Submittals Not Subject to Prior Review, Comment or Approval. Whenever the PPA Documents indicate that Developer is to deliver a Submittal to IFA but express no requirement for IFA review, comment, disapproval, prior approval or other IFA action, then Developer is under no obligation to provide IFA any period of time to review the Submittal or obtain approval of it before proceeding with further Work, and IFA shall have the right, but is not obligated, to at any time review, comment on, take exception to, object to, reject or disapprove the Submittal in accordance with Section 3.1. 7.1. No failure or delay by IFA in delivering comments, exceptions, objections, rejections or disapprovals with respect to the Submittal shall constitute an IFA-Caused Delay, IFA Change, Relief Event or other basis for any Claim.
Appears in 7 contracts
Samples: Public Private Agreement, Public Private Agreement, Public Private Agreement