Common use of Tributary Barrier Confirmation and Removal Planning Clause in Contracts

Tributary Barrier Confirmation and Removal Planning. ‌ Tributary barriers identified in the Tributary Barrier Analysis report (DES 2000b) will be reassessed for depth, velocity, and gradient and re-prioritized if necessary. Two methodologies that may be used are: 1) using the Forest Practices Board Emergency Rule and “Oregon Method” used in the 2000 report; or 2) developing a more simplistic method based on the principles of the 2000 methodology to use as a more rapid assessment tool. The USDA Forest Service supports the latter option. As tributary barriers are documented as either remaining or eliminated, the LCFF will update the tributary barrier removal priority list included in the 2000 report. Once the tributary barrier removal priority list is updated, the LCFF will work with Chelan PUD to implement Lake Chelan Settlement Agreement License Article 6(c) for tributary barrier removal work, such as investigating barrier removal methods, stream channel rehabilitation design at tributary mouths, contractor selection to conduct work, etc. Actual on-the-ground tributary barrier removal efforts will commence in early 2011, depending upon runoff volume and associated lake elevation. Tributary barrier removal efforts were scheduled originally to begin in 2009. However, the schedule was revised due to delay in selecting a design contractor; need by the design contractor to view tributary mouths in 2009 to observe barriers present and discuss with the consulting team and LCFF potential preliminary design features; time required to secure necessary permits; and time required to secure a construction contractor. The LCFF conducted a boat tour of tributary mouths in March 2008, touring both the north and south shores from Twenty-five Mile Creek uplake to Fish Creek. During the tour, LCFF members took numerous photographs of the tributary mouths to initiate photo-documentation of existing tributary mouth conditions and barriers to upstream fish passage. Photographs were posted on the Chelan PUD Lake Chelan Implementation Website. After the conclusion of the tour, Forum members reached consensus that virtually all tributaries observed had barriers, either water depth, water velocity, or gradient, to upstream fish passage at the lake elevation of approximately 1083.0 feet that occurred during the site visit. The LCFF met again on June 17, 2008 to review Statements of Qualifications (SOQs) submitted by potential tributary barrier removal design consultants, select a consultant, and proceed with implementing the Tributary Barrier Removal Project (TBRP). A design consultant, the Fairbanks Environmental Team, was selected by consensus of the LCFF. The LCFF reviewed pertinent information regarding watershed conditions of tributaries to Lake Chelan, such as the USDA Forest Service Regional Assistance Teams (RATs) assessment report, USDA Forest Service Lake Chelan Basin fire map of areas burned since 1998, and tributary mouth photographs taken in March 2008. Based on this information, the priority tributaries selected by the LCFF at the June 17, 2008 meeting were Safety Harbor, Xxxxxxxx, Grade, and Gold creeks. However, even with the selection of priority tributaries, the LCFF members discussed proceeding cautiously with tributary barrier removal efforts due to the following considerations:

Appears in 3 contracts

Samples: www.chelanpud.org, www.chelanpud.org, www.chelanpud.org

AutoNDA by SimpleDocs

Tributary Barrier Confirmation and Removal Planning. ‌ Tributary barriers identified in the Tributary Barrier Analysis report (DES 2000b) will be reassessed for depth, velocity, and gradient and re-prioritized if necessary. Two methodologies that may be used are: 1) using the Forest Practices Board Emergency Rule and “Oregon Method” used in the 2000 report; or 2) developing a more simplistic method based on the principles of the 2000 methodology to use as a more rapid assessment tool. The USDA Forest Service supports the latter option. As tributary barriers are documented as either remaining or eliminated, the LCFF will update the tributary barrier removal priority list included in the 2000 report. Once the tributary barrier removal priority list is updated, the LCFF will work with Chelan PUD to implement Lake Chelan Settlement Agreement License Article 6(c) for tributary barrier removal work, such as investigating barrier removal methods, stream channel rehabilitation design at tributary mouths, contractor selection to conduct work, etc. Actual on-the-ground tributary barrier removal efforts will commence in early 2011, depending upon runoff volume and associated lake elevation. Tributary barrier removal efforts were scheduled originally to begin in 2009. However, the schedule was revised due to delay in selecting a design contractor; need by the design contractor to view tributary mouths in 2009 to observe barriers present and discuss with the consulting team and LCFF potential preliminary design features; time required to secure necessary permits; and time required to secure a construction contractor. The LCFF conducted a boat tour of tributary mouths in March 2008, touring both the north and south shores from Twenty-five Mile Creek uplake up lake to Fish Creek. During the tour, LCFF members took numerous photographs of the tributary mouths to initiate photo-documentation of existing tributary mouth conditions and barriers to upstream fish passage. Photographs were posted on the Chelan PUD Lake Chelan Implementation Website. After the conclusion of the tour, Forum members reached consensus that virtually all tributaries observed had barriers, either water depth, water velocity, or gradient, to upstream fish passage at the lake elevation of approximately 1083.0 feet that occurred during the site visit. The LCFF met again on June 17, 2008 to review Statements of Qualifications (SOQs) submitted by potential tributary barrier removal design consultants, select a consultant, and proceed with implementing the Tributary Barrier Removal Project (TBRP). A design consultant, the Fairbanks Environmental Team, was selected by consensus of the LCFF. The LCFF reviewed pertinent information regarding watershed conditions of tributaries to Lake Chelan, such as the USDA Forest Service Regional Assistance Teams (RATs) assessment report, USDA Forest Service Lake Chelan Basin fire map of areas burned since 1998, and tributary mouth photographs taken in March 2008. Based on this information, the priority tributaries selected by the LCFF at the June 17, 2008 meeting were Safety Harbor, Xxxxxxxx, Grade, and Gold creeks. However, even with the selection of priority tributaries, the LCFF members discussed proceeding cautiously with tributary barrier removal efforts due to the following considerations:

