Subsequent Storage Capacity Tests Clause Samples

The "Subsequent Storage Capacity Tests" clause establishes the procedures and requirements for conducting additional tests to verify the storage capacity of a facility or system after initial commissioning. Typically, this clause outlines when and how these follow-up tests should be performed, who is responsible for conducting them, and the standards or benchmarks that must be met. For example, it may require periodic testing at set intervals or after certain events, such as repairs or upgrades. The core function of this clause is to ensure ongoing compliance with capacity requirements, thereby maintaining operational reliability and addressing any potential degradation or changes in storage performance over time.
Subsequent Storage Capacity Tests. Following the Commercial Operation Date, once each Contract Year Seller will perform a Storage Capacity Test and will give Buyer ten (10) Business Days prior Notice of such test. At least twice per Contract Year, Buyer shall have the right to require Seller to schedule and complete a Storage Capacity Test. In addition, Buyer shall have the right to require a test or retest of the Storage Capacity Test at any time upon no less than five (5) Business Days prior written Notice to Seller if Buyer provides data with such Notice reasonably indicating that the Storage Capacity has varied materially from the results of the most recent Storage Capacity Test. Seller shall have the right to run a retest of any Storage Capacity Test upon five (5) Business Days’ prior written Notice to Buyer (or any shorter period reasonably acceptable to Buyer consistent with Prudent Operating Practice).
Subsequent Storage Capacity Tests. Following the Commercial Operation Date, but not more than once per Contract Year, upon no less than ten (10) Business DaysNotice to Seller, Buyer shall have the right to require Seller to schedule and complete a Storage Capacity Test and to update the Storage Facility’s PMax and other relevant information and values in the CAISO’s Master Data File and Resource Data Template (or successor data systems). In addition, Buyer shall have the right to require a retest of the most recent Storage Capacity Test (and to update the Storage Facility’s PMax and other relevant information and values as specified above) at any time upon no less than five (5) Business Days prior written Notice to Seller if Buyer provides data with such Notice reasonably indicating that the Storage Capacity has varied materially from the results of the most recent Storage Capacity Test or any other guaranteed operational characteristics are not being met. Seller shall have the right to perform a Storage Capacity Test or run a retest of any Storage Capacity Test at any time during any Contract Year upon five (5) Business Days’ prior written Notice to Buyer (or any shorter period reasonably acceptable to Buyer consistent with Prudent Operating Practice).
Subsequent Storage Capacity Tests. Following the Commercial Operation Storage Capacity Test(s), at least fifteen (15) days in advance of the start of each Contract Year, upon no less than ten (10) Business Days prior Notice to Buyer, Seller shall schedule and complete a Storage Capacity Test. In addition, Buyer shall have the right to require a retest of the Storage Capacity Test at any time upon no less than five (5) Business Days prior Notice to Seller if Buyer provides data with such Notice reasonably indicating that the then-current Contract Capacity has varied materially from the results of the most recent prior Storage Capacity Test. Seller shall have the right to run retests of any Storage Capacity Test at any time upon five (5) Business Days’ prior Notice to Buyer (or any shorter period reasonably acceptable to Buyer consistent with Prudent Operating Practice).