Time of Submission of Claim for Increase in Contract Time and Cost. A Claim for an increase in the Contract Times (or Milestones) and/or amendment of the contract or contract price for additional cost of the Project due to a delay in the Work shall be submitted within thirty (30) days of the last date of the claimed delay.
Appears in 14 contracts
Samples: Construction Agreement, Construction Agreement, Design Bid Build Contractor Services
Time of Submission of Claim for Increase in Contract Time and Cost. A Claim for an increase in the Contract Times (or Milestones) and/or amendment of the contract or contract price for additional cost of the Demolition Project due to a delay in the Demolition Work shall be submitted within thirty ten (3010) days of the last date of the claimed delay.
Appears in 3 contracts
Samples: Demolition Contractor Services Agreement, Demolition Contractor Services Agreement, Demolition Contractor Services Agreement