Requirements for Occupancy. Subject to Section 8.12 herein, no building erected on the Lots or Blocks within the Plan shall be occupied until a Certificate of Inspection re: Readiness for Occupancy has been issued by the Municipality’s Chief Building Official and the said Certificate shall not be issued until: (a) A Certificate of Preliminary Acceptance has been issued for Stage 2 Works for the Phase of the Subdivision including the subject Lot or Block; (b) The roadway from the entrance of the Development to and including the lot or Block of which the building is a part, has received the base course asphalt; (c) The electrical distribution plant including street lights have been installed and approved by the Utility; (d) The traffic and street signs have been installed and approved by the Director of Infrastructure and Development; (e) Subject to Section 6.4 (c), the final grading of the Lot or Block is in conformity with the overall Lot Grading Plan or such variances therefrom as have been approved by the Municipality’s Chief Building Official pursuant to Section 6.4 (c); (f) The telephone lines, cable T.V. and gas mains have been installed and approved by the Director of Infrastructure and Development; and (g) The Developer agrees that the preceding requirements in this Section are in addition to and not in substitution for the requirements of the Ontario Building Code Act as amended and regulations thereunder with respect to certificates for occupancy.
Appears in 1 contract
Samples: Subdivision Agreement
Requirements for Occupancy. Subject to Section 8.12 8.11 herein, no building erected on the Lots or Blocks within the Plan shall be occupied until a Certificate of Inspection re: Readiness for Occupancy has been issued by the Municipality’s Chief Building Official and the said Certificate shall not be issued until:
(a) A Certificate of Preliminary Acceptance has been issued granted for Stage 2 Works servicing for the Phase phase of the Subdivision including the subject Lot or Block;.
(b) The roadway from the entrance of the Development Subdivision to and including the lot or Block block of which the building is a part, has received the base course asphalt;.
(c) The electrical distribution plant including street lights have been installed and approved by the Utility;Utility Company.
(d) The traffic and street signs have been installed and approved by the Director of Infrastructure and Development;Municipality’s Engineer.
(e) Subject to Section 6.4 (c), the final grading of the Lot or Block is in conformity with the overall Lot Grading Plan grading plan or such variances therefrom as have been approved by the Municipality’s Chief Building Official pursuant to Section 6.4 (c);.
(f) The telephone lines, cable T.V. and gas mains have been installed and approved by the Director of Infrastructure and Development; andMunicipality’s Engineer.
(g) The Developer agrees that the preceding requirements in this Section are in addition to and not in substitution for of the requirements of the Ontario Building Code Act as amended Act, 1992, S.O. 1992, c.23, and any amendments thereto and regulations thereunder with respect to certificates for occupancy.
Appears in 1 contract
Samples: Subdivision Agreement
Requirements for Occupancy. Subject to Section 8.12 herein, no building erected on the Lots or Blocks within the Plan shall be occupied until a Certificate of Inspection re: Readiness for Occupancy has been issued by the Municipality’s Chief Building Official and the said Certificate shall not be issued until:
(a) A Certificate of Preliminary Acceptance has been issued for Stage 2 Works for the Phase of the Subdivision including the subject Lot or Block;
(b) The roadway from the entrance of the Development to and including the lot or Block of which the building is a part, has received the base course asphalt;
(c) The electrical distribution plant including street lights have been installed and approved by the Utility;
(d) The traffic and street signs have been installed and approved by the Director General Manager of Infrastructure and Development;
(e) Subject to Section 6.4 (c), the final grading of the Lot or Block is in conformity with the overall Lot Grading Plan or such variances therefrom as have been approved by the Municipality’s Chief Building Official pursuant to Section 6.4 (c);
(f) The telephone lines, cable T.V. and gas mains have been installed and approved by the Director General Manager of Infrastructure and Development; and
(g) The Developer agrees that the preceding requirements in this Section are in addition to and not in substitution for the requirements of the Ontario Building Code Act as amended and regulations thereunder with respect to certificates for occupancy.
Appears in 1 contract
Samples: Subdivision Agreement
Requirements for Occupancy. Subject to Section 8.12 8.11 herein, no building erected on the Lots or Blocks within the Plan shall be occupied until a Certificate of Inspection re: Readiness for Occupancy has been issued by the Municipality’s Chief Building Official and the said Certificate shall not be issued until:
(a) A Certificate of Preliminary Acceptance has been issued granted for Stage 2 Works servicing for the Phase phase of the Subdivision including the subject Lot or Block;.
(b) The roadway from the entrance of the Development Subdivision to and including the lot or Block block of which the building is a part, has received the base course asphalt;.
(c) The electrical distribution plant including street lights have been installed and approved by the Utility;.
(d) The traffic and street signs have been installed and approved by the Director of Infrastructure and Development;Municipality’s Engineer.
(e) Subject to Section 6.4 (c), the final grading of the Lot or Block is in conformity with the overall Lot Grading Plan grading plan or such variances therefrom as have been approved by the Municipality’s Chief Building Official pursuant to Section 6.4 (c);.
(f) The telephone lines, cable T.V. and gas mains have been installed and approved by the Director of Infrastructure and Development; andMunicipality’s Engineer.
(g) The Developer agrees that the preceding requirements in this Section are in addition to and not in substitution for of the requirements of the Ontario Building Code Act as amended Act, 1992, S.O. 1992, c.23, and any amendments thereto and regulations thereunder with respect to certificates for occupancy.
Appears in 1 contract
Samples: Subdivision Agreement