Waiver of Claims by Owner. As of the date of the final certificate for payment, the Owner expressly waives and releases the Contractor from all claims against the Contractor including without limitation those that might arise from the negligence or breach of contract by the Contractor except one or more of the following: .1 those made in writing prior to the date of the final certificate for payment and still unsettled; .2 those arising from the provisions of GC 12.1 - INDEMNIFICATION or GC
Appears in 9 contracts
Samples: Construction Contract, Construction Contract, Construction Contract
Waiver of Claims by Owner. As of the date of the final certificate for payment, the Owner expressly waives and releases the Contractor from all claims against the Contractor including without limitation those that might arise from the negligence or breach of contract by the Contractor except one or more of the following:
.1 those made in writing prior to the date of the final certificate for payment and still unsettled; .2 those arising from the provisions of GC 12.1 - INDEMNIFICATION or GC
Appears in 1 contract
Samples: Construction Contract