Queue Number. 1.7.1 The Utility shall assign a Queue Number pursuant to Section 1.4.2. Subject to an Interconnection Customer’s election to participate in an optional Utility-sponsored System Impact Grouping Study, as described in Section 4.3.4, the Queue Number of each Interconnection Request shall be used to determine the cost responsibility for the Upgrades necessary to accommodate the interconnection. Subject to Sections 1.7.3, 1.8, and Section 4.3.4, the Queue Number of each Interconnection Request shall also determine the order in which each Interconnection Request is studied. 1.7.2 Subject to the provisions of Sections 1.4, 1.5, and 1.6, Generating Facilities shall retain the Queue Number assigned to their initial Interconnection Request throughout the review process, including when moving through the processes covered by Sections 2, 3, and 4. 1.7.3 A Queue Number established for purposes of administering a Competitive Resource Solicitation under Section 4.3.4 shall not be subject to the Interdependency provisions of Section 1.8. Any Interconnection Customer that elects to participate in the System Impact Grouping Study and is selected through the Competitive Resource Solicitation shall complete the Section 4 Study process based upon the Queue Position designated to administer the Competitive Resource Solicitation and the Interconnection Customer’s cost responsibility shall be determined based upon the terms of the Competitive Resource Solicitation. Any Interconnection Customer that elects to participate in the System Impact Grouping Study established in Section 4.3.4 but is not selected through the Competitive Resource Solicitation shall be deemed subordinate to the designated Competitive Resource Solicitation Queue Number or an Interconnection Customer that has completed System Impact Study and committed to Upgrades under Section 4.3.9, but shall maintain its original Queue Position for purposes of determining cost responsibility for Upgrades in relation to (i) other Interconnection Customers that elected to participate in the System Impact Grouping Study, but were not selected through the Competitive Resource Solicitation; and (ii) projects that were assigned a Queue Number after the date on which the Queue Number was designated by the Utility to administer the System Impact Grouping Study.
Appears in 2 contracts
Samples: Interconnection Procedures, Interconnection Procedures
Queue Number. 1.7.1 The Utility shall assign a Queue Number pursuant to Section 1.4.2. Subject to an Interconnection Customer’s election to participate in an optional Utility-sponsored System Impact Grouping Study, as described in Section 4.3.4, the Queue Number of each Interconnection Request shall be used to determine the cost responsibility for the Upgrades necessary to accommodate the interconnection. Subject to Sections Section 1.7.3, 1.8, and Section 4.3.4, the Queue Number of each Interconnection Request shall also determine the order in which each Interconnection Request is studied.
1.7.2 Subject to the provisions of Sections 1.4, 1.5, and 1.6, Generating Facilities shall retain the Queue Number assigned to their initial Interconnection Request throughout the review process, including when where moving through the processes covered by Sections 2, 3, and 4.
1.7.3 A Queue Number established for purposes of administering a Competitive Resource Solicitation under Section 4.3.4 shall not be subject to the Interdependency provisions of Section 1.8. Any Interconnection Customer that elects to participate in the System Impact Grouping Study and is selected through the Competitive Resource Solicitation shall complete the Section 4 Study process based upon the Queue Position designated to administer the Competitive Resource Solicitation and the Interconnection Customer’s cost responsibility shall be determined based upon the terms of the Competitive Resource Solicitation. Any Interconnection Customer that elects to participate in the System Impact Grouping Study established in Section 4.3.4 but is not selected through the Competitive Resource Solicitation shall be deemed subordinate to the designated Competitive Resource Solicitation Queue Number or an Interconnection Customer that has completed System Impact Study and committed to Upgrades under Section 4.3.9, but shall maintain its original Queue Position for purposes of determining cost responsibility for Upgrades in relation to (i) other Interconnection Customers that elected to participate in the System Impact Grouping Study, but were not selected through the Competitive Resource Solicitation; and (ii) projects that were assigned a Queue Number after the date on which the Queue Number was designated by the Utility to administer the System Impact Grouping Study.
Appears in 1 contract
Samples: Interconnection Procedures
Queue Number. 1.7.1 The Utility shall assign a Queue Number pursuant to Section 1.4.2. Subject to an Interconnection Customer’s election to participate in an optional Utility-sponsored System Impact Grouping Study, as described in Section 4.3.4, the The Queue Number of each Interconnection Request shall be used to determine the cost responsibility for the Upgrades necessary to accommodate the interconnection. Subject to Sections 1.7.3, Section 1.8, and Section 4.3.4, the Queue Number of each Interconnection Request shall also determine the order in which each Interconnection Request is studied.
1.7.2 Subject to the provisions of Sections 1.4, 1.5, and 1.6, Generating Facilities shall retain the Queue Number assigned to their initial Interconnection Request throughout the review process, including when where moving through the processes covered by Sections 2, 3, and 4.
1.7.3 A 1.8 Interdependent Projects C” “Interdependent Customer” (or “Project”), “Project A,” and “Project B,” and “Project are defined in the glossary of terms (see Attachment 1).
1.8.1 Upon an Interconnection Customer’s submission of a Section 1.4 Interconnection Request for the Section 3 Fast Track Process or Section 4 Study Process, the Utility shall review the Interconnection Request and make a preliminary determination whether any known Interdependency exists between the Interconnection Customer’s proposed Generating Facility and any other Interconnection Customer with a lower Queue Number established for purposes of administering a Competitive Resource Solicitation under Section 4.3.4 shall not be subject to the Interdependency provisions of Section 1.8Number. Any Interconnection Customer preliminary determination by the Utility that elects to participate the Generating Facility does not create an Interdependency will result in the System Impact Grouping Study Interconnection Request being preliminarily designated as a Project A and is selected through the Competitive Resource Solicitation Utility shall complete proceed immediately to either the Section 3 Fast Track Process or the Section 4 Study process based upon process, as applicable. The Utility shall advise the Queue Position designated to administer Interconnection Customer at the Competitive Resource Solicitation and Section 4.2 Scoping Meeting, if requested by the Interconnection Customer’s cost responsibility shall , regarding its preliminary determination of whether Interdependency would be created by the Generating Facility. A Generating Facility designated and reviewed for system impacts as a Project A may still be determined based upon the terms of the Competitive Resource Solicitation. Any Interconnection Customer that elects to participate in the System Impact Grouping Study established in Section 4.3.4 but is not selected through the Competitive Resource Solicitation shall create an Interdependency and may be deemed subordinate to the designated Competitive Resource Solicitation Queue Number or an Interconnection Customer that has completed System Impact Study and committed to Upgrades under Section 4.3.9, but shall maintain its original Queue Position for purposes of determining cost responsibility for Upgrades in relation to (i) other Interconnection Customers that elected to participate in the System Impact Grouping Study, but were not selected through the Competitive Resource Solicitation; and (ii) projects that were assigned a Queue Number after the date on which the Queue Number was designated by the Utility to administer as an Interdependent Project during the System Impact Grouping Study.Section
Appears in 1 contract
Samples: Interconnection Procedures