Common use of Value of Omitted and Extra Work Clause in Contracts

Value of Omitted and Extra Work. (1) The amount by which the Contract consideration is to be increased or decreased by any Change Order or Field Order shall be determined by the Fund by one or more of the following methods: a. By applying the applicable price or prices set forth on the attached Schedule "I" of this Agreement or by applying a unit price agreed to by both parties. Subject to the provisions of Section 4.04, this method must be used if the Contract Documents contain applicable unit prices. b. By estimating the fair and reasonable cost of: (i) labor, including all wages, required wage supplements and insurance required by law (workers' compensation, social security, disability, unemployment, etc.) paid to or on behalf of foremen, workers and other employees below the rank of superintendent directly employed at the site of the Project; (ii) materials; and (iii) equipment, excluding hand tools, which, in the judgment of the Fund, would have been or will be employed exclusively and directly on the omitted work or extra work, as the case may be; and, in the case of extra work, where the same is performed directly by the Contractor, by adding to the total of such estimated costs a sum equal to 15 percent thereof, but, where the extra work is performed by a subcontractor, by adding a sum equal to 15 percent of said costs for the benefit of such subcontractor, and by adding, for the benefit of the Contractor (no further allowance will be made where extra work is performed by the sub- subcontractor), an additional sum equal to 10 percent of the first $10,000 of the above-estimated costs, including the subcontractor's percentage override, plus 5 percent of the next $90,000 of the total of said items, plus 3 percent of any sum in excess of $100,000 of the total of said items. There is no markup on the premium portion of overtime labor. For the purposes of the aforesaid percentage overrides, the words "extra work" shall be defined as a complete item of added, modified or changed work as described in the Consultant's written instructions to the Contractor. Such "extra work" may include the work of one or more trades and/or subcontractors or sub-subcontractors and shall include all labor, materials, plant, equipment, tools and all incidentals directly and/or indirectly necessary, related, involved in or convenient to the successful completion of the extra work item. Where the Consultant's aforesaid written instructions to the Contractor involve both an increase and a reduction in similar or related work, the above percentage overrides will be applied only on the amount, if any, the cost of the increased work exceeds the cost of the reduced work. No overhead and profit shall be retained by the Contractor on the cost of work determined by the method provided in Subparagraph (1)a. All profit, overhead and expense of whatsoever kind and nature, other than those set forth above in items (i) through (iii), of the Contractor, its subcontractors and sub-subcontractors, are covered by the aforesaid percentage overrides and no additional payment therefor will be made by the Fund. The Fund may make such cost estimate either before or after the extra work is completed by the Contractor. c. By determining the actual cost of the extra work in the same manner as in the above subdivision b except that actual costs of the Contractor shall be utilized in lieu of estimated costs. The Fund shall have the option to utilize this method provided it notifies the Contractor of its intent to do so prior to the time the Contractor commences performance of such extra work. (2) Irrespective of the method used or to be used by the Fund in determining the value of a Change Order or Field Order, the Contractor, within fifteen (15) working days after a request for the same, must submit to the Fund and the Consultant a detailed breakdown of the Contractor's estimate of the value of the omitted and/or extra work. All change and field orders must be prepared and submitted using the Fund’s Open Item Log (OIL) System. (3) Equipment Watch Rental Rate Blue Book (published online by Intertec Penton Media, Inc.) or other published rates as approved by the Fund in writing, will be utilized for the equipment rental pricing. For the purposes of paragraph (1) hereof, the cost of equipment shall be determined, irrespective of the actual price for any rental or actual cost associated with such equipment as follows: take the monthly rate listed in Equipment Watch and dividing the same by 176 hours to establish an hourly rate and then multiplying such hourly rate by the actual number of hours that the equipment was used. The Contractor will submit an actual rental invoice, or acceptable quotation from a bonafide equipment rental supplier for rented equipment when equipment is not owned by the Contractor. The equipment rental supplier cannot be an “affiliate” of the Contractor, nor in any way be related to the Contractor. If submitted invoices/quotations are acceptable to the Fund, the Contractor will be reimbursed the actual rental cost including sales tax and appropriate mark-up. If no listing of rates for an item of equipment is contained in Equipment Watch, the Fund shall determine the reasonable rate of rental of the particular item of equipment by such other means as it finds appropriate. The edition Equipment Watch to be used shall be that in effect on the date of the receipt of bids for this Contract. None of the provisions of Equipment Watch shall be deemed referred to or included in this Contract excepting only the aforesaid monthly rates. To the cost of equipment as determined above, there is to be added the actual cost of gasoline, oil, grease and maintenance required for operation of such equipment and, in the case of equipment utilized only for extra work when, in the opinion of the Consultant, suitable equipment therefor was not available on the site, the reasonable cost of transporting said equipment to and from the site. Notwithstanding the foregoing, if the Consultant should determine that the nature or size of the equipment used by the Contractor in connection with the extra work is larger or more elaborate, as the case may be, than the size or nature of the minimum equipment determined by the Consultant to be suitable for the extra work, the cost of equipment will not be based upon the equipment used by the Contractor but instead will be based on the smallest or least elaborate equipment determined by the Consultant to have been suitable for the performance of the extra work. (4) Unless otherwise specifically provided for in a Change Order or Field Order, the compensation specified therein for extra work includes full payment for both the extra work covered thereby and for any damage or expense caused the Contractor by any delays to other work to be done under the Contract resulting from or on account of said extra work, and the Contractor waives all rights to any other compensation for said extra work, damage or expense.

