Time Extensions. 2.03.1 If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).
Appears in 43 contracts
Samples: Agreement for Professional Planning Services, Security Guard Services Agreement, Agreement for the Child and Adult Care After School Food Service Program
Time Extensions. 2.03.1 3.03.1 If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 calendar days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).
Appears in 15 contracts
Samples: Professional Services, Services Agreement, Energy Consulting Services Agreement
Time Extensions. 2.03.1 3.4.2.1 If Contractor Consultant requests an extension of time to complete its performance, then the DirectorDirector may, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 180 calendar days. The extension must be in writing but does not require amendment of this Agreement. Contractor Consultant is not entitled to damages for delay(s) regardless of the cause of the delay(s).
Appears in 10 contracts
Samples: Professional Services Agreement, Professional Services, On Call Professional Comprehensive Communication Services Agreement
Time Extensions. 2.03.1 If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 ninety (90) days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).
Appears in 6 contracts
Samples: Agreement for Blower Repair/Replacement Services, Janitorial Cleaning Agreement, Security Guard Services Agreement
Time Extensions. 2.03.1
3.03.1 If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).
Appears in 3 contracts
Samples: Agreement for Long Range Dredging Operational Plan, Dredging Monitoring Contractor Services Agreement, Management Agreement
Time Extensions. 2.03.1 If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 daystime. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).
Appears in 3 contracts
Samples: Professional Services, Client Application Support Services Agreement, Services Agreement
Time Extensions. 2.03.1 3.5.2.1 If Contractor Consultant requests an extension of time to complete its performance, then the DirectorDirector may, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 180 calendar days. The extension must be in writing writing, but does not require amendment of this Agreement. Contractor Consultant is not entitled to damages for delay(s) regardless of the cause of the delay(s).
Appears in 2 contracts
Samples: Agreement for Master Program Management Services for Disaster Related Projects Phase 2, Agreement for Master Program Management Services for Disaster Related Projects Phase 2
Time Extensions.
2.03.1 If In addition to the authority of the Director to extend this Agreement pursuant to the terms of Section 4.03.1 hereinbelow, if Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).
Appears in 2 contracts
Samples: Professional Planning Services Agreement, Professional Planning Services Agreement
Time Extensions. 2.03.1 3.03.1. If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).
Appears in 2 contracts
Samples: Professional Services Agreement, Professional Services Agreement
Time Extensions. 2.03.1 3.03.1 If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).
Appears in 2 contracts
Samples: Electronic Citation Solution Agreement, Agreement for Services
Time Extensions. 2.03.1
3.3.1 If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).
Appears in 2 contracts
Samples: Library Digital Databases and Collections Services Agreement, Library Digital Materials Services Agreement
Time Extensions. 2.03.1
3.03.1. If Contractor Consultant requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 180 days. The extension must be in writing but does not require amendment of this Agreement. Contractor Consultant is not entitled to damages for delay(s) regardless of the cause of the delay(s).
Appears in 1 contract
Samples: Disaster Recovery and Consulting Services Agreement
Time Extensions. 2.03.1
4.1 If the Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, Director may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).
Appears in 1 contract
Time Extensions. 2.03.1 If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 180 days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).
Appears in 1 contract
Samples: Security Guard Services Agreement
Time Extensions. 2.03.1 If Contractor requests an extension of time to complete its performance, then the DirectorCity Attorney, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).
Appears in 1 contract
Time Extensions. 2.03.1 3.4.2.1. If Contractor requests an extension of time to complete its performance, then the DirectorDirector may, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 180 calendar days. The extension must be in writing writing, but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).
Appears in 1 contract
Time Extensions. 2.03.1 3.03.1 If Contractor requests an extension of time to complete its performance, then the DirectorCity Attorney, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 calendar days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).
