Common use of Response to Contractor Questions Clause in Contracts

Response to Contractor Questions. The timeframes for the Design Professional’s responses to requested information shall be no longer than the following: Requests for Information (RFIs) – and Requests for Clarification (RFCs) – seven (7) calendar days.

Appears in 3 contracts

Samples: Master Design Professional Agreement, Master Design Professional Agreement, www.sjeccd.edu

AutoNDA by SimpleDocs

Response to Contractor Questions. The timeframes for the Design Professional’s responses to requested information shall be no longer than the following: Requests for Information (RFIsRFI’s) – and or Requests for Clarification (RFCsRFC’s) – seven five (75) calendar days except in circumstances demonstrated by Design Professional to reasonably require more days.

Appears in 1 contract

Samples: www.sjcc.edu