Appears in 2 contracts

Samples: Construction Contract, Construction Contract

AutoNDA by SimpleDocs

Value of Omitted and Extra Work. (1) The amount by which the Contract consideration is to be increased or decreased by any Change Order or Field Order shall be determined by the Fund by one or more of the following methods: a. By applying the applicable price or prices set forth on the attached Schedule "I" of this Agreement or by applying a unit price agreed to by both parties. Subject to the provisions of Section 4.04, this method must be used if the Contract Documents contain applicable unit prices. b. By estimating the fair and reasonable cost of: (i) labor, including all wages, required wage supplements and insurance required by law (workers' compensation, social security, disability, unemployment, etc.) paid to or on behalf of foremen, workers and other employees below the rank of superintendent directly employed at the site of the Project; (ii) materials; and (iii) equipment, excluding hand tools, which, in the judgment of the Fund, would have been or will be employed exclusively and directly on the omitted work or extra work, as the case may be; and, in the case of extra work, where the same is performed directly by the Contractor, by adding to the total of such estimated costs a sum equal to 15 percent thereof, but, where the extra work is performed by a subcontractor, by adding a sum equal to 15 percent of said costs for the benefit of such subcontractor, and by adding, for the benefit of the Contractor (no further allowance will be made where extra work is performed by the sub- sub-subcontractor), an additional sum equal to 10 percent of the first $10,000 of the above-estimated costs, including the subcontractor's percentage override, plus 5 percent of the next $90,000 of the total of said items, plus 3 percent of any sum in excess of $100,000 of the total of said items. There is no markup on the premium portion of overtime labor. For the purposes of the aforesaid percentage overrides, the words "extra work" shall be defined as a complete item of added, modified or changed work as described in the Consultant's written instructions to the Contractor. Such "extra work" may include the work of one or more trades and/or subcontractors or sub-subcontractors and shall include all labor, materials, plant, equipment, tools and all incidentals directly and/or indirectly necessary, related, involved in or convenient to the successful completion of the extra work item. Where the Consultant's aforesaid written instructions to the Contractor involve both an increase and a reduction in similar or related work, the above percentage overrides will be applied only on the amount, if any, the cost of the increased work exceeds the cost of the reduced work. No overhead and profit shall be retained by the Contractor on the cost of work determined by the method provided in Subparagraph (1)a. All profit, overhead and expense of whatsoever kind and nature, other than those set forth above in items (i) through (iii), of the Contractor, its subcontractors and sub-subcontractors, are covered by the aforesaid percentage overrides and no additional payment therefor will be made by the Fund. The Fund may make such cost estimate either before or after the extra work is completed by the Contractor. c. By determining the actual cost of the extra work in the same manner as in the above subdivision b except that actual costs of the Contractor shall be utilized in lieu of estimated costs. The Fund shall have the option to utilize this method provided it notifies the Contractor of its intent to do so prior to the time the Contractor commences performance of such extra work. (2) Irrespective of the method used or to be used by the Fund in determining the value of a Change Order or Field Order, the Contractor, within fifteen (15) working days after a request for the same, must submit to the Fund and the Consultant a detailed breakdown of the Contractor's estimate of the value of the omitted and/or extra work. All change and field orders must be prepared and submitted using the Fund’s Open Item Log (OIL) System. (3) Equipment Watch Rental Rate Blue Book (published online by Intertec Penton Media, Inc.) or other published rates as approved by the Fund in writing, will be utilized for the equipment rental pricing. For the purposes of paragraph (1) hereof, the cost of equipment shall be determined, irrespective of the actual price for any rental or actual cost associated with such equipment as follows: take the monthly rate listed in Equipment Watch and dividing the same by 176 hours to establish an hourly rate and then multiplying such hourly rate by the actual number of hours that the equipment was used. The Contractor will submit an actual rental invoice, or acceptable quotation from a bonafide equipment rental supplier for rented equipment when equipment is not owned by the Contractor. The equipment rental supplier cannot be an “affiliate” of the Contractor, nor in any way be related to the Contractor. If submitted invoices/quotations are acceptable to the Fund, the Contractor will be reimbursed the actual rental cost including sales tax and appropriate markxxxx-up. If no listing of rates for an item of equipment is contained in Equipment Watch, the Fund shall determine the reasonable rate of rental of the particular item of equipment by such other means as it finds appropriate. The edition Equipment Watch to be used shall be that in effect on the date of the receipt of bids for this Contract. None of the provisions of Equipment Watch shall be deemed referred to or included in this Contract excepting only the aforesaid monthly rates. To the cost of equipment as determined above, there is to be added the actual cost of gasoline, oil, grease and maintenance required for operation of such equipment and, in the case of equipment utilized only for extra work when, in the opinion of the Consultant, suitable equipment therefor was not available on the site, the reasonable cost of transporting said equipment to and from the site. Notwithstanding the foregoing, if the Consultant should determine that the nature or size of the equipment used by the Contractor in connection with the extra work is larger or more elaborate, as the case may be, than the size or nature of the minimum equipment determined by the Consultant to be suitable for the extra work, the cost of equipment will not be based upon the equipment used by the Contractor but instead will be based on the smallest or least elaborate equipment determined by the Consultant to have been suitable for the performance of the extra work. (4) Unless otherwise specifically provided for in a Change Order or Field Order, the compensation specified therein for extra work includes full payment for both the extra work covered thereby and for any damage or expense caused the Contractor by any delays to other work to be done under the Contract resulting from or on account of said extra work, and the Contractor waives all rights to any other compensation for said extra work, damage or expense.

