Timeframes and Communications. 1. All time designations shall be in calendar days unless otherwise stipulated. If any Signatory does not object to FEMA’s finding or determination related to an Undertaking within an agreed upon timeframe, FEMA may proceed to the next step in the consultation process as described in Stipulation II, Project Review. 2. Due to the varied nature of Undertakings, the individual response times to FEMA’s requests for comment/concurrence will vary. These response times are contingent upon FEMA ensuring that its findings and determinations are made by Qualified staff and supported by documentation as required by 36 CFR § 800.11(d) and 36 CFR § 800.11(e), and consistent with FEMA guidance. a. For Emergency Undertakings as outlined in Stipulation II.B, Expedited Review of Emergency Undertakings, the SHPO shall respond to any FEMA request for comments within three (3) days after receipt, unless FEMA determines the nature of the emergency action warrants a shorter time period. b. For Undertakings associated with the Individual Assistance (IA) and Public Assistance (PA) programs, the response time for each request for concurrence shall be a maximum of fifteen (15) days, or in accordance with temporary timelines established by FEMA on a Declaration by Declaration basis. c. For the Hazard Mitigation Grant Program (HMGP) and all non-disaster programs, the response time for each request for concurrence shall be a maximum of thirty (30) days. 3. The consulting parties may send and accept official notices, comments, requests for further information and documentation, and other communications required by this Agreement by e-mail.
Appears in 4 contracts
Samples: Programmatic Agreement, Programmatic Agreement, Programmatic Agreement
Timeframes and Communications. 1. All time designations shall be in calendar days unless otherwise stipulated. If any Signatory does not object to FEMA’s finding or determination related to an Undertaking within an agreed upon timeframe, FEMA may proceed to the next step in the consultation process as described in Stipulation II, Project Review.
2. Due to the varied nature of Undertakings, the individual response times to FEMA’s requests for comment/concurrence will vary. These response times are contingent upon FEMA ensuring that its findings and determinations are made by Qualified staff and supported by documentation as required by 36 CFR § 800.11(d) and 36 CFR § 800.11(e), and consistent with FEMA guidance.
a. For Emergency Undertakings as outlined in Stipulation II.B, Expedited Review of Emergency Undertakings, the SHPO and participating Tribe(s) shall respond to any FEMA request for comments within three (3) days after receipt, unless FEMA determines the nature of the emergency action warrants a shorter time period.
b. For Undertakings associated with the Individual Assistance (IA) and Public Assistance (PA) programs, the response time for each request for concurrence shall be a maximum of fifteen (15) days, or in accordance with temporary timelines established by FEMA on a Declaration by Declaration basis.
c. For the Hazard Mitigation Grant Program (HMGP) and all non-disaster programs, the response time for each request for concurrence shall be a maximum of thirty (30) days.
3. The consulting parties may send and accept official notices, comments, requests for further information and documentation, and other communications required by this Agreement by e-mail.
Appears in 3 contracts
Samples: Programmatic Agreement, Programmatic Agreement, Programmatic Agreement
Timeframes and Communications. 1. All time designations shall be in calendar days unless otherwise stipulated. If any Signatory does not object to FEMA’s finding or determination related to an Undertaking within an agreed upon timeframe, FEMA may proceed to the next step in the consultation process as described in Stipulation II, Project Review.
2. Due to the varied nature of Undertakings, the individual response times to FEMA’s requests for comment/concurrence will vary. These response times are contingent upon FEMA ensuring that its findings and determinations are made by Qualified staff and supported by documentation as required by 36 CFR § 800.11(d) and 36 CFR § 800.11(e), and consistent with FEMA guidance.
a. For Emergency Undertakings as outlined in Stipulation II.B, Expedited Review of Emergency Undertakings, the SHPO and participating Tribes shall respond to any FEMA request for comments within three (3) days after receipt, unless FEMA determines the nature of the emergency action warrants a shorter time period.
b. For Undertakings associated with the Individual Assistance (IA) and Public Assistance (PA) programs, the response time for each request for concurrence shall be a maximum of fifteen (15) days, or in accordance with temporary timelines established by FEMA on a Declaration by Declaration basis.
c. For the Hazard Mitigation Grant Program (HMGP) and all non-disaster programs, the response time for each request for concurrence shall be a maximum of thirty (30) days.
3. The consulting parties may send and accept official notices, comments, requests for further information and documentation, and other communications required by this Agreement by e-mailmail unless otherwise requested.
