Tested Duration Energy Performance Test Sample Clauses

Tested Duration Energy Performance Test. Test Limits Parameter Description Cmax Set-point for power delivered to the Electric Revenue Meter during the Design Charge Duration of the Performance Test; value from the latest Performance Test or as specified by Seller before the Performance Test; not to exceed Design Cmax. Design Cmax Appendix II Design Charge Duration Appendix II Dmax Set-point for power delivered to the Electric Revenue Meter during the Design Dmax Duration of the Performance Test; value from the latest Performance Test or as specified by Seller before the Performance Test. Output must remain within +/-2% of Dmax to be considered steady state. Design Dmax Appendix II Design Dmax Duration Appendix II Measured Outputs Parameter Description State of Charge (SOC) As measured in normal operations. Delivered Discharge Energy Measured by the Electric Revenue Meter as reported in the CAISO Operational Meter Analysis and Reporting (“OMAR”) output for the shortest available reporting interval (5 minutes as of July 2015). Calculated Results Parameter Description
AutoNDA by SimpleDocs

Related to Tested Duration Energy Performance Test

  • Acceptance/Performance Test 4.7.1 Prior to synchronization of the Power Project, the SPD shall be required to get the Project certified for the requisite acceptance/performance test as may be laid down by Central Electricity Authority or an agency identified by the central government to carry out testing and certification for the solar power projects.

  • Performance Testing 7.2.1 The Design-Builder shall direct and supervise the tests and, if necessary, the retests of the Plant using Design-Builder’s supervisory personnel and the Air Emissions Tester shall conduct the air emissions test, in each case, in accordance with the testing procedures set forth in Exhibit A (the “Performance Tests”), to demonstrate, at a minimum, compliance with the Performance Guarantee Criteria. Owner is responsible for obtaining Air Emissions Tester and for ensuring Air Emissions Tester’s timely performance. Design-Builder shall cooperate with the Air Emissions Tester to facilitate performance of all air emissions tests. Design-Builder shall not be held responsible for the actions of Owner’s employees and third parties involved in the Performance Testing, including but not limited to Air Emissions Tester.

  • CONTRACTOR PERFORMANCE AUDIT The Contractor shall allow the Authorized User to assess Contractor’s performance by providing any materials requested in the Authorized User Agreement (e.g., page load times, response times, uptime, and fail over time). The Authorized User may perform this Contractor performance audit with a third party at its discretion, at the Authorized User’s expense. The Contractor shall perform an independent audit of its Data Centers, at least annually, at Contractor expense. The Contractor will provide a data owner facing audit report upon request by the Authorized User. The Contractor shall identify any confidential, trade secret, or proprietary information in accordance with Appendix B, Section 9(a), Confidential/Trade Secret Materials.

  • Ongoing Performance Measures The Department intends to use performance-reporting tools in order to measure the performance of Contractor(s). These tools will include the Contractor Performance Survey (Exhibit H), to be completed by Customers on a quarterly basis. Such measures will allow the Department to better track Vendor performance through the term of the Contract(s) and ensure that Contractor(s) consistently provide quality services to the State and its Customers. The Department reserves the right to modify the Contractor Performance Survey document and introduce additional performance-reporting tools as they are developed, including online tools (e.g. tools within MFMP or on the Department's website).

  • OUTCOME IF GRANTEE CANNOT COMPLETE REQUIRED PERFORMANCE Unless otherwise specified in this Statement of Work, if Grantee cannot complete or otherwise comply with a requirement included in this Statement of Work, HHSC, at its sole discretion, may impose remedies or sanctions outlined under Contract Attachment C, Local Mental Health Authority Special Conditions, Section 7.09 (Remedies and Sanctions).

  • Criteria for Performance Assessment A. A teacher’s performance shall be assessed based on the criteria set forth in the evaluation instrument, Appendix D.

  • Quarterly Contractor Performance Reporting Customers shall complete a Contractor Performance Survey (Exhibit I) for each Contractor on a Quarterly basis. Customers will electronically submit the completed Contractor Performance Survey(s) to the Department Contract Manager no later than the due date indicated in Contract Exhibit D, Section 17, Additional Special Contract Conditions. The completed Contractor Performance Survey(s) will be used by the Department as a performance-reporting tool to measure the performance of Contractors. The Department reserves the right to modify the Contractor Performance Survey document and introduce additional performance-reporting tools as they are developed, including online tools (e.g. tools within MyFloridaMarketPlace or on the Department's website).

  • PERFORMANCE OUTCOMES 8 A. CONTRACTOR shall achieve performance objectives, tracking and reporting Performance 9 Outcome Objective statistics in monthly programmatic reports, as appropriate. ADMINISTRATOR 10 recognizes that alterations may be necessary to the following services to meet the objectives, and,

  • Performance Measurement Satisfactory performance of this Contract will be measured by:

  • Performance Levels (a) The Performance Levels which apply to the performance by the respective Parties of their obligations under this Agreement are set out in Part 1 of Schedule 5. A failure by either Party to achieve the relevant Performance Level will not constitute a breach of this Agreement and the only consequences of such failure as between the Parties shall be the consequences set out in this Clause 5.6.