Timeframes and Communications. 1. All time designations shall be in calendar days unless otherwise stipulated. If any Signatory does not object to FEMA’s finding or determination related to an Undertaking within an agreed upon timeframe, FEMA may proceed to the next step in the consultation process as described in Stipulation II, Project Review. 2. Due to the varied nature of Undertakings, the individual response times to FEMA’s requests for comment/concurrence will vary. These response times are contingent upon FEMA ensuring that its findings and determinations are made by Qualified staff and supported by documentation as required by 36 CFR § 800.11(d) and 36 CFR § 800.11(e), and consistent with FEMA guidance. a. For Emergency Undertakings as outlined in Stipulation II.B, Expedited Review of Emergency Undertakings, the SHPO and participating Tribe(s) shall respond to any FEMA request for comments within three (3) days after receipt, unless FEMA determines the nature of the emergency action warrants a shorter time period. b. For Undertakings associated with the Individual Assistance (IA) and Public Assistance (PA) programs, the response time for each request for concurrence while the Joint Field Office (JFO) is open shall be a maximum of ten (10) days, or in accordance with temporary timelines established by FEMA on a Declaration by Declaration basis. FEMA will call the THPOs and consulting Tribe(s) to inform them the notice and documentation has been sent and this is an expedited review. c. For the Hazard Mitigation Grant Program (HMGP), all non-disaster programs, IA, and PA undertakings to be reviewed after the JFO is closed, the response time for each request for concurrence shall be a maximum of thirty (30) days. 3. The consulting parties may send and accept official notices, comments, requests for further information and documentation, and other communications required by this Agreement by e-mail.
Appears in 5 contracts
Samples: Statewide Programmatic Agreement, Statewide Programmatic Agreement, Programmatic Agreement
Timeframes and Communications. 1. All time designations shall be in calendar days unless otherwise stipulated. If any Signatory does not object to FEMA’s finding or determination related to an Undertaking within an agreed upon timeframe, FEMA may proceed to the next step in the consultation process as described in Stipulation II, Project Review.
2. Due to the varied nature of Undertakings, the individual response times to FEMA’s requests for comment/concurrence will vary. These response times are contingent upon FEMA ensuring that its findings and determinations are made by Qualified staff and supported by documentation as required by 36 CFR § 800.11(d) and 36 CFR § 800.11(e), and consistent with FEMA guidance.
a. For Emergency Undertakings as outlined in Stipulation II.B, Expedited Review of Emergency Undertakings, the SHPO and participating Tribe(s) shall respond to any FEMA request for comments within three (3) days after receipt, unless FEMA determines the nature of the emergency action warrants a shorter time period.
b. For Undertakings associated with the Individual Assistance (IA) and Public Assistance (PA) programs, the response time for each request for concurrence while the Joint Field Office (JFO) is open shall be a maximum of ten (10) days, or in accordance with temporary timelines established by FEMA on a Declaration by Declaration basis. FEMA will call the THPOs and consulting Tribe(s) to inform them the notice and documentation has been sent and this is an expedited review.
c. For the Hazard Mitigation Grant Program (HMGP), all non-disaster programs, IA, and IA and PA undertakings to be reviewed after the JFO is closed, the response time for each request for concurrence shall be a maximum of thirty (30) days.
3. The consulting parties may send and accept official notices, comments, requests for further information and documentation, and other communications required by this Agreement by e-mail.thirty
Appears in 2 contracts
Samples: Programmatic Agreement, Programmatic Agreement
Timeframes and Communications. 1. All time designations shall be in calendar days unless otherwise stipulated. If any Signatory does not object to FEMA’s finding or determination related to an Undertaking within an agreed upon timeframe, FEMA may proceed to the next step in the consultation process as described in Stipulation II, Project Review.
2. Due to the varied nature of Undertakings, the individual response times to FEMA’s requests for comment/concurrence will vary. These response times are contingent upon FEMA ensuring that its findings and determinations are made by Qualified staff and supported by documentation as required by 36 CFR § 800.11(d) and 36 CFR § 800.11(e), and consistent with FEMA guidance.
a. For Emergency Undertakings as outlined in Stipulation II.B, Expedited Review of Emergency Undertakings, the SHPO and participating Tribe(s) Tribes shall respond to any FEMA request for comments within three (3) business days after receipt, unless FEMA determines the nature of the emergency action warrants a shorter time period.
b. For Undertakings associated with the Individual Assistance (IA) and Public Assistance (PA) programs, the response time for each request for concurrence while the Joint Field Office (JFO) is open shall be a maximum of ten fifteen (1015) daysdays after receipt, or in accordance with temporary timelines established by FEMA and agreed upon by SHPO and participating Tribes on a Declaration by Declaration basis. FEMA will call the THPOs and consulting Tribe(s) to inform them the notice and documentation has been sent and this is an expedited review.
c. For the Hazard Mitigation Grant Program (HMGP), ) and all non-disaster programs, IA, and PA undertakings to be reviewed after the JFO is closed, the response time for each request for concurrence shall be a maximum of thirty (30) days.