Appears in 1 contract

Samples: Construction Contract

Value of Omitted and Extra Work. (1) The amount by which the Contract consideration is to be increased or decreased by any Change Order or Field Order shall be determined by the Fund by one or more of the following methods: a. By applying the applicable price or prices set forth on the attached Schedule "I" of this Agreement or by applying a unit price agreed to by both parties. Subject to the provisions of Section 4.04, this method must be used if the Contract Documents contain applicable unit prices. b. By estimating the fair and reasonable cost of: (i) labor, including all wages, required wage supplements and insurance required by law (workers' compensation, social security, disability, unemployment, etc.) paid to or on behalf of foremen, workers and other employees below the rank of superintendent directly employed at the site of the Project; (ii) materials; and (iii) equipment, excluding hand tools, which, in the judgment of the Fund, would have been or will be employed exclusively and directly on the omitted work or extra work, as the case may be; and, in the case of extra work, where the same is performed directly by the Contractor, by adding to the total of such estimated costs a sum equal to 15 percent thereof, but, where the extra work is performed by a subcontractor, by adding a sum equal to 15 percent of said costs for the benefit of such subcontractor, and by adding, for the benefit of the Contractor (no further allowance will be made where extra work is performed by the sub- subcontractor), an additional sum equal to 10 percent of the first $10,000 of the above-estimated costs, including the subcontractor's percentage override, plus 5 percent of the next $90,000 of the total of said items, plus 3 percent of any sum in excess of $100,000 of the total of said items. There is no markup on the premium portion of overtime labor. For the purposes of the aforesaid percentage overrides, the words "extra work" shall be defined as a complete item of added, modified or changed work as described in the Consultant's written instructions to the Contractor. Such "extra work" may include the work of one or more trades and/or subcontractors or sub-subcontractors and shall include all labor, materials, plant, equipment, tools and all incidentals directly and/or indirectly necessary, related, involved in or convenient to the successful completion of the extra work item. Where the Consultant's aforesaid written instructions to the Contractor involve both an increase and a reduction in similar or related work, the above percentage overrides will be applied only on the amount, if any, the cost of the increased work exceeds the cost of the reduced work. No overhead and profit shall be retained by the Contractor on the cost of work determined by the method provided in Subparagraph (1)a. All profit, overhead and expense of whatsoever kind and nature, other than those set forth above in items (i) through (iii), of the Contractor, its subcontractors and sub-subcontractors, are covered by the aforesaid percentage overrides and no additional payment therefor will be made by the Fund. The Fund may make such cost estimate either before or after the extra work is completed by the Contractor. c. By determining the actual cost of the extra work in the same manner as in the above subdivision b except that actual costs of the Contractor shall be utilized in lieu of estimated costs. The Fund shall have the option to utilize this method provided it notifies the Contractor of its intent to do so prior to the time the Contractor commences performance of such extra work. (2) Irrespective of the method used or to be used by the Fund in determining the value of a Change Order or Field Order, the Contractor, within fifteen (15) working days after a request for the same, must submit to the Fund and the Consultant a detailed breakdown of the Contractor's estimate of the value of the omitted and/or extra work. All change and field orders must be prepared and submitted using the Fund’s Open Item Log (OIL) System. (3) Equipment Watch Rental Rate The “Blue Book Book” (published online by Intertec Penton Media, Inc.Publishing) or other published rates as approved by the Fund in writing, will be utilized exclusively for the equipment rental pricing. For the purposes of paragraph (1) hereof, the cost of equipment shall be determined, irrespective of the actual price for any rental or actual cost associated with such equipment as follows: take for the first 40 hours of use by taking the monthly rate listed in Equipment Watch the "Blue Book" and dividing the same by 176 hours to establish an hourly rate and then multiplying such hourly rate by the actual number of hours that the equipment was used. The Contractor will submit an actual rental invoice, or acceptable quotation from a bonafide equipment rental supplier for rented equipment when equipment is not owned by the Contractor. The equipment rental supplier cannot be an “affiliate” of the Contractor, nor in any way be related to the Contractor. If submitted invoices/quotations are acceptable to the Fund, the Contractor will be reimbursed the actual rental cost including sales tax and appropriate markxxxx-up. If no listing of rates for an item of equipment is contained in Equipment Watchthe "Blue Book", the Fund shall determine the reasonable rate of rental of the particular item of equipment by such other means as it finds appropriate. The edition Equipment Watch of the "Blue Book" to be used shall be that in effect on the date of the receipt of bids for this Contract. None of the provisions of Equipment Watch the "Blue Book" shall be deemed referred to or included in this Contract excepting only the aforesaid monthly rates. To the cost of equipment as determined above, there is to be added the actual cost of gasoline, oil, grease and maintenance required for operation of such equipment and, in the case of equipment utilized only for extra work when, in the opinion of the Consultant, suitable equipment therefor was not available on the site, the reasonable cost of transporting said equipment to and from the site. Notwithstanding the foregoing, if the Consultant should determine that the nature or size of the equipment used by the Contractor in connection with the extra work is larger or more elaborate, as the case may be, than the size or nature of the minimum equipment determined by the Consultant to be suitable for the extra work, the cost of equipment will not be based upon the equipment used by the Contractor but instead will be based on the smallest or least elaborate equipment determined by the Consultant to have been suitable for the performance of the extra work. (4) Unless otherwise specifically provided for in a Change Order or Field Order, the compensation specified therein for extra work includes full payment for both the extra work covered thereby and for any damage or expense caused the Contractor by any delays to other work to be done under the Contract resulting from or on account of said extra work, and the Contractor waives all rights to any other compensation for said extra work, damage or expense.

