Punch List Completion Sample Clauses
The Punch List Completion clause outlines the process for identifying and addressing minor outstanding work items or deficiencies at the end of a construction project. Typically, after substantial completion, the contractor and owner jointly inspect the project to create a punch list detailing items that need correction or completion before final acceptance. This clause ensures that all minor issues are formally documented and resolved, providing a clear path to project closeout and protecting both parties by clarifying expectations for final deliverables.
Punch List Completion. The Contractor understands and agrees that time is of the essence in closing out the Work of this Contract. Upon Substantial Completion of the Work, the Punch List will be transmitted to the Contractor from the Member. The Contractor agrees to begin performance of Punch List Work immediately after receipt of the Punch List. Failure of the Contractor or its Subcontractors to begin the Punch List Work within three (3) business days after receipt of the Punch List will be construed as failure to prosecute the Work of the Contract. Punch List Work will be continuously prosecuted once begun and completed within thirty (30) Days from the receipt of the Punch List. Should the Contractor fail to complete the Punch List within this period of time, the liquidated damages (See Section Three: General Terms and Conditions for JOC, Article 45, Liquidated Damages) Contract General Conditions will apply.
Punch List Completion.
10.1. The Contractor understands and agrees that time is of the essence in closing out the Work of this Contract. Upon Substantial Completion of the Work, the Punch List will be transmitted to the Contractor from the Sourcewell Member. The Contractor agrees to begin performance of Punch List Work immediately after receipt of the Punch List.
10.2. Failure of the Contractor or its Subcontractors to begin the Punch List Work within three (3) business days after receipt of the Punch List will be construed as failure to prosecute the Work of the Contract.
10.3. Punch List Work will be continuously prosecuted once begun and completed within 30 Days from the receipt of the Punch List. Should the Contractor fail to complete the Punch List within this period of time, the liquidated damages as identified in Article 26 of the Contract General Conditions will apply.
Punch List Completion. The Seller shall cause all items on the Punch List (the “Seller Punch List Items”) to be completed no later than ninety ( 90) Days after the achievement of Project Substantial Completion or as soon as reasonably practicable thereafter (the “Punch List Completion Deadline”). 31
Punch List Completion. Our Inspector will generate and make the contractor aware of deficiencies as they occur in the field. We will encourage the contractor to repair or replace work that does not meet the specifications when it is identified. Interwest will oversee the complete performance of all punch
Punch List Completion. As soon as possible, but in Landlord shall, subject to the any event on or before 90 provisions of Paragraph 10 below, days after the applicable complete any punch-list items Notice of Substantial identified in any Punch List (defined Completion (defined below in below in Paragraph 10) and attached to Paragraph 10) has been any Notice of Substantial Completion, confirmed (or deemed except for Delay Items. confirmed) by Landlord and Tenant.