Appears in 2 contracts
Samples: Programmatic Agreement, Programmatic Agreement
Timeframes and Communications. 1. All time designations shall be in calendar days unless otherwise stipulated. If any Signatory does not object to FEMA’s finding or determination related to an Undertaking within an agreed upon timeframe, FEMA may proceed to the next step in the consultation process as described in Stipulation II, Project Review.
2. Due to the varied nature of Undertakings, the individual response times to FEMA’s requests for comment/concurrence will vary. These response times are contingent upon FEMA ensuring that its findings and determinations are made by Qualified staff and supported by documentation as required by 36 CFR § 800.11(d) and 36 CFR § 800.11(e), and consistent with FEMA guidance. When corresponding with SHPO or other consulting parties, FEMA will identify the program(s) under which the Undertaking falls, and specify the applicable review timeframe.
a. For Emergency Undertakings as outlined in Stipulation II.B, Expedited Review of Emergency Undertakings, the SHPO and participating Tribe(s) shall respond to any FEMA request for comments within three (3) days after receipt, unless FEMA determines the nature of the emergency action warrants a shorter time period.
b. For Undertakings associated with the Individual Assistance (IA) and Public Assistance (PA) programs, the response time for each request for concurrence shall be a maximum of fifteen (15) days, or in accordance with temporary timelines established by FEMA on a Declaration by Declaration basis.
c. For the Hazard Mitigation Grant Program (HMGP) and all non-disaster programs, the response time for each request for concurrence shall be a maximum of thirty (30) days.
3. The consulting parties may send and accept official notices, comments, requests for further information and documentation, and other communications required by this Agreement by e-mail.
Appears in 1 contract
Samples: Programmatic Agreement
Timeframes and Communications. 1. All time designations shall be in calendar days unless otherwise stipulated. If any Signatory does not object to FEMA’s finding or determination related to an Undertaking within an agreed upon timeframe, FEMA may proceed to the next step in the consultation process as described in Stipulation II, Project Review.
2. Due to the varied nature of Undertakings, the individual response times to FEMA’s requests for comment/concurrence will vary. These response times are contingent upon FEMA ensuring that its findings and determinations are made by Qualified staff and supported by documentation as required by 36 CFR § 800.11(d) and 36 CFR § 800.11(e), and consistent with FEMA guidance.
a. For Emergency Undertakings as outlined in Stipulation II.B, Expedited Review of Emergency Undertakings, the SHPO and participating Tribe(s) shall respond to any FEMA request for comments within three (3) days after receipt, unless FEMA determines the nature of the emergency action warrants a shorter time period.
b. For Undertakings associated with the Individual Assistance (IA) and Public Assistance (PA) programs, the response time for each request for concurrence shall be a maximum of fifteen (15) days, or in accordance with temporary timelines established by FEMA on a Declaration by Declaration basis.
c. For the Hazard Mitigation Grant Program (HMGP) and all non-disaster programs, the response time for each request for concurrence shall be a maximum of thirty (30) days.
3. The consulting parties may send and accept official notices, comments, requests for further information and documentation, and other communications required by this Agreement by e-mail.thirty
Appears in 1 contract
Samples: Programmatic Agreement
Timeframes and Communications. 1. All time designations shall be in calendar days unless otherwise stipulated. If any Signatory does not object to FEMA’s finding or determination related to an Undertaking within an agreed upon timeframe, FEMA may proceed to the next step in the consultation process as described in Stipulation II, Project Review.
2. Due to the varied nature of Undertakings, the individual response times to FEMA’s requests for comment/concurrence will may vary. These response times are contingent upon FEMA ensuring that its findings and determinations are made by Qualified staff and supported by documentation as required by 36 CFR § §800.11(d) and 36 CFR § §800.11(e), ) and consistent with FEMA guidance.
a. For Expedited Review of Emergency Undertakings as outlined in Stipulation II.B, II.B Expedited Review of Emergency Undertakings, the SHPO shall respond to any FEMA request for comments within three (3) days after receipt, unless FEMA determines the nature of the emergency action warrants a shorter time period.
b. For Undertakings associated with the Individual Assistance (IA) and Public Assistance (PA) programs, the response review time for each request for concurrence shall be a maximum of fifteen (15) days, or in accordance with temporary timelines established by FEMA on a Declaration by to Declaration basis.
c. For the Hazard Mitigation Grant Program (HMGP) and all non-disaster programs, the response time for each request for concurrence shall be a maximum of thirty (30) days.
3. The consulting parties may send and accept official notices, comments, requests for further information and documentation, and other communications required by this the Agreement by e-mail.