Smoke Evacuation Test. a. District Attorney, 300 North Flower and Sheriff’s Forensic, 000 Xxxxx Xxxxxx Xxxxxx, Xxxxx Xxx: (1) The HVAC system shall transfer to the smoke control mode automatically when the fire alarm system is activated. (2) When the HVAC system transfers to the smoke control mode the following sequences of events shall occur: (a) Energize fans SF-1 and SE-1. (b) De-Energize RF-1, RF-2, and SF-2. (c) DE-Energize EF-1, EF-2 and EF-3. (d) Close supply air dampers on all floors. (e) Close return air dampers on all floors. (f) Close smoke exhaust air dampers on all floors. (g) Open smoke exhaust air dampers on involved floor. (h) Open supply air dampers on floor above and below involved floor. b. If any defects are found while testing the supply air dampers, Contractor shall notify the OC Public Works/OCFO Project Manager or designee and complete the repairs of the supply air dampers as soon as possible. c. Maintain a record of each inspection, test, certification and repair. File a copy of the inspection and test document in the log book in the Fire Control Room or as designated by the Building Coordinator of the facility. Submit one copy of the document to OC Public Works/OCFO, to the attention of the Project Manager or designee. In order to receive payment, all of the above requirements must be met. The inspections, general maintenance, test results, repair and certification reports must be submitted with the monthly, quarterly and semi-annual and annual invoice(s) and a work order describing the service and the work order must be signed by the facility contact.
Appears in 2 contracts
Samples: Facility Security Equipment, Systems and Services, Subordinate Contract for Facility Security Equipment, Systems and Services
Smoke Evacuation Test. a. District AttorneyOC Public Works/Headquarters, 300 North Flower and Sheriff’s Forensic, 000 Xxxxx Xxxxxx Xxxxxx, Xxxxx Xxx:
(1) The HVAC system shall transfer to the smoke control mode automatically when the fire alarm system is activated.
(2) When the HVAC system transfers to the smoke control mode the following sequences of events shall occur:
(a) Energize fans SF-1 and SE-1.
(b) De-Energize RF-1, RF-2, and SF-2.
(c) DE-Energize EF-1, EF-2 and EF-3.
(d) Close supply air dampers on all floors.
(e) Close return air dampers on all floors.
(f) Close smoke exhaust air dampers on all floors.
(g) Open smoke exhaust air dampers on involved floor.
(h) Open supply air dampers on floor above and below involved floor.
b. If any defects are found while testing the supply air dampers, Contractor shall notify the OC Public Works/OCFO Project Manager or designee and complete the repairs of the supply air dampers as soon as possible.
c. Maintain a record of each inspection, test, certification and repair. File a copy of the inspection and test document in the log book in the Fire Control Room or as designated by the Building Coordinator of the facility. Submit one copy of the document to OC Public Works/OCFO, to the attention of the Project Manager or designee. In order to receive payment, all of the above requirements must be met. The inspections, general maintenance, test results, repair and certification reports must be submitted with the monthly, quarterly and semi-annual and annual invoice(s) and a work order describing the service and the work order must be signed by the facility contact.
Appears in 1 contract
Smoke Evacuation Test. a. District AttorneyOC Public Works/Headquarters, 300 North Flower and Sheriff’s ForensicForensi c, 000 Xxxxx Xxxxxx Xxxxxx, Xxxxx Xxx:
(1) The HVAC system shall transfer to the smoke control mode automatically when the fire alarm system is activated.
(2) When the HVAC system transfers to the smoke control mode the following sequences of events shall occur:
(a) Energize fans SF-1 and SE-1.
(b) De-Energize RF-1, RF-2, and SF-2.
(c) DE-Energize EF-1, EF-2 and EF-3.
(d) Close supply air dampers on all floors.
(e) Close return air dampers on all floors.
(f) Close smoke exhaust air dampers on all floors.
(g) Open smoke exhaust air dampers on involved floor.
(h) Open supply air dampers on floor above and below involved floor.
b. If any defects are found while testing the supply air dampers, Contractor shall notify the OC Public Works/OCFO Project Manager or designee and complete the repairs of the supply air dampers as soon as possible.
c. Maintain a record of each inspection, test, certification and repair. File a copy of the inspection and test document in the log book in the Fire Control Room or as designated by the Building Coordinator of the facility. Submit one copy of the document to OC Public Works/OCFO, to the attention of the Project Manager or designee. In order to receive payment, all of the above requirements must be met. The inspections, general maintenance, test results, repair and certification reports must be submitted with the monthly, quarterly and semi-annual and annual invoice(s) and a work order describing the service and the work order must be signed by the facility contact.
Appears in 1 contract
Samples: Subordinate Contract for Facility Security Equipment, Systems and Services