SUBLETTING OF CONTRACT. (11-18-2014) 108-6 SP1 G186 Revise the 2012 Standard Specifications as follows: All requests to sublet work shall be submitted within 30 days of the date of availability or prior to expiration of 20% of the contract time, whichever date is later, unless otherwise approved by the Engineer. Purchasing materials for subcontractors is not included in the percentage of work required to be performed by the Contractor. If the Contractor sublets items of work but elects to purchase material for the subcontractor, the value of the material purchased will be included in the total dollar amount considered to have been sublet.
Appears in 47 contracts
Samples: Roadway Contract, Roadway Contract, Roadway Contract