filed with the Program Manager, or if there is no Program Manager, with the Owner by the Design-Builder not later than thirty (30) days after the Program Manager’s decision to reject the claim, time being of the essence. The "Statement of Claim" shall contain a concise and clear recital of the grounds and the legal basis upon which the claim is asserted, including a designation of the provision or provisions of the Contract Documents and the legal basis of liability on which the claim is based. The Statement of Claim shall indicate the dollar amount of the claim and the number of days of adjustment of the Contract Time.
Appears in 14 contracts
Samples: Design Build Contract, Design Build Contract, Design Build Contract
Protest; Statement of General Claim; Time of Submission. No protest of a claim decision of the Program Manager Design Professional by the Design-BuilderCM/GC, whether said claim shall be accrued or prospective, shall be valid unless a "Statement of Claim" in writing and accompanied by vouchers and other supporting data shall have been filed with the Program Manager, or if there is no Program Manager, with the Owner by the Design-Builder CM/GC not later than thirty (30) days after the Program ManagerDesign Professional’s decision to reject the claim, time being of the essence. The "Statement of Claim" shall contain a concise and clear recital of the grounds and the legal basis upon which the claim is asserted, including a designation of the provision or provisions of the Contract Documents and the legal basis of liability on which the claim is based. The Statement of Claim shall indicate the dollar amount of the claim and the number of days of adjustment of the Contract Time.
Appears in 13 contracts
Samples: Construction Management Agreement, Construction Management Agreement, Construction Management Agreement
Protest; Statement of General Claim; Time of Submission. No protest of a claim decision of the Program Manager Executive Administrator by the Design-Builder, whether said claim shall be accrued or prospective, shall be valid unless a "Statement of Claim" in writing and accompanied by vouchers and other supporting data shall have been filed with the Program Manager, or if there is no Program Manager, with the Owner by the Design-Builder not later than thirty (30) days after the Program ManagerExecutive Administrator’s decision to reject the claim, time being of the essence. The "Statement of Claim" shall contain a concise and clear recital of the grounds and the legal basis upon which the claim is asserted, including a designation of the provision or provisions of the Contract Documents and the legal basis of liability on which the claim is based. The Statement of Claim shall indicate the dollar amount of the claim and the number of days of adjustment of the Contract Time.
Appears in 2 contracts
Samples: Design Build Contract, Construction Contract
Protest; Statement of General Claim; Time of Submission. No protest of a the Owner‟s claim decision of the Program Manager by the Design-BuilderContractor, whether said claim shall be accrued or prospective, shall be valid unless a "Statement of Claim" in writing and accompanied by vouchers and other supporting data shall have been filed with the Program ManagerOwner‟s Representative, or if there is no Program ManagerOwner‟s Representative, with the Owner by the Design-Builder Contractor not later than thirty (30) days after the Program Manager’s Design Professional‟s decision to reject the claim, time being of the essence. The "Statement of Claim" shall contain a concise and clear recital of the grounds and the legal basis upon which the claim is asserted, including a designation of the provision or applicable provisions of the Contract Documents and the legal basis of liability on which the claim is basedDocuments. The Statement of Claim shall indicate the dollar amount of the claim and the number of days of adjustment of the Contract Time.
Appears in 1 contract
Protest; Statement of General Claim; Time of Submission. No protest of a the Owner’s claim decision of the Program Manager by the Design-BuilderCM/GC, whether said claim shall be accrued or prospective, shall be valid unless a "Statement of Claim" in writing and accompanied by vouchers and other supporting data shall have been filed with the Program Manager, or if there is no Program Manager, with the Owner by the Design-Builder CM/GC not later than thirty (30) days after the Program Manager’s decision to reject the claim, time being of the essence. The "Statement of Claim" shall contain a concise and clear recital of the grounds and the legal basis upon which the claim is asserted, including a designation of the provision or provisions of the Contract Documents and the legal basis of liability on which the claim is based. The Statement of Claim shall indicate the dollar amount of the claim and the number of days of adjustment of the Contract Time.
Appears in 1 contract
Samples: Construction Management Agreement