Released for Construction. Developer may start the construction of any element of the permanent components only after occurrence of all of the following: 1. The Designer has conducted its design QC checks throughout the design process in compliance with the Design QA/QC Plan and certifies, in writing, that the Design Document is complete to the appropriate level or stage of review, checked, and ready to be Released-for-Construction. 2. The DQAM has signed the title sheet for the drawings, certifying to the following (the title sheet can be formatted to include the items of certification): a. Design checks have been completed; b. Design Work conforms to requirements of the PPA Documents; c. Any Deviations or design exceptions have been approved, in writing, by IFA; d. Design QC activities are following Developer’s Design QA/QC Plan; and e. All outstanding issues or comments from Design Reviews have been resolved to IFA’s satisfaction. 3. The Responsible Engineer has signed all drawings prepared under their direction. For those drawings and documents included in the Submittal that are prepared by a manufacturer or Supplier or other persons not under the direct supervision of the Responsible Engineer, the Responsible Engineer shall affix a stamp that indicates the design shown on the sheet or Design Document conforms to the overall design and requirements of the PPA Documents. 4. The DQAM has signed the title sheet to the drawings certifying to the items contained in Section 3.2.4. The title sheet can be formatted to include the items of certification. 5. Developer has verified in writing the following: a. Design has undergone constructability review and is constructible as represented; b. Design Documents, Construction Documents, and related documents for the portion of the East End Crossing to be constructed are complete and checked; c. The design and drawings for maintenance of traffic (MOT) and temporary erosion control and environmental measures applicable to the Work are complete; and d. Adequate stakes, lines, and monuments necessary to control the Work have been established on the Site. e. Developer has addressed the IFA-provided written comments regarding the Design Documents and applicable MOT plans, temporary erosion control measures, and environmental requirements to the IFA’s satisfaction. 6. Developer’s Lead Engineer stamps the Design Documents as “released for construction”. See Section 3.1.8 of the PPA for additional information regarding the affect of IFA’s consultation and written comments. Any design Nonconformance Reports issued by the DQAM or IFA shall be addressed and resolved by Developer, to the satisfaction of IFA prior to any design being Released-for- Construction.
Appears in 2 contracts
Released for Construction. Developer may start the construction of any element of the permanent components only after occurrence of all of the following:
1. The Designer has conducted its design QC checks throughout the design process in compliance with the Design QA/QC Plan and certifies, in writing, that the Design Document is complete to the appropriate level or stage of review, checked, and ready to be Released-for-Construction.
2. The DQAM has signed the title sheet for the drawings, certifying to the following (the title sheet can be formatted to include the items of certification):
a. Design checks have been completed;
b. Design Work conforms to requirements of the PPA Documents;
c. Any Deviations or design exceptions have been approved, in writing, by IFA;
d. Design QC activities are following Developer’s Design QA/QC Plan; and
e. All outstanding issues or comments from Design Reviews have been resolved to IFA’s satisfaction.
3. The Responsible Engineer has signed all drawings prepared under their direction. For those drawings and documents included in the Submittal that are prepared by a manufacturer or Supplier or other persons not under the direct supervision of the Responsible Engineer, the Responsible Engineer shall affix a stamp that indicates the design shown on the sheet or Design Document conforms to the overall design and requirements of the PPA Documents.
4. The DQAM has signed the title sheet to the drawings certifying to the items contained in Section 3.2.4. The title sheet can be formatted to include the items of certification.
5. Developer has verified in writing the following:
a. Design has undergone constructability review and is constructible as represented;
b. Design Documents, Construction Documents, and related documents for the portion of the East End Crossing to be constructed are complete and checked;
c. The design and drawings for maintenance of traffic (MOT) and temporary erosion control and environmental measures applicable to the Work are complete; and
d. Adequate stakes, lines, and monuments necessary to control the Work have been established on the Site.
e. Developer has addressed the IFA-provided written comments regarding the Design Documents and applicable MOT plans, temporary erosion control measures, and environmental requirements to the IFA’s satisfaction.
6. Developer’s Lead Engineer stamps the Design Documents as “released for construction”. See Section 3.1.8 of the PPA for additional information regarding the affect of IFA’s consultation and written comments. Any design Nonconformance Reports issued by the DQAM or IFA shall be addressed and resolved by Developer, to the satisfaction of IFA prior to any design being Released-for- Construction.
Appears in 1 contract
Samples: Public Private Agreement
Released for Construction. Developer may start the construction of any element of the permanent components only after occurrence of all of the following:
1. The Designer has conducted its design QC checks throughout the design process in compliance with the Design QA/QC Plan and certifies, in writing, that the Design Document is complete to the appropriate level or stage of review, checked, and ready to be Released-for-Construction.
2. The DQAM has signed the title sheet for the drawings, certifying to the following (the title sheet can be formatted to include the items of certification):
a. Design checks have been completed;
b. Design Work conforms to requirements of the PPA Documents;
c. Any Deviations or design exceptions have been approved, in writing, by IFA;
d. Design QC activities are following Developer’s Developer‘s Design QA/QC Plan; and
e. All outstanding issues or comments from Design Reviews have been resolved to IFA’s IFA‘s satisfaction.
3. The Responsible Engineer has signed all drawings prepared under their direction. For those drawings and documents included in the Submittal that are prepared by a manufacturer or Supplier or other persons not under the direct supervision of the Responsible Engineer, the Responsible Engineer shall affix a stamp that indicates the design shown on the sheet or Design Document conforms to the overall design and requirements of the PPA Documents.
4. The DQAM has signed the title sheet to the drawings certifying to the items contained in Section 3.2.4. The title sheet can be formatted to include the items of certification.
5. Developer has verified in writing the following:
a. Design has undergone constructability review and is constructible as represented;
b. Design Documents, Construction Documents, and related documents for the portion of the East End Crossing to be constructed are complete and checked;
c. The design and drawings for maintenance of traffic (MOT) and temporary erosion control and environmental measures applicable to the Work are complete; and
d. Adequate stakes, lines, and monuments necessary to control the Work have been established on the Site.
e. Developer has addressed the IFA-provided written comments regarding the Design Documents and applicable MOT plans, temporary erosion control measures, and environmental requirements to the IFA’s IFA‘s satisfaction.
6. Developer’s Developer‘s Lead Engineer stamps the Design Documents as “released ―released for construction”. construction‖. See Section 3.1.8 of the PPA for additional information regarding the affect of IFA’s IFA‘s consultation and written comments. Any design Nonconformance Reports issued by the DQAM or IFA shall be addressed and resolved by Developer, to the satisfaction of IFA prior to any design being Released-for- Construction.
Appears in 1 contract