Appears in 2 contracts

Samples: www.chelanpud.org, www.chelanpud.org

Tributary Barrier Confirmation and Removal Planning. Tributary barriers identified in the Tributary Barrier Analysis report (DES 2000b) will be reassessed for depth, velocity, and gradient and re-prioritized if necessary. Two methodologies that may be used are: 1) using the Forest Practices Board Emergency Rule and “Oregon Method” used in the 2000 report; or 2) developing a more simplistic method based on the principles of the 2000 methodology to use as a more rapid assessment tool. The USDA Forest Service supports the latter option. As tributary barriers are documented as either remaining or eliminated, the LCFF will update the tributary barrier removal priority list included in the 2000 report. Once the tributary barrier removal priority list is updated, the LCFF will work with Chelan PUD to implement Lake Chelan Settlement Agreement License Article 6(c) for tributary barrier removal work, such as investigating barrier removal methods, stream channel rehabilitation design at tributary mouths, contractor selection to conduct work, etc. Actual on-the-ground tributary barrier removal efforts will commence in early 2011, depending upon runoff volume and associated lake elevation. Tributary barrier removal efforts were scheduled originally to begin in 2009. However, the schedule scheduled was revised due to the following events: delay in selecting a design contractor; need by the design contractor to view tributary mouths in 2009 to observe barriers present and discuss with the consulting team and LCFF potential preliminary design features; time required to secure necessary permits; and time required to secure a construction contractor. The LCFF conducted a boat tour of tributary mouths in March 2008, touring both the north and south shores from Twenty-five five-Mile Creek uplake to Fish Creek. During the tour, LCFF members took numerous photographs of the tributary mouths to initiate photo-documentation of existing tributary mouth conditions and barriers to upstream fish passage. Photographs were posted on the Chelan PUD Lake Chelan Implementation Website. After the conclusion of the tour, Forum members reached consensus that virtually all tributaries observed had barriers, either water depth, water velocity, or gradient, to upstream fish passage at the lake elevation of approximately 1083.0 feet that occurred during the site visit. The LCFF met again on June 17, 2008 to review Statements of Qualifications (SOQs) submitted by potential tributary barrier removal design consultants, select a and consultant, and proceed with implementing the Tributary Barrier Removal Project (TBRP). A design consultant, the Fairbanks Environmental Team, was selected by consensus of the LCFF. The LCFF reviewed pertinent information regarding watershed conditions of tributaries to Lake Chelan, such as the USDA Forest Service Regional Assistance Teams (RATs) assessment report, USDA Forest Service Lake Chelan Basin fire map of areas burned since 1998, and tributary mouth photographs taken in March 2008. Based on this information, the priority tributaries selected by the LCFF at the June 17, 2008 meeting were Safety Harbor, Xxxxxxxx, Grade, and Gold creeks. However, even with the selection of priority tributaries, the LCFF members discussed proceeding cautiously with tributary barrier removal efforts due to the following considerations:

