Service Provider Build. 14.1 The Service Provider's Co-location Project Manager will manage the Service Provider Build and keep the LFC informed of progress. 14.2 The Service Provider must complete the Service Provider Build in accordance with its Permit to Work and this Manual and in a good and workmanlike manner. The Service Provider may change the configuration of the Service Provider Build (as detailed in its Service Orders) only if the LFC agrees (whose agreement must not be unreasonably withheld, refused or delayed). 14.3 The LFC's Permit to Work procedure is set out in detail in clause 40. The Service Provider must have an approved Permit to Work before commencing the Service Provider Build.
Appears in 6 contracts
Samples: Ufb Services Agreement, Ufb Services Agreement, Ultrafast Fibre Ufb Services Agreement
Service Provider Build. 14.1 The Service Provider's Co-location Project Manager will manage the Service Provider Build and keep the LFC informed of progress.
14.2 The Service Provider must complete the Service Provider Build in accordance with its Permit to Work and this Manual and in a good and workmanlike manner. The Service Provider may change the configuration of the Service Provider Build (as detailed in its Service Orders) only if the LFC agrees (whose agreement must not be unreasonably withheld, refused or delayed).
14.3 The LFC's Permit to Work procedure is set out in detail in clause 4041. The Service Provider must have an approved Permit to Work before commencing the Service Provider Build.
Appears in 1 contract
Samples: Ufb Services Agreement
Service Provider Build. β
14.1 The Service Provider's Co-location Project Manager will manage the Service Provider Build and keep the LFC informed of progress.
14.2 The Service Provider must complete the Service Provider Build in accordance with its Permit to Work and this Manual and in a good and workmanlike manner. The Service Provider may change the configuration of the Service Provider Build (as detailed in its Service Orders) only if the LFC agrees (whose agreement must not be unreasonably withheld, refused or delayed).
14.3 The LFC's Permit to Work procedure is set out in detail in clause 40. The Service Provider must have an approved Permit to Work before commencing the Service Provider Build.
Appears in 1 contract
Samples: Services Agreement
Service Provider Build. 14.1 The Service Provider's Co-location Project Manager will manage the Service Provider Build and keep the LFC informed of progress.
14.2 The Service Provider must complete the Service Provider Build in accordance with its Permit to Work and this Manual and in a good and workmanlike manner. The Service Provider may change the configuration of the Service Provider Build (as detailed in its Service Orders) only if the LFC agrees (whose which agreement must not be unreasonably withheld, refused or delayed).
14.3 The LFC's Permit to Work procedure is set out in detail in clause 4038. The Service Provider must have an approved Permit to Work before commencing the Service Provider Build.
Appears in 1 contract
Samples: Ufb Services Agreement