Remedy for Concurrent Delay. Contractor’s sole remedy for Excusable Delays satisfying the requirements of Section 13.3.1 that are concurrent delays to the Critical Path shall be an adjustment to the Scheduled Substantial Completion Date in accordance with this Contract. Multiple delays to the Critical Path caused by the same party shall not be considered concurrent delays.
Appears in 3 contracts
Samples: Design Build Contract, Design Build Contract, Design Build Contract
Remedy for Concurrent Delay. Contractor’s sole remedy for Excusable Delays satisfying the requirements of Section 13.3.1 that are concurrent delays to the Critical Path shall be an adjustment to the Scheduled Substantial Completion Date Contract Time(s) in accordance with this Contract. Multiple delays to the Critical Path caused by the same party shall not be considered concurrent delays.
Appears in 2 contracts
Samples: Design Build Contract, Design Build Contract