Uncontrollable Circumstances. (a) Upon Contractor’s written request and submission of substantiating documentation of a delay resulting from an Uncontrollable Circumstance, the City Representative shall give Contractor a non-compensable extension of time. Contractor shall submit a written request within seven days of the commencement of the Uncontrolled Circumstance.