Appears in 2 contracts

Samples: citeseerx.ist.psu.edu, www.chelanpud.org

Tributary Barrier Confirmation and Removal Planning. Tributary barriers identified in the Tributary Barrier Analysis report (DES 2000b) will be reassessed for depth, velocity, and gradient and re-prioritized if necessary. Two methodologies that may be used are: 1) using the Forest Practices Board Emergency Rule and “Oregon Method” used in the 2000 report; or 2) developing a more simplistic method based on the principles of the 2000 methodology to use as a more rapid assessment tool. The USDA Forest Service supports the latter option. As tributary barriers are documented as either remaining or eliminated, the LCFF will update the tributary barrier removal priority list included in the 2000 report. Once the tributary barrier removal priority list is updated, the LCFF will work with Chelan PUD to implement Lake Chelan Settlement Agreement License Article 6(c) for tributary barrier removal work, such as investigating barrier removal methods, stream channel rehabilitation design at tributary mouths, contractor selection to conduct work, etc. Actual on-the-ground tributary barrier removal efforts will commence in early 2011, depending upon runoff volume and associated lake elevation. Tributary barrier removal efforts were scheduled originally to begin in 2009. However, the schedule was revised due to delay in selecting a design contractor; need by the design contractor to view tributary mouths in 2009 to observe barriers present and discuss with the consulting team and LCFF potential preliminary design features; time required to secure necessary permits; and time required to secure a construction contractor. The LCFF conducted a boat tour of tributary mouths in March 2008, touring both the north and south shores from Twenty-five Mile Creek uplake up lake to Fish Creek. During the tour, LCFF members took numerous photographs of the tributary mouths to initiate photo-documentation of existing tributary mouth conditions and barriers to upstream fish passage. Photographs were posted on the Chelan PUD Lake Chelan Implementation Website. After the conclusion of the tour, Forum members reached consensus that virtually all tributaries observed had barriers, either water depth, water velocity, or gradient, to upstream fish passage at the lake elevation of approximately 1083.0 feet that occurred during the site visit. The LCFF met again on June 17, 2008 to review Statements of Qualifications (SOQs) submitted by potential tributary barrier removal design consultants, select a consultant, and proceed with implementing the Tributary Barrier Removal Project (TBRP). A design consultant, the Fairbanks Environmental Team, was selected by consensus of the LCFF. The LCFF reviewed pertinent information regarding watershed conditions of tributaries to Lake Chelan, such as the USDA Forest Service Regional Assistance Teams (RATs) assessment report, USDA Forest Service Lake Chelan Basin fire map of areas burned since 1998, and tributary mouth photographs taken in March 2008. Based on this information, the priority tributaries selected by the LCFF at the June 17, 2008 meeting were Safety Harbor, Xxxxxxxx, Grade, and Gold creeks. However, even with the selection of priority tributaries, the LCFF members discussed proceeding cautiously with tributary barrier removal efforts due to the following considerations:

Appears in 1 contract

Samples: www.chelanpud.org

AutoNDA by SimpleDocs

Tributary Barrier Confirmation and Removal Planning. Tributary barriers identified in the Tributary Barrier Analysis report (DES 2000b) will be reassessed for depth, velocity, and gradient and re-prioritized if necessary. Two methodologies that may be used are: 1) using the Forest Practices Board Emergency Rule and “Oregon Method” used in the 2000 report; or 2) developing a more simplistic method based on the principles of the 2000 methodology to use as a more rapid assessment tool. The USDA Forest Service supports the latter option. As tributary barriers are documented as either remaining or eliminated, the LCFF will update the tributary barrier removal priority list included in the 2000 report. Once the tributary barrier removal priority list is updated, the LCFF will work with Chelan PUD to implement Lake Chelan Settlement Agreement License Article 6(c) for tributary barrier removal work, such as investigating barrier removal methods, stream channel rehabilitation design at tributary mouths, contractor selection to conduct work, etc. Actual on-the-ground tributary barrier removal efforts will commence in early 2011, depending upon runoff volume and associated lake elevation. Tributary barrier removal efforts were scheduled originally to begin in 2009. However, the schedule was revised due to delay in selecting a design contractor; need by the design contractor to view tributary mouths in 2009 to observe barriers present and discuss with the consulting team and LCFF potential preliminary design features; time required to secure necessary permits; and time required to secure a construction contractor. The LCFF conducted a boat tour of tributary mouths in March 2008, touring both the north and south shores from Twenty-five Mile Creek uplake to Fish Creek. During the tour, LCFF members took numerous photographs of the tributary mouths to initiate photo-documentation of existing tributary mouth conditions and barriers to upstream fish passage. Photographs were posted on the Chelan PUD Lake Chelan Implementation Website. After the conclusion of the tour, Forum members reached consensus that virtually all tributaries observed had barriers, either water depth, water velocity, or gradient, to upstream fish passage at the lake elevation of approximately 1083.0 feet that occurred during the site visit. The LCFF met again on June 17, 2008 to review Statements of Qualifications (SOQs) submitted by potential tributary barrier removal design consultants, select a consultant, and proceed with implementing the Tributary Barrier Removal Project (TBRP). A design consultant, the Fairbanks Environmental Team, was selected by consensus of the LCFF. The LCFF reviewed pertinent information regarding watershed conditions of tributaries to Lake Chelan, such as the USDA Forest Service Regional Assistance Teams (RATs) assessment report, USDA Forest Service Lake Chelan Basin fire map of areas burned since 1998, and tributary mouth photographs taken in March 2008. Based on this information, the priority tributaries selected by the LCFF at the June 17, 2008 meeting were Safety Harbor, Xxxxxxxx, Grade, and Gold creeks. However, even with the selection of priority tributaries, the LCFF members discussed proceeding cautiously with tributary barrier removal efforts due to the following considerations:

Appears in 1 contract

Samples: www.chelanpud.org

Time is Money Join Law Insider Premium to draft better contracts faster.