Appears in 1 contract

Samples: Construction Contract

Value of Omitted and Extra Work. (1) The amount by which the Contract consideration is to be increased or decreased by any Change Order or Field Order shall be determined by the Fund by one or more of the following methods: a. By applying the applicable price or prices set forth on the attached Schedule "I" of this Agreement or by applying a unit price agreed to by both parties. Subject to the provisions of Section 4.04, this method must be used if the Contract Documents contain applicable unit prices. b. By estimating the fair and reasonable cost of: (i) labor, including all wages, required wage supplements and insurance required by law (workers' compensation, social security, disability, unemployment, etc.) paid to or on behalf of foremen, workers and other employees below the rank of superintendent directly employed at the site of the Project; (ii) materials; and (iii) equipment, excluding hand tools, which, in the judgment of the Fund, would have been or will be employed exclusively and directly on the omitted work or extra work, as the case may be; and, in the case of extra work, where the same is performed directly by the Contractor, by adding to the total of such estimated costs a sum equal to 15 percent thereof, but, where the extra work is performed by a subcontractor, by adding a sum equal to 15 percent of said costs for the benefit of such subcontractor, and by adding, for the benefit of the Contractor (no further allowance will be made where extra work is performed by the sub- subcontractor), an additional sum equal to 10 percent of the first $10,000 of the above-estimated costs, including the subcontractor's percentage override, plus 5 percent of the next $90,000 of the total of said items, plus 3 percent of any sum in excess of $100,000 of the total of said items. There is no markup on the premium portion of overtime labor. For the purposes of the aforesaid percentage overrides, the words "extra work" shall be defined as a complete item of added, modified or changed work as described in the Consultant's written instructions to the Contractor. Such "extra work" may include the work of one or more trades and/or subcontractors or sub-subcontractors and shall include all labor, materials, plant, equipment, tools and all incidentals directly and/or indirectly necessary, related, involved in or convenient to the successful completion of the extra work item. Where the Consultant's aforesaid written instructions to the Contractor involve both an increase and a reduction in similar or related work, the above percentage overrides will be applied only on the amount, if any, the cost of the increased work exceeds the cost of the reduced work. No overhead and profit shall be retained by the Contractor on the cost of work determined by the method provided in Subparagraph (1)a. All profit, overhead and expense of whatsoever kind and nature, other than those set forth above in items (i) through (iii), of the Contractor, its subcontractors and sub-subcontractors, are covered by the aforesaid percentage overrides and no additional payment therefor will be made by the Fund. The Fund may make such cost estimate either before or after the extra work is completed by the Contractor. c. By determining the actual cost of the extra work in the same manner as in the above subdivision b except that actual costs of the Contractor shall be utilized in lieu of estimated costs. The Fund shall have the option to utilize this method provided it notifies the Contractor of its intent to do so prior to the time the Contractor commences performance of such extra work. (2) Irrespective of the method used or to be used by the Fund in determining the value of a Change Order or Field Order, the Contractor, within fifteen (15) working days after a request for the same, must submit to the Fund and the Consultant a detailed breakdown of the Contractor's estimate of the value of the omitted and/or extra work. All change and field orders must be prepared and submitted using the Fund’s Open Item Log (OIL) System. (3) Equipment Watch Rental Rate Blue Book (published online by Intertec Penton Media, Inc.) or other published rates as approved by the Fund in writing, will be utilized for the equipment rental pricing. For the purposes of paragraph (1) hereof, the cost of equipment shall be determined, irrespective of the actual price for any rental or actual cost associated with such equipment as follows: take the monthly rate listed in Equipment Watch and dividing the same by 176 hours to establish an hourly rate and then multiplying such hourly rate by the actual number of hours that the equipment was used. The Contractor will submit an actual rental invoice, or acceptable quotation from a bonafide equipment rental supplier for rented equipment when equipment is not owned by the Contractor. The equipment rental supplier cannot be an “affiliate” of the Contractor, nor in any way be related to the Contractor. If submitted invoices/quotations are acceptable to the Fund, the Contractor will be reimbursed the actual rental cost including sales tax and appropriate markxxxx-up. If no listing of rates for an item of equipment is contained in Equipment Watch, the Fund shall determine the reasonable rate of rental of the particular item of equipment by such other means as it finds appropriate. The edition Equipment Watch to be used shall be that in effect on the date of the receipt of bids for this Contract. None of the provisions of Equipment Watch shall be deemed referred to or included in this Contract excepting only the aforesaid monthly rates. To the cost of equipment as determined above, there is to be added the actual cost of gasoline, oil, grease and maintenance required for operation of such equipment and, in the case of equipment utilized only for extra work when, in the opinion of the Consultant, suitable equipment therefor was not available on the site, the reasonable cost of transporting said equipment to and from the site. Notwithstanding the foregoing, if the Consultant should determine that the nature or size of the equipment used by the Contractor in connection with the extra work is larger or more elaborate, as the case may be, than the size or nature of the minimum equipment determined by the Consultant to be suitable for the extra work, the cost of equipment will not be based upon the equipment used by the Contractor but instead will be based on the smallest or least elaborate equipment determined by the Consultant to have been suitable for the performance of the extra work. (4) Unless otherwise specifically provided for in a Change Order or Field Order, the compensation specified therein for extra work includes full payment for both the extra work covered thereby and for any damage or expense caused the Contractor by any delays to other work to be done under the Contract resulting from or on account of said extra work, and the Contractor waives all rights to any other compensation for said extra work, damage or expense.