3. The consulting parties may send and accept official notices, comments, requests for further information and documentation, and other communications required by this Agreement by e-mail.thirty
Appears in 1 contract
Samples: Programmatic Agreement
Timeframes and Communications. 1. All time designations shall be in calendar days unless otherwise stipulated. If any Signatory does not object to FEMA’s finding or determination related to an Undertaking within an agreed upon timeframe, FEMA may proceed to the next step in the consultation process as described in Stipulation II, Project Review.
2. Due to the varied nature of Undertakings, the individual response times to FEMA’s requests for comment/concurrence will vary. These response times are contingent upon FEMA ensuring that its findings and determinations are made by Qualified staff and supported by documentation as required by 36 CFR § 800.11(d) and 36 CFR § 800.11(e), and consistent with FEMA guidance. The response times set forth in this agreement or otherwise agreed upon on a Declaration by Declaration basis will be clearly stated in FEMA’s requests for comment/concurrence.
a. For Emergency Undertakings as outlined in Stipulation II.B, Expedited Review of Emergency Undertakings, the SHPO and participating Tribe(s) shall respond to any FEMA request for comments within three (3) days after receipt, unless FEMA determines the nature of the emergency action warrants a shorter time period.
b. For Undertakings associated with the Individual Assistance (IA) and Public Assistance (PA) programs, the response time for each request for concurrence while the Joint Field Office (JFO) is open shall be a maximum of ten fifteen (1015) days, or in accordance with temporary timelines established by FEMA on a Declaration by Declaration basis. FEMA will call the THPOs and consulting Tribe(s) to inform them the notice and documentation has been sent and this is an expedited review.
c. For the Hazard Mitigation Grant Program (HMGP), ) and all non-disaster programs, IA, and PA undertakings to be reviewed after the JFO is closed, the response time for each request for concurrence shall be a maximum of thirty (30) days.
3. The consulting parties may send and accept official notices, comments, requests for further information and documentation, and other communications required by this Agreement by e-mail.
Appears in 1 contract
Samples: Programmatic Agreement
Timeframes and Communications. 1. All time designations shall be in calendar days unless otherwise stipulated. If any Signatory does not object to FEMA’s finding or determination related to an Undertaking within an agreed upon timeframe, FEMA may proceed to the next step in the consultation process as described in Stipulation II, Project Review.
2. Due to the varied nature of Undertakings, the individual response times to FEMA’s requests for comment/concurrence will vary. These response times are contingent upon FEMA ensuring that its findings and determinations are made by Qualified staff and supported by documentation as required by 36 CFR § 800.11(d) and 36 CFR § 800.11(e), and consistent with FEMA guidance.
a. For Emergency Undertakings as outlined in Stipulation II.B, Expedited Review of Emergency Undertakings, the SHPO and participating Tribe(s) shall respond to any FEMA request for comments within three (3) days after receipt, unless FEMA determines the nature of the emergency action warrants a shorter time period.
b. For Undertakings associated with the Individual Assistance (IA) and Public Assistance (PA) programs, the response time for each request for concurrence while the Joint Field Office (JFO) is open shall be a maximum of ten fifteen (1015) days, or in accordance with temporary timelines established by FEMA and agreed to by the SHPO and participating Tribe(s) on a Declaration by Declaration basis. FEMA will call the THPOs and consulting Tribe(s) to inform them the notice and documentation has been sent and this is an expedited review.
c. For the Hazard Mitigation Grant Program (HMGP), all non-disaster programs, IA, and IA and PA undertakings to be reviewed after the JFO is closed, the response time for each request for concurrence shall be a maximum of thirty (30) days.. --DRAFT--
3. The consulting parties may send and accept official notices, comments, requests for further information and documentation, and other communications required by this Agreement by e-mail.
Appears in 1 contract
Samples: Programmatic Agreement
Timeframes and Communications. 1. All time designations shall be in calendar days unless otherwise stipulated. If any Signatory does not object to FEMA’s finding or determination related to an Undertaking within an agreed upon timeframe, FEMA may proceed to the next step in the consultation process as described in Stipulation II, Project Review.