Appears in 1 contract
Time Extensions. 2.03.1 3.4.1.1. If Contractor Consultant requests an extension of time to complete its performance, then the DirectorDirector may, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 180 calendar days. The extension must be in writing writing, but does not require amendment of this Agreement. Contractor Consultant is not entitled to damages for delay(s) regardless of the cause of the delay(s).
Appears in 1 contract
Samples: Professional Services
Time Extensions. 2.03.1
3.5.1. If Contractor requests an extension of time to complete its performance, then the DirectorCity Attorney, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).
Appears in 1 contract
Time Extensions. 2.03.1 2.04.1 If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).
Appears in 1 contract
Samples: Arbitrage Calculation and Consulting Services Agreement
Time Extensions. 2.03.1
3.03.1 If Contractor Agency requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 days. The extension must be in writing but does not require amendment of this Agreement. Contractor Agency is not entitled to damages for delay(s) regardless of the cause of the delay(s).
Appears in 1 contract
Time Extensions. 2.03.1
3.5.1. If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).
Appears in 1 contract
Time Extensions. 2.03.1 3.03.1 If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 ninety (90) days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).
Appears in 1 contract
Samples: Licensing Agreement
Time Extensions. 2.03.1 3.39.1 If Contractor the Director requests an extension of time to complete its Contractor’s performance, then the DirectorCPO may, in upon consultation with the CPO, may, in his or her sole discretionDirector involved, extend the time so long as the extension does not exceed 90 180 calendar days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).
Appears in 1 contract
Samples: Professional Services
Time Extensions. 2.03.1 If Contractor requests an extension of time to complete its performance, then the Fleet Management Department Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).
Appears in 1 contract
Time Extensions. 2.03.1 If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).
Appears in 1 contract
Samples: Managed Telecommunications Maintenance Services Agreement
Time Extensions. 2.03.1 3.4.3.1 If Contractor requests an extension of time to complete its performance, then the DirectorDirector may, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 180 calendar days. The extension must be in writing but does not require amendment of this AgreementContract. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).
Appears in 1 contract
Samples: Professional Services
Time Extensions. 2.03.1 3.03.1 If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 180 calendar days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).
Appears in 1 contract
Time Extensions. 2.03.1 If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 thirty days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).
Appears in 1 contract
Samples: Professional Services
Time Extensions. 2.03.1 3.4.2.1 If Contractor requests an extension of time to complete its performance, then the DirectorDirector may, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 180 calendar days. The extension must be in writing writing, but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).
Appears in 1 contract
Time Extensions. 2.03.1 If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 ninety (90) days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).
Appears in 1 contract
Time Extensions. 2.03.1 3.4.1.1. If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, Director may extend the time so long as the extension does not exceed 90 180 calendar days. The extension must be in writing writing, but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).
Appears in 1 contract
Samples: Agreement for Case Management Intermediary Services
Time Extensions. 2.03.1 2.04.1 If Contractor requests an extension of time to complete its performance, then the DirectorCity Controller, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).
Appears in 1 contract
Samples: Professional Services
Time Extensions. 2.03.1 3.5.2.1. If Contractor requests an extension of time to complete its performance, then the DirectorDirector may, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 180 calendar days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).
Appears in 1 contract
Samples: On Call Planning Services Agreement
Time Extensions. 2.03.1 3.7.1 If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, Director may, in his or her its sole discretion, extend the time so long as the extension does not exceed 90 180 days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).
Appears in 1 contract
Samples: Agreement for the Administration of an Aviation Pole Banner Program
Time Extensions. 2.03.1 If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the Chief Procurement Officer (CPO), may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).
Appears in 1 contract
Time Extensions. 2.03.1
3.03.1. If Contractor requests an extension of time to complete its performance, then the Director, in consultation with the CPO, may, in his or her sole discretion, extend the time so long as the extension does not exceed 90 days. The extension must be in writing but does not require amendment of this Agreement. Contractor is not entitled to damages for delay(s) regardless of the cause of the delay(s).
Appears in 1 contract