Appears in 1 contract

Samples: Construction Contract

AutoNDA by SimpleDocs

Value of Omitted and Extra Work. (1) The amount by which the Contract consideration is to be increased or decreased by any Change Order or Field Order shall be determined by the Fund by one or more of the following methods: a. By applying the applicable price or prices set forth on the attached Schedule "I" of this Agreement or by applying a unit price agreed to by both parties. Subject to the provisions of Section 4.04, this method must be used if the Contract Documents contain applicable unit prices. b. By estimating the fair and reasonable cost of: (i) labor, including all wages, required wage supplements and insurance required by law (workers' compensation, social security, disability, unemployment, etc.) paid to or on behalf of foremen, workers and other employees below the rank of superintendent directly employed at the site of the Project; (ii) materials; and (iii) equipment, excluding hand tools, which, in the judgment of the Fund, would have been or will be employed exclusively and directly on the omitted work or extra work, as the case may be; and, in the case of extra work, where the same is performed directly by the Contractor, by adding to the total of such estimated costs a sum equal to 15 percent thereof, but, where the extra work is performed by a subcontractor, by adding a sum equal to 15 percent of said costs for the benefit of such subcontractor, and by adding, for the benefit of the Contractor (no further allowance will be made where extra work is performed by the sub- sub-subcontractor), an additional sum equal to 10 percent of the first $10,000 of the above-estimated costs, including the subcontractor's percentage override, plus 5 percent of the next $90,000 of the total of said items, plus 3 percent of any sum in excess of $100,000 of the total of said items. There is no markup on the premium portion of overtime labor. For the purposes of the aforesaid percentage overrides, the words "extra work" shall be defined as a complete item of added, modified or changed work as described in the Consultant's written instructions to the Contractor. Such "extra work" may include the work of one or more trades and/or subcontractors or sub-subcontractors and shall include all labor, materials, plant, equipment, tools and all incidentals directly and/or indirectly necessary, related, involved in or convenient to the successful completion of the extra work item. Where the Consultant's aforesaid written instructions to the Contractor involve both an increase and a reduction in similar or related work, the above percentage overrides will be applied only on the amount, if any, the cost of the increased work exceeds the cost of the reduced work. No overhead and profit shall be retained by the Contractor on the cost of work determined by the method provided in Subparagraph (1)a. All profit, overhead and expense of whatsoever kind and nature, other than those set forth above in items (i) through (iii), of the Contractor, its subcontractors and sub-subcontractors, are covered by the aforesaid percentage overrides and no additional payment therefor will be made by the Fund. The Fund may make such cost estimate either before or after the extra work is completed by the Contractor. c. By determining the actual cost of the extra work in the same manner as in the above subdivision b except that actual costs of the Contractor shall be utilized in lieu of estimated costs. The Fund shall have the option to utilize this method provided it notifies the Contractor of its intent to do so prior