REPORTS BY CONTRACTOR. In addition to any reports required elsewhere under this Contract, including Exhibit A (Statement of Work) and Attachment A.1 (Tasks and Deliverables) to this Contract, in order to control expenditures and to ensure the reporting of all Work provided by Contractor, Contractor must provide to County Project Manager, as frequently as may be requested by County Project Manager, but in no event more frequently than weekly, written reports which must include, at a minimum, the following information: a. Period covered by the report, b. Summary of Project status as of reporting xxxx, x. Overview of the Work provided during the reporting period, d. Progress status of each Work component scheduled for the reporting period, e. Issues/problems encountered, proposed resolutions and projected completion dates for problem resolution, f. Status of contractually defined Deliverables, milestones and walk-throughs scheduled in the Project Schedule, g. Action items and decisions from the previous meeting, h. Planned activities for the next two reporting periods, and i. Any other information which the County may from time-to-time require.
Appears in 2 contracts
Samples: Contract for Regional Photo System (Rps) Solution, Contract for Regional Photo System (Rps) Solution
REPORTS BY CONTRACTOR. In addition to any reports required elsewhere under this Contract, including Exhibit A (Statement of WorkWork - General) and Attachment A.1 (Tasks and DeliverablesSOW Outline) to this Contract, in order to control expenditures and to ensure the reporting of all Work provided by Contractor, Contractor must provide to County Project Manager, as frequently as may be requested by County Project Manager, but in no event more frequently than weekly, written reports which must include, at a minimum, the following information:
a. Period covered by the report,
b. Summary of Project status as of reporting xxxx,
x. Overview of the Work provided during the reporting period,
d. Progress status of each Work component scheduled for the reporting period,
e. Issues/problems encountered, proposed resolutions and projected completion dates for problem resolution,
f. Status of contractually defined Deliverables, milestones and walk-throughs scheduled in the Project Schedule,
, g. Action items and decisions from the previous meeting,
h. Planned activities for the next two reporting periods, and
i. Any other information which the County may from time-to-time require.
Appears in 1 contract
Samples: Contract for Computer Aided Dispatch (Cad) Services
REPORTS BY CONTRACTOR. In addition to any reports required elsewhere under this Contract, including Exhibit A (Statement of Work) and Attachment A.1 (Tasks and Deliverables) to this Contract, in order to control expenditures and to ensure the reporting of all Work provided by Contractor, Contractor must provide to County Project Manager, as frequently as may be requested by County Project Manager, but in no event more frequently than weekly, written reports which must include, at a minimum, the following information:
a. Period covered by the report,
b. Summary of Project status as of reporting xxxx,
x. Overview of the Work provided during the reporting period,
d. Progress status of each Work component scheduled for the reporting period,
e. Issues/problems encountered, proposed resolutions and projected completion dates for problem resolution,
f. Status of contractually defined Deliverables, milestones and walk-throughs scheduled in the Project Schedule,
, g. Action items and decisions from the previous meeting,
h. Planned activities for the next two reporting periods, and
i. Any other information which the County may from time-to-time require.
Appears in 1 contract