Common use of Use of Pre-COD Security to Pay Delay Damages Clause in Contracts

Use of Pre-COD Security to Pay Delay Damages. If the Commercial Operation Date occurs after the Expected Commercial Operation Date and Seller has failed to pay any Delay Damages when due under Section 3.1.13, PGE shall be entitled to and shall draw upon the Pre-COD Security an amount equal to the Delay Damages until such time as the Pre-COD Security is exhausted. PGE shall also be entitled to draw upon the Pre-COD Security for Contract Termination Damages.

Appears in 4 contracts

Samples: Wholesale Renewable Power Purchase Agreement, Wholesale Renewable Power Purchase Agreement, Wholesale Renewable Power Purchase Agreement

AutoNDA by SimpleDocs

Use of Pre-COD Security to Pay Delay Damages. If the Commercial Operation Date occurs after the Expected Commercial Operation Date and Seller has failed to pay any Delay Damages when due under Section 3.1.13, PGE shall be entitled to and shall draw upon the Pre-Pre- COD Security an amount equal to the Delay Damages until such time as the Pre-COD Security is exhausted. PGE shall also be entitled to draw upon the Pre-COD Security for Contract Termination Damages.

Appears in 1 contract

Samples: Wholesale Renewable Power Purchase Agreement

AutoNDA by SimpleDocs
Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!