The Company Covenants. The Company hereby covenants to and agrees with BPDB to: (a) Until Construction Start Date, the Company shall obtain all necessary financing in an amount sufficient for the construction, completion, operation and maintenance of the Project in the manner contemplated by this Contract. (b) Until Construction Start Date, use all reasonable efforts to negotiate and execute the contracts with the Contractor(s) that will perform the Project’s engineering, procurement and construction and the Financing Documents; (c) Work with and cooperate in good faith with BPDB with respect to all of BPDB’s obligations and rights hereunder; (d) Design, engineer, construct, complete, own and operate the Project in accordance with (i) the plans and specifications prepared in accordance with this Contract, (ii) the Contracted Operating Characteristics set forth in Schedule 1. (iii) all Laws of Bangladesh, (e) Design, construct and complete the Project in a manner which is suitable for the intended purpose, only with materials and equipment that are new and of international utility-grade quality, in such a manner as to provide a reasonable likelihood, with proper maintenance and Operation, that the useful life of the Project will be at least equal to the Term; (f) All equipments related to the facility (Solar PV Panels, Inverter & Metering equipments) will be tested at the manufacturer's premises following manufacture. Any reasonable costs of such a visit shall be borne by the Company. (g) Provide the electrical Interconnection between the Project and Baraiyarhat 132/33 kV grid substation system as per PGCB's guideline. (h) Provide at its own risk and expense the necessary facilities and services for the safety, comfort and protection of its personnel; (i) After Commercial Operation Date, operate and maintain the Project, in accordance with: (i) Prudent Utility Practices, (ii) the operating procedures developed pursuant to Section 6.3 and the Dispatch Instructions, and (iii) the Technical Limits set forth in Schedule 2. by the laws of Bangladesh, and to be responsible for the disposal and treatment of waste in connection with the Project.
Appears in 1 contract
Samples: Power Purchase Agreement
The Company Covenants. The Company hereby covenants to and agrees with BPDB to:
(a) Until Construction Start Date, the Company shall obtain all necessary financing in an amount sufficient for the construction, completion, operation and maintenance of the Project in the manner contemplated by this Contract.
(b) Until Construction Start Date, use all reasonable efforts to negotiate and execute the contracts with the Contractor(s) that will perform the Project’s engineering, procurement and construction and the Financing Documents;
(c) Work with and cooperate in good faith with BPDB with respect to all of BPDB’s obligations and rights hereunder;
(d) Design, engineer, construct, complete, own and operate the Project in accordance with
(i) the plans and specifications prepared in accordance with this Contract,
(ii) the Contracted Operating Characteristics set forth in Schedule 1.
(iii) all Laws of Bangladesh,
(e) Design, construct and complete the Project in a manner which is suitable for the intended purpose, only with materials and equipment that are new and of international utility-grade quality, in such a manner as to provide a reasonable likelihood, with proper maintenance and Operation, that the useful life of the Project will be at least equal to the Term;
(f) All equipments related to the facility (Solar PV Panels, Inverter & Metering equipments) will be tested at the manufacturer's premises following manufacture. Any reasonable costs of such a visit shall be borne by the Company.
(g) Provide the electrical Interconnection between the Project and Baraiyarhat Bhaluka 132/33 kV grid substation system as per PGCB's guideline.
(h) Provide at its own risk and expense the necessary facilities and services for the safety, comfort and protection of its personnel;
(i) After Commercial Operation Date, operate and maintain the Project, in accordance with:
(i) Prudent Utility Practices,
(ii) the operating procedures developed pursuant to Section 6.3 and the Dispatch Instructions, and
(iii) the Technical Limits set forth in Schedule 2. .
(j) Be responsible at its own risk and expense for ensuring that the construction and operation of the Project complies with all environmental and safety regulations mandated by the laws of Bangladesh, and to be responsible for the disposal and treatment of waste in connection with the Project.
Appears in 1 contract
Samples: Power Purchase Agreement
The Company Covenants. The Company hereby covenants to and agrees with BPDB to:
(a) Until Construction Start Date, the Company shall obtain all necessary financing in an amount sufficient for the construction, completion, operation and maintenance of the Project in the manner contemplated by this Contract.
(b) Until Construction Start Date, use all reasonable efforts to negotiate and execute the contracts with the Contractor(s) that will perform the Project’s engineering, procurement and construction and the Financing Documents;
(c) Work with and cooperate in good faith with BPDB with respect to all of BPDB’s obligations and rights hereunder;
(d) Design, engineer, construct, complete, own and operate the Project in accordance with
(i) the plans and specifications prepared in accordance with this Contract,
(ii) the Contracted Operating Characteristics set forth in Schedule 1.
