Schedule Relief. If FM delays the commencement of construction or the occurrence of commercial operation, then the CC Longstop Date, Target COD, and COD Longstop Date will be extended for such reasonable period of delay directly resulting from such FM event. The occurrence of an event of FM which occurs after commercial operation of the facility will not extend the term. •
Appears in 2 contracts
Samples: Renewable Electricity Support Agreement, www.aeso.ca
Schedule Relief. If FM delays the commencement of construction or the occurrence of commercial operation, then the CC Longstop Date, Target COD, and COD Longstop Date will be extended for such reasonable period of delay directly resulting from such FM event. The occurrence of an event of FM which occurs after commercial operation of the facility will not extend the term. •
Appears in 1 contract
Samples: www.aeso.ca
Schedule Relief. If FM delays the commencement of construction or the occurrence of commercial operation, then the CC Longstop Date, Target COD, and COD Longstop Date will be extended for such reasonable period of delay directly resulting from such FM event. The occurrence of an event of FM which occurs after commercial operation of the facility will not extend the term. •.
Appears in 1 contract
Samples: www.aeso.ca