to the time the Contractor commences performance of such extra work. (2) Irrespective of the method used or to be used by the Fund in determining the value of a Change Order or Field Order, the Contractor, within fifteen (15) working days after a request for the same, must submit to the Fund and the Consultant a detailed breakdown of the Contractor's estimate of the value of the omitted and/or extra work. All change and field orders must be prepared and submitted using the Fund’s Open Item Log (OIL) System. (3) Equipment Watch Rental Rate The “Blue Book Book” (published online by Intertec Penton Media, Inc.Publishing) or other published rates as approved by the Fund in writing, will be utilized exclusively for the equipment rental pricing. For the purposes of paragraph (1) hereof, the cost of equipment shall be determined, irrespective of the actual price for any rental or actual cost associated with such equipment as follows: take for the first 40 hours of use by taking the monthly rate listed in Equipment Watch the "Blue Book" and dividing the same by 176 hours to establish an hourly rate and then multiplying such hourly rate by the actual number of hours that the equipment was used. The Contractor will submit an actual rental invoice, or acceptable quotation from a bonafide equipment rental supplier for rented equipment when equipment is not owned by the Contractor. The equipment rental supplier cannot be an “affiliate” of the Contractor, nor in any way be related to the Contractor. If submitted invoices/quotations are acceptable to the Fund, the Contractor will be reimbursed the actual rental cost including sales tax and appropriate markxxxx-up. If no listing of rates for an item of equipment is contained in Equipment Watchthe "Blue Book", the Fund shall determine the reasonable rate of rental of the particular item of equipment by such other means as it finds appropriate. The edition Equipment Watch of the "Blue Book" to be used shall be that in effect on the date of the receipt of bids for this Contract. None of the provisions of Equipment Watch the "Blue Book" shall be deemed referred to or included in this Contract excepting only the aforesaid monthly rates. To the cost of equipment as determined above, there is to be added the actual cost of gasoline, oil, grease and maintenance required for operation of such equipment and, in the case of equipment utilized only for extra work when, in the opinion of the Consultant, suitable equipment therefor was not available on the site, the reasonable cost of transporting said equipment to and from the site. Notwithstanding the foregoing, if the Consultant should determine that the nature or size of the equipment used by the Contractor in connection with the extra work is larger or more elaborate, as the case may be, than the size or nature of the minimum equipment determined by the Consultant to be suitable for the extra work, the cost of equipment will not be based upon the equipment used by the Contractor but instead will be based on the smallest or least elaborate equipment determined by the Consultant to have been suitable for the performance of the extra work. (4) Unless otherwise specifically provided for in a Change Order or Field Order, the compensation specified therein for extra work includes full payment for both the extra work covered thereby and for any damage or expense caused the Contractor by any delays to other work to be done under the Contract resulting from or on account of said extra work, and the Contractor waives all rights to any other compensation for said extra work, damage or expense.

