Temporary Supports, Structures and Facilities. (a) Project Co shall have the sole responsibility for the design, erection, operation, maintenance, and removal of temporary supports, structures, and facilities and the design and execution of construction methods required in their use. Any review of Project Co’s temporary supports, structures, or facilities or any shop drawings related thereto by Owner or Consultant does not relieve Project Co of its “sole responsibility” under this section. (b) Project Co shall engage registered professional engineering personnel skilled in the appropriate disciplines to perform those functions referred to in Section 11.20(a) where required by law or by the Contract Documents and in all cases, where such temporary supports, structures, and facilities and their method of construction are of such a nature that professional engineering skill is required to produce safe and satisfactory results. (c) Subject to Section 11.17, but notwithstanding the provisions of Sections 11.2, 11.20(a) and 11.20(b) or provisions to the contrary elsewhere in the Contract Documents, where such Contract Documents include designs for temporary supports, structures and facilities or specify a method of construction in whole or in part, such facilities and methods shall be considered to be part of the design of the Work and Project Co shall not be held responsible for that part of the design or the specified method of construction. Project Co shall, however, be responsible for the execution of such design or specified method of construction in the same manner as for the execution of the Work.
Appears in 7 contracts
Samples: Project Agreement, Project Agreement, Project Agreement
Temporary Supports, Structures and Facilities. (a) Project Co shall have the sole responsibility for the design, erection, operation, maintenance, and removal of temporary supports, structures, and facilities and the design and execution of construction methods required in their use. Any review of Project Co’s Co‟s temporary supports, structures, or facilities or any shop drawings related thereto by Owner or Consultant does not relieve Project Co of its “sole responsibility” under this section.
(b) Project Co shall engage registered professional engineering personnel skilled in the appropriate disciplines to perform those functions referred to in Section 11.20(a) where required by law or by the Contract Documents and in all cases, where such temporary supports, structures, and facilities and their method of construction are of such a nature that professional engineering skill is required to produce safe and satisfactory results.
(c) Subject to Section 11.17, but notwithstanding the provisions of Sections 11.2, 11.20(a) and 11.20(b) or provisions to the contrary elsewhere in the Contract Documents, where such Contract Documents include designs for temporary supports, structures and facilities or specify a method of construction in whole or in part, such facilities and methods shall be considered to be part of the design of the Work and Project Co shall not be held responsible for that part of the design or the specified method of construction. Project Co shall, however, be responsible for the execution of such design or specified method of construction in the same manner as for the execution of the Work.
Appears in 1 contract
Samples: Project Agreement
Temporary Supports, Structures and Facilities. (a) Project Co shall have the sole responsibility for the design, erection, operation, maintenance, and removal of temporary supports, structures, and facilities and the design and execution of construction methods required in their use. Any review of Project Co’s temporary supports, structures, or facilities or any shop drawings related thereto by Owner STEGH or Consultant does not relieve Project Co of its “sole responsibility” under this section.section.
(b) Project Co shall engage registered professional engineering personnel skilled in the appropriate disciplines to perform those functions referred to in Section 11.20(a) where required by law or by the Contract Documents and in all cases, where such temporary supports, structures, and facilities and their method method of construction are of such a nature that professional engineering skill is required to produce safe and satisfactory results.
(c) Subject to Section 11.17, but notwithstanding the provisions of Sections 11.2, 11.20(a) and 11.20(b) or provisions to the contrary elsewhere in the Contract Documents, where such Contract Documents include designs for temporary supports, structures and facilities or specify a method of construction in whole or in part, such facilities and methods shall be considered to be part of the design of the Work and Project Co shall not be held responsible for that part of the design or the specified method of construction. Project Co shall, however, be responsible for the execution of such design or specified method of construction in the same manner as for the execution of the Work.
Appears in 1 contract
Samples: Project Agreement
Temporary Supports, Structures and Facilities.
(a) Project Co shall have the sole responsibility for the design, erection, operation, maintenance, and removal of temporary supports, structures, and facilities and the design and execution of construction methods required in their use. Any review of Project Co’s temporary supports, structures, or facilities or any shop drawings drawings related thereto by Owner Contracting Authority or Consultant does not relieve Project Co of its “sole responsibility” under this section.
(b) Project Co shall engage registered professional engineering personnel skilled in the appropriate disciplines to perform those functions referred to in Section 11.20(a) where required by law or by the Contract Documents and in all cases, where such temporary supports, structures, and facilities and their method of construction are of such a nature that professional engineering skill is required to produce safe and satisfactory results.results.
(c) Subject to Section 11.17Sections 11.31-11.36, but notwithstanding the provisions of Sections 11.2, 11.20(a) and 11.20(b) or provisions to the contrary elsewhere in the Contract Documents, where such Contract Documents include designs for temporary supports, structures and facilities or specify a method of construction in whole or in part, such facilities and methods shall be considered to be part of the design of the Work and Project Co shall not be held responsible for that part of the design or the specified method of construction. Project Co shall, however, be responsible for the execution of such design or specified method of construction in the same manner as for the execution of the Work.
Appears in 1 contract
Samples: Project Agreement
Temporary Supports, Structures and Facilities. (a) Project Co shall have the sole responsibility for the design, erection, operation, maintenance, and removal of temporary supports, structures, and facilities and the design and execution of construction methods required in their use. Any review of Project Co’s temporary supports, structures, or facilities or any shop drawings related thereto by Owner CHH or Consultant does not relieve Project Co of its “sole responsibility” under this section.
(b) Project Co shall engage registered professional engineering personnel skilled in the appropriate disciplines to perform those functions referred to in Section 11.20(a) where required by law or by the Contract Documents and in all cases, where such temporary supports, structures, and facilities and their method of construction are of such a nature that professional engineering skill is required to produce safe and satisfactory results.
