Variation Order Procedure. 21.4.1. If the IAA requests a proposal, prior to instructing a Variation Order, the Supplier shall respond in writing as soon as practicable but in any event within the time stipulated by the IAA, by submitting: 21.4.1.1. a detailed evaluation of the work to be performed and a plan for its execution; 21.4.1.2. the effect of the Variation on the Works and on the Project, including any effect on the Schedule and on the Approved Project Execution Plan; and 21.4.1.3. an estimation of the costs associated with such Variation, including working hours and prices of all Components, all in accordance with Section 21.5 below. 21.4.2. The IAA shall, as soon as practicable after receiving such proposal, respond with approval, disapproval or comments and request from the Supplier to make amendments thereto. The Supplier shall not delay any work whilst awaiting a response. 21.4.3. Each instruction to execute a Variation shall be issued as a Variation Order by the IAA to the Supplier, who shall acknowledge receipt. Upon receipt of a Variation Order, the Supplier shall forthwith proceed to carry out the Variation and be bound to the terms and conditions of the Contract in doing so as if such Variation was required under the Contract. 21.4.4. It is hereby agreed that the IAA shall decide, at his sole discretion, whether to ask for such proposal or not, and the Supplier shall in any event be obliged to execute each and every Variation instructed by the IAA. Furthermore it is clarified that nothing herein shall be construed as imposing any obligation on the Supplier to issue a Variation Order.
Appears in 1 contract
Samples: Contract for Design, Supply, Installation, Commissioning and Support of Passenger Boarding Bridges
Variation Order Procedure. 21.4.1. If the IAA requests a proposal, prior to instructing a Variation Order, the Supplier shall respond in writing as soon as practicable but in any event within the time stipulated by the IAA, by submitting:
21.4.1.1. a detailed evaluation of the work to be performed and a plan for its execution;
21.4.1.2. the effect of the Variation on the Works and on the Project, including any effect on the Schedule Time for Completion and on the Approved Project Execution PlanDetailed Schedule; and
21.4.1.3. an estimation of the costs associated with such Variation, including working hours and prices of all Components, all in accordance with Section 21.5 below.
21.4.2. The IAA shall, as soon as practicable after receiving such proposal, respond with approval, disapproval or comments and request from the Supplier to make amendments thereto. The Supplier shall not delay any work whilst awaiting a response.
21.4.3. Each instruction to execute a Variation shall be issued as a Variation Order by the IAA to the Supplier, who shall acknowledge receipt. Upon receipt of a Variation Order, the Supplier shall forthwith proceed to carry out the Variation and be bound to the terms and conditions of the Contract in doing so as if such Variation was required under the Contract.
21.4.4. It is hereby agreed that the IAA shall decide, at his sole discretion, whether to ask for such proposal or not, and the Supplier shall in any event be obliged to execute each and every Variation instructed by the IAA. Furthermore it is clarified that nothing herein shall be construed as imposing any obligation on the Supplier IAA to issue a Variation Order.
Appears in 1 contract
Variation Order Procedure. 21.4.122.4.1. If the IAA requests a proposal, prior to instructing a Variation Order, the Supplier shall respond in writing as soon as practicable but in any event within the time stipulated by the IAA, by submitting:
21.4.1.122.4.1.1. a detailed evaluation of the work to be performed and a plan for its execution;
21.4.1.222.4.1.2. the effect of the Variation on the Works and on the Project, including any effect on the Schedule Time for Completion and on the Approved Project Execution Plan; and
21.4.1.322.4.1.3. an estimation of the costs associated with such Variation, including working hours and prices of all Components, all in accordance with Section 21.5 22.5 below.
21.4.222.4.2. The IAA shall, as soon as practicable after receiving such proposal, respond with approval, disapproval or comments and request from the Supplier to make amendments thereto. The Supplier shall not delay any work whilst awaiting a response.
21.4.322.4.3. Each instruction to execute a Variation shall be issued as a Variation Order by the IAA to the Supplier, who shall acknowledge receipt. Upon receipt of a Variation Order, the Supplier shall forthwith proceed to carry out the Variation and be bound to the terms and conditions of the Contract in doing so as if such Variation was required under the Contract.
21.4.422.4.4. It is hereby agreed that the IAA shall decide, at his sole discretion, whether to ask for such proposal or not, and the Supplier shall in any event be obliged to execute each and every Variation instructed by the IAA. Furthermore it is clarified that nothing herein shall be construed as imposing any obligation on the Supplier to issue a Variation Order.