Appears in 1 contract

Samples: Construction Contract

Value of Omitted and Extra Work. (1) The amount by which the Contract consideration is to be increased or decreased by any Change Order or Field Order shall be determined by the Fund University by one or more of the following methods: a. By accepting an amount agreed upon by both parties, which amount is to be calculated in a manner similar to that provided in subdivision c hereof. b. By applying the applicable price or prices set forth on in the attached Schedule "I" of this Agreement or by applying a unit price agreed to by both parties. Subject to the provisions of Section Sections 4.04, this method must be used if the Contract Documents contain applicable unit prices. b. c. By estimating the fair and reasonable cost of: (i) labor, including all wages, required wage supplements and insurance required by law (workers' compensation, social security, disability, unemployment, etc.) paid to or on behalf of foremen, workers and other employees below the rank of superintendent directly employed at the site of the Project; (ii) materials; and (iii) equipment, excluding hand tools, which, in the judgment of the FundUniversity, would have been or will be employed exclusively and directly on the omitted work or extra work, as the case may be; and, in the case of extra work, where the same is performed directly by the Contractor, by adding to the total of such estimated costs a sum equal to 15 percent thereof, but, where the extra work is performed by a subcontractor, by adding a sum equal to 15 percent of said costs for the benefit of such subcontractor, and by adding, for the benefit of the Contractor (no further allowance will be made where extra work is performed by the sub- subcontractorsub‑subcontractor), an additional sum equal to 10 percent of the first $10,000 of the above-estimated above‑estimated costs, including the subcontractor's percentage override, plus 5 percent of the next $90,000 of the total of said items, plus 3 percent of any sum in excess of $100,000 of the total of said items. There is no markup on the premium portion of overtime labor. For the purposes of the aforesaid percentage overrides, the words "extra work" shall be defined as a complete item of added, modified or changed work as described in the Consultant's written instructions to the Contractor. Such "extra work" may include the work of one or more trades and/or subcontractors or sub-subcontractors sub‑subcontractors and shall include all labor, materials, plant, equipment, tools and all incidentals directly and/or indirectly necessary, related, involved in or convenient to the successful completion of the extra work item. Where the Consultant's aforesaid written instructions to the Contractor involve both an increase and a reduction in similar or related work, the above percentage overrides will be applied only on the amount, if any, the cost of the increased work exceeds the cost of the reduced work. No overhead and profit shall be retained by the Contractor on the cost of work determined by the method provided in Subparagraph (1)a. All profit, overhead and expense of whatsoever kind and nature, other than those set forth above in items (i) through (iii), of the Contractor, its subcontractors and sub-subcontractorssub‑subcontractors, are covered by the aforesaid percentage overrides and no additional payment therefor therefore will be made by the FundUniversity. The Fund University may make such cost estimate either before or after the extra work is completed by the Contractor. c. d. By determining the actual cost of the extra work in the same manner as in the above subdivision b c except that actual costs of the Contractor shall be utilized in lieu of estimated costs. The Fund University shall have the option to utilize of utilizing this method provided it notifies the Contractor of its intent to do so prior to the time the Contractor commences performance of such extra work. (2) Irrespective of the method used or to be used by the Fund University in determining the value of a Change Order or Field Order, the Contractor, within fifteen (15) working days after a request for the same, must submit to the Fund University and the