Unauthorized Changes in the Work. Contractor shall not be entitled to an increase in the Contract Price or an extension of the Contract Times with respect to any work performed that is not required by the Contract Documents as amended, modified, or supplemented and approved by Owner, except in the case of an emergency or in the case of uncovering Work as provided in the Agreement.
Appears in 14 contracts
Samples: Construction Agreement, Construction Agreement, Design Bid Build Contractor Services
Unauthorized Changes in the Work. Contractor shall not be entitled to an increase in the Contract Price or an extension of the Contract Times Time with respect to any work performed that is not required by the Contract Documents as amended, modified, or supplemented and approved by Owneras provided in Paragraph 3.04, except in the case of an emergency or in the case of uncovering Work as provided in the AgreementParagraph 6.17.
Appears in 7 contracts
Samples: Construction Contract, Construction Contract, Construction Contract
Unauthorized Changes in the Work. A. Contractor shall not be entitled to an increase in the Contract Price or an extension of the Contract Times with respect to any work performed that is not required by the Contract Documents Documents, as amended, modified, or supplemented and approved by Ownersupplemented, except in the case of an emergency as provided in Paragraph 7.15 or in the case of uncovering Work as provided in the AgreementParagraph 14.05.
Appears in 1 contract
Samples: Construction Contract
Unauthorized Changes in the Work.
A. Contractor shall not be entitled to an increase in the Contract Price or an extension of the Contract Times with respect to any work performed that is not required by the Contract Documents Documents, as amended, modified, or supplemented and approved by Ownersupplemented, except in the case of an emergency as provided in Paragraph 7.15 or in the case of uncovering Work as provided in the AgreementParagraph 14.05.C.2.
Appears in 1 contract
Samples: Construction Contract
Unauthorized Changes in the Work. Contractor shall not be entitled to an increase in the Contract Price or an extension of the Contract Times with respect to any work performed that is not required by the Contract Documents as amended, modified, or supplemented and approved by Owner, except in the case of an emergency or in the case of uncovering Work as provided in the Agreementfor with Owner’s approval and execution of a Contract amendment or Change Order.
Appears in 1 contract
Samples: Contract for Civil Engineering Construction Projects