Common use of Termination for Extended Delay Clause in Contracts

Termination for Extended Delay. Buyer may terminate this Agreement with regard to a Unit if the Commercial Operations Date for such Unit is not achieved by June 1, 2002, except to the extent such delay is caused by a Force Majeure Event, in which case such termination date shall be extended by the Force Majeure Period, but in no event beyond June 1, 2003 (provided, however, that Buyer may terminate this Agreement following a Force Majeure Period lasting twelve months or more, unless Seller closes on financing for the Facility by May 31, 2002). If this Agreement is terminated with regard to a Unit(s) pursuant to this Section 3.3.7 for failure to achieve the Commercial Operations Date by June 1, 2002, (i) Buyer's sole remedy for damages and Seller's sole liability for damages shall be for Buyer to offset Delay LDs against Capacity Charges accrued and not paid to Seller prior to termination and to receive the Default Rate of interest on Delay LDs accrued in excess of Capacity Charges due at any given time until such Delay LDs are received by Buyer through offsets against Capacity Charges and (ii) Seller shall have no obligation to pay Delay LDs accrued during any Commercial Operations Delay Period except as an offset against Capacity Charges due from Buyer. If this Agreement is terminated pursuant to this Section 3.3.7, neither Party shall have any liability to the other Party whatsoever (including liability for previously accrued Delay LDs or Capacity Charges, but excluding liability in respect of Delay Book Out Charges and interest accrued on the DLD Escrow at the Default Rate).

Appears in 2 contracts

Samples: Power Sales Agreement (Aquila Inc), Power Sales Agreement (Aquila Inc)

AutoNDA by SimpleDocs

Termination for Extended Delay. Buyer may terminate this ------------------------------ Agreement with regard to a Unit if the Commercial Operations Date for such Unit is not achieved by June 1, 2002, except to the extent such delay is caused by a Force Majeure Event, in which case such termination date shall be extended by the Force Majeure Period, but in no event beyond June 1, 2003 (provided, however, that Buyer may terminate this Agreement following -------- ------- a Force Majeure Period lasting twelve months or more, unless Seller closes on financing for the Facility by May 31, 2002). If this Agreement is terminated with regard to a Unit(s) pursuant to this Section 3.3.7 for failure to achieve the Commercial Operations Date by June 1, 2002, (i) Buyer's sole remedy for damages and Seller's sole liability for damages shall be for Buyer to offset Delay LDs against Capacity Charges accrued and not paid to Seller prior to termination and to receive the Default Rate of interest on Delay LDs accrued in excess of Capacity Charges due at any given time until such Delay LDs are received by Buyer through offsets against Capacity Charges and (ii) Seller shall have no obligation to pay Delay LDs accrued during any Commercial Operations Delay Period except as an offset against Capacity Charges due from Buyer. If this Agreement is terminated pursuant to this Section 3.3.7, neither Party shall have any liability to the other Party whatsoever (including liability for previously accrued Delay LDs or Capacity Charges, but excluding liability in respect of Delay Book Out Charges and interest accrued on the DLD Escrow at the Default Rate).

Appears in 2 contracts

Samples: Power Sales Agreement (Dominion Resources Inc /Va/), Power Sales Agreement (Dominion Resources Inc /Va/)

AutoNDA by SimpleDocs
Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!