Consultant a detailed breakdown of the Contractor's estimate of the value of the omitted and/or extra work. All change and field orders must be prepared and submitted using the Fund’s Open Item Log (OIL) System. (3) Equipment Watch Rental Rate Blue Book (published online by Intertec Penton Media, Inc.) or other published rates as approved by the Fund in writing, will be utilized for the equipment rental pricing. For the purposes of paragraph (1) hereof, the cost of equipment shall be determined, irrespective of the actual price for any rental or actual cost associated with such equipment and irrespective of whether the equipment is or is not owned by the Contractor, as follows: take (a) for the first 40 hours of use by taking the monthly rate listed in the "Green Book" (the publication of the Associated Equipment Watch Distributors of Oakbrook, Illinois) and dividing the same by 176 hours to establish an hourly rate and then multiplying such hourly rate by the actual number of hours that the equipment was used. The Contractor will submit an actual rental invoice; and (b) for any period of time in excess of the first 40 hours of use by taking 50 percent of the hourly rate established in accordance with the above for equipment used for periods of less than 40 hours, or acceptable quotation from a bonafide equipment rental supplier for rented equipment when equipment is not owned and then multiplying such rate by the Contractoractual number of hours in excess of 40 hours that the equipment was used. The In the event that the "Green Book" does not list the item of equipment rental supplier cannot be an “affiliate” of the Contractor, nor in any way be related to the Contractor. If submitted invoices/quotations are acceptable to the Fundused, the Contractor will applicable rate shall be reimbursed determined in the actual rental cost including sales tax and appropriate mark-upsame manner as that set forth above except that the monthly rate shall be that set forth in the "Blue Book" (published by Equipment Guidebook Co. of Palo Alto, California). If no listing of or rates for an item of equipment is contained in Equipment Watcheither the "Green Book" or the "Blue Book", the Fund University shall determine the reasonable rate of rental of the particular item of equipment by such other means as it finds appropriate. The edition Equipment Watch editions of the "Green Book" and the "Blue Book" to be used shall be that those in effect on the date of the receipt of bids for this Contract. None of the provisions of Equipment Watch the "Green Book" or the "Blue Book" shall be deemed referred to or included in this Contract excepting only the aforesaid monthly rates. To the cost of equipment as determined above, there is to be added the actual cost of gasoline, oil, grease and maintenance required for operation of such equipment and, in the case of equipment utilized only for extra work when, in the opinion of the Consultant, suitable equipment therefor therefore was not available on the site, the reasonable cost of transporting said equipment to and from the site. Notwithstanding the foregoing, if the Consultant should determine that the nature or size of the equipment used by the Contractor in connection with the extra work is larger or more elaborate, as the case may be, than the size or nature of the minimum equipment determined by the Consultant to be suitable for the extra work, the cost of equipment will not be based upon the equipment used by the Contractor but instead will be based on the smallest or least elaborate equipment determined by the Consultant to have been suitable for the performance of the extra work. (4) Unless otherwise specifically provided for in a Change Order or Field Order, the compensation specified therein for extra work includes full payment for both the extra work covered thereby and for any damage or expense caused the Contractor by any delays to other work to be done under the Contract resulting from or on account of said extra work, and the Contractor waives all rights to any other compensation for said extra work, damage or expense.

Appears in 1 contract

Samples: Construction Contract

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!