Temporary Plant Roads Within Contractor's Area. The construction/installation area will be constructed and maintained by Contractor. All roads constructed by Contractor shall be adequate for applied traffic loads and to prevent damage to underground facilities. All temporary roads are to be removed prior to "Final Acceptance," unless Owner or Owner’s Representative directs them to be retained.
Appears in 3 contracts
Samples: Master Equipment Agreement, Master Equipment Agreement, Master Equipment Agreement
Temporary Plant Roads Within Contractor's Area. The construction/installation construction area will be constructed and maintained by Contractor. All roads constructed by Contractor shall be adequate for applied traffic loads and to prevent damage to underground facilities. All temporary roads are to be removed prior to "Final Acceptance," unless Owner or Owner’s 's Representative directs them to be retained.
Appears in 2 contracts
Samples: Master Construction Agreement, Master Construction Agreement