2. Due to the varied nature of Undertakings, the individual response times to FEMA’s requests for comment/concurrence will vary. These response times are contingent upon FEMA ensuring that its findings and determinations are made by Qualified staff and supported by documentation as required by 36 CFR § 800.11(d) and 36 CFR § 800.11(e), and consistent with FEMA guidance.
a. For Emergency Undertakings as outlined in Stipulation II.B, Expedited Review of Emergency Undertakings, the SHPO and participating Tribe(s) shall respond to any FEMA request for comments within three (3) days after receipt, unless FEMA determines the nature of the emergency action warrants a shorter time period.
b. For Undertakings associated with the Individual Assistance (IA) and Public Assistance (PA) programs, the response time for each request for concurrence while the Joint Field Office (JFO) is open shall be a maximum of ten fifteen (1015) days, or in accordance with temporary timelines established by FEMA and agreed to by the SHPO and participating Tribe(s) on a Declaration by Declaration basis. FEMA will call the THPOs and consulting Tribe(s) to inform them the notice and documentation has been sent and this is an expedited review.
c. For the Hazard Mitigation Grant Program (HMGP), all non-disaster programs, IA, and IA and PA undertakings to be reviewed after the JFO is closed, the response time for each request for concurrence shall be a maximum of thirty (30) days.
3. The consulting parties may send and accept official notices, comments, requests for further information and documentation, and other communications required by this Agreement by e-mail.thirty
Appears in 1 contract
Samples: Statewide Programmatic Agreement
Timeframes and Communications. 1. All time designations shall be in calendar days unless otherwise stipulated. If any Signatory does not object to FEMA’s finding or determination related to an Undertaking within an agreed agreed-upon timeframe, FEMA may proceed to the next step in the consultation process as described in Stipulation II., Project Review.
2. Due to the varied nature of Undertakings, the individual response times to FEMA’s requests for comment/concurrence will vary. These response times are contingent upon FEMA ensuring that its findings and determinations are made by Qualified staff and supported by documentation as required by 36 CFR § 800.11(d) and 36 CFR § 800.11(e), and consistent with FEMA guidance.
a. For Emergency Undertakings as outlined in Stipulation II.BII.B., Expedited Review of Emergency Undertakings, the SHPO and participating Tribe(s) shall respond to any FEMA request for comments within three (3) days after receipt, unless FEMA determines the nature of the emergency action warrants a shorter time period.
b. For Undertakings associated with the Individual Assistance (IA) program the response time for each request for concurrence shall be fifteen (15) days, and for Undertakings associated with the Public Assistance (PA) programsprogram, the response time for each request for concurrence while the shall be fifteen (15) days for submittals related to an open declared-disaster operation (i.e. Joint Field Office Office), and thirty (JFO30) is open shall be a maximum of ten (10) daysdays thereafter, or in accordance with temporary timelines established by FEMA on a Declaration by Declaration-by-Declaration basis. FEMA will call the THPOs and consulting Tribe(s) to inform them the notice and documentation has been sent and this is an expedited review.
c. For the Hazard Mitigation Grant Program (HMGP), ) and all non-disaster programs, IA, and PA undertakings to be reviewed after the JFO is closed, the response time for each request for concurrence shall be a maximum of thirty (30) days.
3. The consulting parties may send and accept official notices, comments, requests for further information and documentation, and other communications required by this Agreement by e-mail. As appropriate, if it will facilitate completion of reviews, hard copies may be requested.
Appears in 1 contract
Samples: Programmatic Agreement
Timeframes and Communications. 1. All time designations shall be in calendar days unless otherwise stipulated. If any Signatory signatory does not object to FEMA’s finding or determination related to an Undertaking within an agreed upon timeframe, FEMA may proceed to the next step in the consultation process as described in Stipulation II, Project Review.
2. Due to the varied nature of Undertakings, the individual response times to FEMA’s requests for comment/concurrence will may vary. These response times are contingent upon FEMA ensuring that its findings and determinations are made by Qualified staff and supported by documentation as required by 36 CFR § 800.11(d) and 36 CFR § 800.11(e), and consistent with FEMA guidance.
a. For Emergency Undertakings Undertakings, as outlined in Stipulation II.BII.B.2(c)(i), Expedited Review of Emergency Undertakings, the SHPO and participating Tribe(s) Tribes shall respond to any FEMA request for comments within three seven (37) days after receipt, unless FEMA determines the nature of the emergency action warrants a shorter time period.
b. For Undertakings associated with the Individual Assistance (IA) and Public Assistance (PA) programs, the response time for each request for concurrence while the Joint Field Office (JFO) is open shall be a maximum of ten fifteen (1015) days, or in accordance with temporary timelines established by FEMA on a Declaration by Declaration basis. FEMA will call the THPOs and consulting Tribe(s) to inform them the notice and documentation has been sent and this is an expedited review.
c. For the Hazard Mitigation Grant Program (HMGP), ) and all non-disaster programs, IA, and PA undertakings to be reviewed after the JFO is closed, the response time for each request for concurrence shall be a maximum of thirty (30) days.
3. The consulting parties Signatories may send and accept official notices, comments, requests for further information and documentation, and other communications required by this Agreement by e-mail.
4. FEMA will maintain a record of contact information for the Signatories. A Signatory may update this information by notification to FEMA without amending the Agreement. The Signatory will notify the Region VI Environmental Officer within thirty 30 days after an update, whereupon FEMA will notify the other Signatories of the update.