Common use of RELEASES OF HAZARDOUS SUBSTANCES Clause in Contracts

RELEASES OF HAZARDOUS SUBSTANCES. Upon any release of any hazardous substance in connection with the Work, whether relating to a pre-existing condition or acts or omissions of Contractor, Contractor shall take immediate action reasonably necessary to contain the release and if the hazardous material release is not a Contractor release, Owner will pay Contractor the reasonable costs incurred by Contractor in taking such containment action. Owner may elect to have Contractor control and carry out any containment, clean-up, removal and remediation activity needed, provided that if the release is not a Contractor release, Owner will be responsible to pay Contractor for such Contractor containment activities in accordance with Section 10.4 of these General Conditions, including allowance of additional Contract Time thereunder.

Appears in 4 contracts

Samples: Northern Arizona University Standard Form Agreement, Form Agreement, Form Agreement

AutoNDA by SimpleDocs
Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!