(iii) all Laws of Bangladesh,
(e) Design, construct and complete the Project in a manner which is suitable for the intended purpose, only with materials and equipment that are new and of international utility-grade quality, in such a manner as to provide a reasonable likelihood, with proper maintenance and Operation, that the useful life of the Project will be at least equal to the Term;
(f) All equipments related to the facility (Solar PV Panels, Inverter & Metering equipments) will be tested at the manufacturer's premises following manufacturemanufacture pursuant to Section 12 & Schedule 1. Any reasonable All costs of such a visit test shall be borne by the Company.
(g) Provide the electrical Interconnection between the Project and Baraiyarhat Chandraghona 132/33 kV grid substation system as per PGCB's guideline.
(h) Provide at its own risk and expense the necessary facilities and services for the safety, comfort and protection of its personnel;
(i) After Commercial Operation Date, operate and maintain the Project, in accordance with:
(i) Prudent Utility Practices,
(ii) the operating procedures developed pursuant to Section 6.3 and the Dispatch Instructions, and
(iii) the Technical Limits set forth in Schedule 2. .
(j) Be responsible at its own risk and expense for ensuring that the construction and operation of the Project complies with all environmental and safety regulations mandated by the laws of Bangladesh, and to be responsible for the disposal and treatment of waste in connection with the Project.
Appears in 1 contract
Samples: Power Purchase Agreement
The Company Covenants. The Company hereby covenants to and agrees with BPDB to:
(a) Until Construction Start Date, the Company shall obtain all necessary financing in an amount sufficient for the construction, completion, operation and maintenance of the Project in the manner contemplated by this Contract.
(b) Until Construction Start Date, use all reasonable efforts to negotiate and execute the contracts with the Contractor(s) that will perform the Project’s engineering, procurement and construction and the Financing Documents;
(c) Work with and cooperate in good faith with BPDB with respect to all of BPDB’s obligations and rights hereunder;
(d) Design, engineer, construct, complete, own and operate the Project in accordance with
(i) the plans and specifications prepared in accordance with this Contract,
(ii) the Contracted Operating Characteristics set forth in Schedule 1.
(iii) all Laws of Bangladesh,
(e) Design, construct and complete the Project in a manner which is suitable for the intended purpose, only with materials and equipment that are new and of international utility-grade quality, in such a manner as to provide a reasonable likelihood, with proper maintenance and Operation, that the useful life of the Project will be at least equal to the Term;
(f) All equipments related to the facility (Solar PV Panels, Inverter & Metering equipments) will be tested at the manufacturer's premises following manufacture. Any reasonable costs of such a visit shall be borne by the Company.
(g) Provide the electrical Interconnection between the Project and Baraiyarhat Chuadanga 132/33 kV grid substation system as per PGCB's guideline.
(h) Provide at its own risk and expense the necessary facilities and services for the safety, comfort and protection of its personnel;
(i) After Commercial Operation Date, operate and maintain the Project, in accordance with:
(i) Prudent Utility Practices,
(ii) the operating procedures developed pursuant to Section 6.3 and the Dispatch Instructions, and
(iii) the Technical Limits set forth in Schedule 2. .
(j) Be responsible at its own risk and expense for ensuring that the construction and operation of the Project complies with all environmental and safety regulations mandated by the laws of Bangladesh, and to be responsible for the disposal and treatment of waste in connection with the Project.
Appears in 1 contract
Samples: Power Purchase Agreement
The Company Covenants. The Company hereby covenants to and agrees with BPDB to:
(a) Until Construction Start Date, the The Company shall obtain all necessary financing in an amount sufficient for the construction, completion, operation and maintenance of the Project in the manner contemplated by this Contract.
(b) Until Construction Start Date, use all reasonable efforts to negotiate and execute the contracts with the Contractor(s) that will perform the Project’s engineering, procurement and construction and the Financing Documents;
(c) Work with and cooperate in good faith with BPDB with respect to all of BPDBEntity’s obligations and rights hereunder;
(d) Design, engineer, construct, complete, own and operate the Project in accordance with
(i) the plans and specifications prepared in accordance with this Contract,
(ii) the Contracted Operating Characteristics set forth in Schedule 12.
(iii) all Laws of Bangladesh,
(e) Design, construct and complete the Project in a manner which is suitable for the intended purpose, only with materials and equipment that are new or old and of international utility-grade quality, in such a manner as to provide a reasonable likelihood, with proper maintenance and Operation, that the useful life of the Project will be at least equal to the Term;
(f) All equipments related to Provide the facility (Solar PV Panels, Inverter & Metering equipments) will be tested at electrical Interconnection Project between the manufacturerProject and Entity's premises following manufacture. Any reasonable costs of such a visit shall be borne by the Company0.4kV or 0.23kV grid system as per Entity's instruction.
(g) Provide the electrical Interconnection between the Project and Baraiyarhat 132/33 kV grid substation system as per PGCB's guideline.
