Common use of Resolution by Negotiation Clause in Contracts

Resolution by Negotiation. (a) As an express condition precedent to commencement of any further proceedings with respect to a Claim (except as may be provided under any applicable lien statute), the Party making such Claim shall notify the other Party's Project Director in writing of such Claim. The Contractor's Project Director and the Owner's Project Director shall meet within thirty (30) Days of receipt of the written notice of such Claim for the purpose of attempting to resolve the Claim. (b) If, after the Contractor's Project Director and the Owner's Project Director meet, the Claim remains unresolved or if no such meeting takes place for any reason within such thirty (30) Day period, then an executive vice president (or equivalent) of (i), in the case of Contractor, each Consortium Member (unless otherwise agreed by the Consortium Members) and (ii), in the case of Owner, each of SCE&G and Santee Xxxxxx (unless otherwise agreed by them) shall meet to attempt to resolve such Claim, as applicable, within fifteen (15) Days from the end of such thirty (30) Day period. (c) If the Claim remains unresolved after the fifteen (15) Day period described in Section 27.3(b) and the Parties have not mutually agreed in writing to mediate such Claim, then: (i) with respect to a Claim that exceeds the Threshold Amount, either Party shall have the right to proceed to litigation of such Claim in a court of competent jurisdiction pursuant to Section 27.7; and (ii) with respect to a Claim that meets or falls below the Threshold Amount, such Claim shall be resolved pursuant to Section 27.5. (d) The Parties agree to make a diligent, good faith attempt to resolve a Claim as expeditiously as reasonably possible as provided in this Section 27.3. Execution Version Confidential Trade Secret Information—Subject to Restricted Procedures

Appears in 1 contract

Samples: Engineering, Procurement and Construction Agreement (South Carolina Electric & Gas Co)

AutoNDA by SimpleDocs

Resolution by Negotiation. (a) As an express condition precedent to commencement of any further proceedings with respect to a Claim (except as may be provided under any applicable lien statute), the Party making such Claim shall notify the other Party's ’s Project Director in writing of such Claim. The Contractor's ’s Project Director and the Owner's ’s Project Director shall meet within thirty (30) Days of receipt of the written notice of such Claim for the purpose of attempting to resolve the Claim. (b) If, after the Contractor's ’s Project Director and the Owner's ’s Project Director meet, the Claim remains unresolved or if no such meeting takes place for any reason within such thirty (30) Day period, then an executive vice president (or equivalent) of (i), in the case of Contractor, each Consortium Member (unless otherwise agreed by the Consortium Members) and (ii), in the case of Owner, each of SCE&G and Santee Xxxxxx (unless otherwise agreed by them) shall meet to attempt to resolve such Claim, as applicable, within fifteen (15) Days from the end of such thirty (30) Day period. (c) If the Claim remains unresolved after the fifteen (15) Day period described in Section 27.3(b) and the Parties have not mutually agreed in writing to mediate such Claim, then: (i) with respect to a Claim that exceeds the Threshold Amount, either Party shall have the right to proceed to litigation of such Claim in a court of competent jurisdiction pursuant to Section 27.7; and (ii) with respect to a Claim that meets or falls below the Threshold Amount, such Claim shall be resolved pursuant to Section 27.5. (d) The Parties agree to make a diligent, good faith attempt to resolve a Claim as expeditiously as reasonably possible as provided in this Section 27.3. “[**]” in this Exhibit 10.01 indicates material that has been omitted pursuant to a request for confidential treatment and filed separately with the Securities and Exchange Commission. Execution Version Confidential Trade Secret Information—Subject to Restricted Procedures

Appears in 1 contract

Samples: Engineering, Procurement and Construction Agreement (Scana Corp)

Resolution by Negotiation. (a) As an express condition precedent to commencement of any further proceedings with respect to a Claim (except as may be provided under any applicable lien statute), the Party making such Claim shall notify the other Party's Project Director in writing of such Claim. The Contractor's Project Director and the Owner's Project Director shall meet within thirty (30) Days [**] of receipt of the written notice of such Claim for the purpose of attempting to resolve the Claim. (b) If, after the Contractor's Project Director and the Owner's Project Director meet, the Claim remains unresolved or if no such meeting takes place for any reason within such thirty (30) Day [**] period, then an executive vice president (or equivalent) of (i), in the case of Contractor, each Consortium Member (unless otherwise agreed by the Consortium Members) and (ii), in the case of Owner, each of SCE&G and Santee Xxxxxx Xxxxxx (unless otherwise agreed by them) shall meet to attempt to resolve such Claim, as applicable, within fifteen (15) Days [**] from the end of such thirty (30) Day [**] period. (c) If the Claim remains unresolved after the fifteen (15) Day [**] period described in Section 27.3(b) and the Parties have not mutually agreed in writing to mediate such Claim, then: (i) with respect to a Claim that exceeds the Threshold Amount, either Party shall have the right to proceed to litigation of such Claim in a court of competent jurisdiction pursuant to Section 27.7[**]; and (ii) with respect to a Claim that meets or falls below the Threshold Amount, such Claim shall be resolved pursuant to Section 27.5.[**] (d) The Parties agree to make a diligent, good faith attempt to resolve a Claim as expeditiously as reasonably possible as provided in this Section 27.3. Execution Version Confidential Trade Secret Information—Subject “[**]” in this Exhibit 10.02 indicates material that has been omitted pursuant to Restricted Proceduresa request for confidential treatment and filed separately with the Securities and Exchange Commission.

Appears in 1 contract

Samples: Engineering, Procurement and Construction Agreement

AutoNDA by SimpleDocs

Resolution by Negotiation. (a) As an express condition precedent to commencement of any further proceedings with respect to a Claim (except as may be provided under any applicable lien statute), the Party making such Claim shall notify the other Party's Project Director in writing of such Claim. The Contractor's Project Director and the Owner's Project Director shall meet within thirty (30) Days [**] of receipt of the written notice of such Claim for the purpose of attempting to resolve the Claim. (b) If, after the Contractor's Project Director and the Owner's Project Director meet, the Claim remains unresolved or if no such meeting takes place for any reason within such thirty (30) Day [**] period, then an executive vice president (or equivalent) of (i), in the case of Contractor, each Consortium Member (unless otherwise agreed by the Consortium Members) and (ii), in the case of Owner, each of SCE&G and Santee Xxxxxx Sxxxxx Cxxxxx (unless otherwise agreed by them) shall meet to attempt to resolve such Claim, as applicable, within fifteen (15) Days [**] from the end of such thirty (30) Day [**] period. (c) If the Claim remains unresolved after the fifteen (15) Day [**] period described in Section 27.3(b) and the Parties have not mutually agreed in writing to mediate such Claim, then: (i) with respect to a Claim that exceeds the Threshold Amount, either Party shall have the right to proceed to litigation of such Claim in a court of competent jurisdiction pursuant to Section 27.7[**]; and (ii) with respect to a Claim that meets or falls below the Threshold Amount, such Claim shall be resolved pursuant to Section 27.5.[**] (d) The Parties agree to make a diligent, good faith attempt to resolve a Claim as expeditiously as reasonably possible as provided in this Section 27.3. “[**]” in this Exhibit 10.01 indicates material that has been omitted pursuant to a request for confidential treatment and filed separately with the Securities and Exchange Commission. Execution Version Confidential Trade Secret Information—Subject to Restricted Procedures

Appears in 1 contract

Samples: Engineering, Procurement and Construction Agreement (South Carolina Electric & Gas Co)

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!