Appears in 1 contract
Variation Order Procedure. 21.4.122.4.1. If the IAA requests a proposal, prior to instructing a Variation Order, the Supplier shall respond in writing as soon as practicable but in any event within the time stipulated by the IAA, by submitting:
21.4.1.122.4.1.1. a detailed evaluation of the work to be performed and a plan for its execution;
21.4.1.222.4.1.2. the effect of the Variation on the Works and on the Project, including any effect on the Schedule Time for Completion and on the Approved Project Execution Plan; and
21.4.1.322.4.1.3. an estimation of the costs associated with such Variation, including working hours and prices of all Components, all in accordance with Section 21.5 22.5 below.
21.4.222.4.2. The IAA shall, as soon as practicable after receiving such proposal, respond with approval, disapproval or comments and request from the Supplier to make amendments thereto. The Supplier shall not delay any work whilst awaiting a response.
21.4.322.4.3. Each instruction to execute a Variation shall be issued as a Variation Order by the IAA to the Supplier, who shall acknowledge receipt. Upon receipt of a Variation Order, the Supplier shall forthwith proceed to carry out the Variation and be bound to the terms and conditions of the Contract in doing so as if such Variation was required under the Contract.
21.4.422.4.4. It is hereby agreed that the IAA shall decide, at his sole discretion, whether to ask for such proposal or not, and the Supplier shall in any event be obliged to execute each and every Variation instructed by the IAA. Furthermore it is clarified that nothing herein shall be construed as imposing any obligation on the Supplier IAA to issue a Variation Order.
Appears in 1 contract
Variation Order Procedure. 21.4.115.4.1. If the IAA requests a proposal, prior to instructing a Variation Order, the Supplier Service Provider shall respond in writing as soon as practicable but in any event within the time stipulated by the IAA, by submitting:
21.4.1.1. submitting a detailed evaluation of the work to be performed and a plan for its execution;
21.4.1.2. the effect of the Variation on the Works and on the Projectrequested change, including any the estimated cost and effect on the Schedule and on the Approved Project Execution Plan; and
21.4.1.3. an estimation of the costs associated with such Variation, including working hours and prices of all Components, all in accordance with Section 21.5 belowschedule.
21.4.215.4.2. The IAA shall, as soon as practicable after receiving such proposal, respond with approval, disapproval or comments and request from the Supplier Service Provider to make amendments thereto. The Supplier Service Provider shall not delay any work whilst awaiting a response.
21.4.315.4.3. Each instruction to execute a Variation shall be issued as a Variation Order by the IAA to the SupplierService Provider, who shall acknowledge receipt. Upon receipt of a Variation Order, the Supplier Service Provider shall forthwith proceed to carry out the Variation and be bound to the terms and conditions of the Contract in doing so as if such Variation was required under the Contract.
21.4.415.4.4. It is hereby agreed that the IAA shall decide, at his sole discretion, whether to ask for such proposal or not, and the Supplier Service Provider shall in any event be obliged to execute each and every Variation instructed by the IAA. Furthermore Furthermore, it is clarified that nothing herein shall be construed as imposing any obligation on the Supplier IAA to issue a Variation Order.
Appears in 1 contract
Samples: Professional Services
Variation Order Procedure. 21.4.120.4.1. If the IAA requests a proposal, prior to instructing a Variation Order, the Supplier Contractor shall respond in writing as soon as practicable but in any event within the time stipulated by the IAA, by submitting:
21.4.1.120.4.1.1. a detailed evaluation of the work to be performed and a plan for its execution;
21.4.1.220.4.1.2. the effect of the Variation on the Works and on the Project, including any effect on the Schedule and on the Approved Project Execution PlanTime for Completion; and
21.4.1.320.4.1.3. an estimation of the costs associated with such Variation, including working hours and prices of all Components, all in accordance with Section 21.5 20.5 below.
21.4.220.4.2. The IAA shall, as soon as practicable after receiving such proposal, respond with approval, disapproval or comments and request from the Supplier Contractor to make amendments thereto. The Supplier Contractor shall not delay any work whilst awaiting a response.
21.4.320.4.3. Each instruction to execute a Variation shall be issued as a Variation Order by the IAA to the SupplierContractor, who shall acknowledge receipt. Upon receipt of a Variation Order, the Supplier Contractor shall forthwith proceed to carry out the Variation and be bound to the terms and conditions of the Contract in doing so as if such Variation was required under the Contract.
21.4.420.4.4. It is hereby agreed that the IAA shall decide, at his sole discretion, whether to ask for such proposal or not, and the Supplier Contractor shall in any event be obliged to execute each and every Variation instructed by the IAA. Furthermore it is clarified that nothing herein shall be construed as imposing any obligation on the Supplier Contractor to issue a Variation Order.
Appears in 1 contract
Samples: Contract for Design, Supply, Installation, Commissioning and Maintenance of a Power Plant