(h) Provide at its own risk and expense the necessary facilities and services for the safety, comfort and protection of its personnel;
(ih) After Commercial Operation Date, operate and maintain the Project, in accordance with:
(i) Prudent Utility Practices,
(ii) the operating procedures developed pursuant to Section 6.3 Article 6.4 and the Dispatch Instructions, and
(iii) the Technical Limits set forth in Schedule 2. .
(i) Be responsible at its own risk and expense for ensuring that the construction and operation of the Project complies with all environmental and safety regulations mandated by the laws The Laws of Bangladesh, and to be responsible for the disposal and treatment of waste in connection with the Project.
Appears in 1 contract
Samples: Power Purchase Agreement
The Company Covenants. The Company hereby covenants to and agrees with BPDB to:
(a) Until Construction Start Date, the Company shall obtain all necessary financing in an amount sufficient for the construction, completion, operation and maintenance of the Project in the manner contemplated by this Contract.
(b) Until Construction Start Date, use all reasonable efforts to negotiate and execute the contracts with the Contractor(s) that will perform the Project’s engineering, procurement and construction and the Financing Documents;
(c) Work with and cooperate in good faith with BPDB with respect to all of BPDB’s obligations and rights hereunder;
(d) Design, engineer, construct, complete, own and operate the Project in accordance with
(i) the plans and specifications prepared in accordance with this Contract,
(ii) the Contracted Operating Characteristics set forth in Schedule 1.
(iii) all Laws of Bangladesh,
(e) Design, construct and complete the Project in a manner which is suitable for the intended purpose, only with materials and equipment that are new and of international utility-grade quality, in such a manner as to provide a reasonable likelihood, with proper maintenance and Operation, that the useful life of the Project will be at least equal to the Term;
(f) All equipments related to the facility (Solar PV Panels, Inverter & Metering equipments) will be tested at the manufacturer's premises following manufacturemanufacture pursuant to Section 12 & Schedule 1. Any reasonable All costs of such a visit test shall be borne by the Company.
(g) Provide the electrical Interconnection between the Project and Baraiyarhat Chuadanga 132/33 kV grid substation KV Grid Substation system as per PGCBBPDB's guideline.
(h) Provide at its own risk and expense the necessary facilities and services for the safety, comfort and protection of its personnel;
(i) After Commercial Operation Date, operate and maintain the Project, in accordance with:
(i) Prudent Utility Practices,
(ii) the operating procedures developed pursuant to Section 6.3 and the Dispatch Instructions, and
(iii) the Technical Limits set forth in Schedule 2. .
(j) Be responsible at its own risk and expense for ensuring that the construction and operation of the Project complies with all environmental and safety regulations mandated by the laws of Bangladesh, and to be responsible for the disposal and treatment of waste in connection with the Project.
Appears in 1 contract
Samples: Power Purchase Agreement
The Company Covenants. The Company hereby covenants to and agrees with BPDB to:
(a) Until Construction Start Date, the Company shall obtain all necessary financing in an amount sufficient for the construction, completion, operation and maintenance of the Project in the manner contemplated by this Contract.
(b) Until Construction Start Date, use all reasonable efforts to negotiate and execute the contracts with the Contractor(s) that will perform the Project’s engineering, procurement and construction and the Financing Documents;
(c) Work with and cooperate in good faith with BPDB with respect to all of BPDB’s obligations and rights hereunder;
(d) Design, engineer, construct, complete, own and operate the Project in accordance with
(i) the plans and specifications prepared in accordance with this Contract,
(ii) the Contracted Operating Characteristics set forth in Schedule 1.
(iii) all Laws of Bangladesh,
(e) Design, construct and complete the Project in a manner which is suitable for the intended purpose, only with materials and equipment that are new and of international utility-grade quality, in such a manner as to provide a reasonable likelihood, with proper maintenance and Operation, that the useful life of the Project will be at least equal to the Term;
(f) All equipments related to the facility (Solar PV Panels, Inverter & Metering equipments) will be tested at the manufacturer's premises following manufacturemanufacture pursuant to Section 12 & Schedule 1. Any reasonable All costs of such a visit test shall be borne by the Company.
(g) Provide the electrical Interconnection between the Project and Baraiyarhat Netrokona 132/33 kV grid substation KV Grid Substation system as per PGCBBPDB's guideline.
(h) Provide at its own risk and expense the necessary facilities and services for the safety, comfort and protection of its personnel;
(i) After Commercial Operation Date, operate and maintain the Project, in accordance with:
(i) Prudent Utility Practices,
(ii) the operating procedures developed pursuant to Section 6.3 and the Dispatch Instructions, and
(iii) the Technical Limits set forth in Schedule 2. .
(j) Be responsible at its own risk and expense for ensuring that the construction and operation of the Project complies with all environmental and safety regulations mandated by the laws of Bangladesh, and to be responsible for the disposal and treatment of waste in connection with the Project.
Appears in 1 contract
Samples: Power Purchase Agreement