(c) Subject to Section 11.17, but notwithstanding the provisions of Sections 11.2, 11.20(a) and 11.20(b) or provisions to the contrary elsewhere in the Contract Documents, where such Contract Documents include designs for temporary supports, structures and facilities or specify a method of construction in whole or in part, such facilities and methods shall be considered to be part of the design of the Work and Project Co shall not be held responsible for that part of the design or the specified method of construction. Project Co shall, however, be responsible for the execution of such design or specified method of construction in the same manner as for the execution of the Work.
Appears in 1 contract
Samples: Project Agreement
Temporary Supports, Structures and Facilities. (a) Project Co shall have the sole responsibility for the design, erection, operation, maintenance, and removal of temporary supports, structures, and facilities and the design and execution of construction methods required in their use. Any review of Project Co’s temporary supports, structures, or facilities or any shop drawings related thereto by Owner HMQ or Consultant does not relieve Project Co of its “sole responsibility” under this section.
(b) Project Co shall engage registered professional engineering personnel skilled in the appropriate disciplines to perform those functions referred to in Section 11.20(a) where required by law or by the Contract Documents and in all cases, where such temporary supports, structures, and facilities and their method of construction are of such a nature that professional engineering skill is required to produce safe and satisfactory results.
(c) Subject to Section 11.17, but notwithstanding the provisions of Sections 11.2, 11.20(a) and 11.20(b) or provisions to the contrary elsewhere in the Contract Documents, where such Contract Documents include designs for temporary supports, structures and facilities or specify a method of construction in whole or in part, such facilities and methods shall be considered to be part of the design of the Work and Project Co shall not be held responsible for that part of the design or the specified method of construction. Project Co shall, however, be responsible for the execution of such design or specified method of construction in the same manner as for the execution of the Work.
Appears in 1 contract
Samples: Project Agreement
Temporary Supports, Structures and Facilities. (a) Project Co shall have the sole responsibility for the design, erection, operation, maintenance, and removal of temporary supports, structures, and facilities and the design and execution of construction methods required in their use. Any review of Project Co’s temporary supports, structures, or facilities or any shop drawings related thereto by Owner HMQ or Consultant HMQ Representative does not relieve Project Co of its “sole responsibility” under this section.
(b) Project Co shall engage registered professional engineering personnel skilled in the appropriate disciplines to perform those functions referred to in Section 11.20(a11.26(a) where required by law or by the Contract Documents and in all cases, where such temporary supports, structures, and facilities and their method of construction are of such a nature that professional engineering skill is required to produce safe and satisfactory results.
(c) Subject to Section 11.17, but notwithstanding Notwithstanding the provisions of Sections 11.211.11, 11.20(a11.26(a) and 11.20(b11.26(b) or provisions to the contrary elsewhere in the Contract Documents, where such Contract Documents include designs for temporary supports, structures and facilities or specify a method of construction in whole or in part, such facilities and methods shall be considered to be part of the design of the Work Works and Project Co shall not be held responsible for that part of the design or the specified method of construction. Project Co shall, however, be responsible for the execution of such design or specified method of construction in the same manner as for the execution of the WorkWorks.
Appears in 1 contract
Samples: Project Agreement
Temporary Supports, Structures and Facilities. (a) Project Co shall have the sole responsibility for the design, erection, operation, maintenance, and removal of temporary supports, structures, and facilities and the design and execution of construction methods required in their use. Any review of Project Co’s temporary supports, structures, or facilities or any shop drawings related thereto by Owner CMH or Consultant does not relieve Project Co of its “sole responsibility” under this sectionSection 11.20.
(b) Project Co shall engage registered professional engineering personnel skilled in the appropriate disciplines to perform those functions referred to in Section 11.20(a) where required by law or by the Contract Documents and in all cases, where such temporary supports, structures, and facilities and their method of construction are of such a nature that professional engineering skill is required to produce safe and satisfactory results.
(c) Subject to Section 11.17, but notwithstanding the provisions of Sections 11.2, 11.20(a) and 11.20(b) or provisions to the contrary elsewhere in the Contract Documents, where such Contract Documents include designs for temporary supports, structures and facilities or specify a method of construction in whole or in part, such facilities and methods shall be considered to be part of the design of the Work and Project Co shall not be held responsible for that part of the design or the specified method of construction. Project Co shall, however, be responsible for the execution of such design or specified method of construction in the same manner as for the execution of the Work.
Appears in 1 contract
Samples: Project Agreement
Temporary Supports, Structures and Facilities. (a) Project Co shall have the sole responsibility for the design, erection, operation, maintenance, and removal of temporary supports, structures, and facilities and the design and execution of construction methods required in their use. Any review of Project Co’s temporary supports, structures, or facilities or any shop drawings related thereto by Owner THP or Consultant does not relieve Project Co of its “sole responsibility” under this section.section.
(b) Project Co shall engage registered professional engineering personnel skilled in the appropriate disciplines to perform those functions referred to in Section 11.20(a) where required by law or by the Contract Documents and in all cases, where such temporary supports, structures, and facilities and their method of construction are of such a nature that professional engineering skill is required to produce safe and satisfactory results.results.
(c) Subject to Section 11.17, but notwithstanding the provisions of Sections 11.2, 11.20(a) and 11.20(b) or provisions to the contrary elsewhere in the Contract Documents, where such Contract Documents include designs for temporary supports, structures and facilities or specify a method of construction in whole or in part, such facilities and methods shall be considered to be part of the design of the Work and Project Co shall not be held responsible for that part of the design or the specified method of construction. Project Co shall, however, be responsible for the execution of such design or specified method of construction in the same manner as for the execution of the Work.
Appears in 1 contract
Samples: Project Agreement