AGREEMENT made as of the 14th day of April 2005 in the year.
(In words, indicate day, month and year)
(In words, indicate day, month and year)
BETWEEN the Owner:
(Name, address and other information)
(Name, address and other information)
Pointer Ridge Office Investments, LLC
c/o Xx. Xxxx Xxxxx
6166196 Xxxx Xxxx Xxxx
Xxxxx 000
Xxxx Xxxx, XX 00000
c/o Xx. Xxxx Xxxxx
6166196 Xxxx Xxxx Xxxx
Xxxxx 000
Xxxx Xxxx, XX 00000
and the Contractor:
(Name, address and other information)
(Name, address and other information)
Waverly Construction & Management Company Inc.
0000 Xxxxxxx Xxxxxxx Xx
Xxxxxxxxx, XX 00000
0000 Xxxxxxx Xxxxxxx Xx
Xxxxxxxxx, XX 00000
The Project is:
(Name and location)
(Name and location)
Pointer Xxxxx Xxxxxx Xxxxxxxx
0000 Xxxxxxx Xxxxx Xxxx
Xxxxx, Xx.
0000 Xxxxxxx Xxxxx Xxxx
Xxxxx, Xx.
The Architect is:
(Name, address and other information)
(Name, address and other information)
Xxxxx-Rio Architecture & Interiors
0000 Xxxxxxxx Xxxx
0xx Xxxxx
Xxxxxxxxxxx, XX 00000
0000 Xxxxxxxx Xxxx
0xx Xxxxx
Xxxxxxxxxxx, XX 00000
The Owner and Contractor agree as follows.
1
ARTICLE 1 THE CONTRACT DOCUMENTS
The Contract Documents consist of this Agreement, Conditions of the Contract (General, Supplementary and other Conditions), Drawings, Specifications, Addenda issued prior to execution of this Agreement, other documents listed in this Agreement and Modifications issued after execution of this Agreement; these form the Contract, and are as fully a part of the Contract as if attached to this Agreement or repeated herein. The Contract represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations, representations or agreements, either written or oral. An enumeration of the Contract Documents, other than Modifications, appears in Article 8.
ARTICLE 2 THE WORK OF THIS CONTRACT
The Contractor shall fully execute the Work described in the Contract Documents, except to the extent specifically indicated in the Contract Documents to be the responsibility of others.
ARTICLE 3 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION
3.1 The date of commencement of the Work shall be the date of this Agreement unless a different date is stated below or provision is made for the date to be fixed in a notice to proceed issued by the Owner.
(Insert the date of commencement if it differs from the date of this Agreement or, if applicable, state that the date will be fixed in a notice to proceed)
Within seven (7) calendar days of the Receipt of: 1) Notice to Proceed; 2) Grading Permit; 3) Building Permit; 4) Fully Executed Contract, 5) Written Verification of Funding for the Project being in place.
If, prior to the commencement of the Work, the Owner requires time to file mortgages, mechanic’s liens and other security interests, the Owner’s time requirement shall be as follows:
3.2 The Contract Time shall be measured from the date of commencement.
3.3 The Contractor shall achieve Substantial Completion of the entire Work not later than 210 Calendar Days + 44 weather days = 254 calendar days from the date of commencement, or as follows:
(Insert number of calendar days. Alternatively, a calendar date may be used when coordinated with the date of commencement. Unless stated elsewhere in the Contract Documents, insert any requirements for earlier Substantial Completion of certain portions of the Work.)
Construction duration is 210 Calendar Days + weather days totaling 44 days. This is based upon days starting at mid-April and continuing through mid-November being calculated. At each
2
progress meeting, we will review and total the number of days lost to weather vs. the 44 day value amount, subject to adjustments of this Contract Time as provided in the Contract Documents.
(Insert provisions, if any, for liquidated damages relating to failure to complete on time or for bonus payments for early completion of the Work.)
ARTICLE 4 CONTRACT SUM
4.1 The Owner shall pay the Contractor the Contract Sum in current funds for the Contractor’s performance of the Contract. The Contract Sum shall be Four Million One Hundred Eight Thousand & ___xx/100 Dollars ($4,108,000.00), subject to additions and deductions as provided in Contract Documents.
4.2 The Contract Sum is based upon the following alternates, if any, which are described in the Contract Documents and are hereby accepted by the Owner:
(State the numbers or other identification of accepted alternates. If decisions on other alternates are to be made by the Owner subsequent to the execution of this Agreement, attach a schedule of such other alternates showing the amount for each and the date when that amount expires.)
4.3 Unit prices, if any, are as follows:
N/A
ARTICLE
5 PAYMENTS
5.1 PROGRESS PAYMENTS
5.1.1 Based upon Applications for Payment submitted to the Architect by the Contractor and Certificates for Payment issued by the Architect, the owner shall make progress payments on account of the Contract Sum to the Contractor as provided below and elsewhere in the Contract Documents.
5.1.2 The period covered by each Application for Payment shall be one calendar month ending on the last day of the month, or as follows:
5.1.3 Provided that an Application for Payment is received by the Architect not
later than the 25th day of a month, the Owner
shall make payment to the Contractor not later than the
25th day of the following month. If an Application for Payment is received by the Architect after the application date fixed above, payment shall be made by the Owner not later than twenty-five calendar days after the Architect receives the Application for Payment.
5.1.4 Each Application for Payment shall be based on the most recent schedule of values submitted by the Contractor in accordance with the Contract Documents. The schedule of values shall allocate the entire Contract Sum among the various portions of the Work. The schedule of values shall be prepared in such form and supported by such data to substantiate its accuracy as
3
the Architect may require. This schedule, unless objected to by the Architect, shall be used as a basis for reviewing the Contractor’s Applications for Payment.
5.1.5 Applications for Payment shall indicate the percentage of completion of each portion of the Work as of the end of the period covered by the Application for Payment.
5.1.6 Subject to other provisions of the Contract Documents, the amount of each progress payment shall be computed as follows:
.1 | Take that portion of the Contract Sum properly allocable to completed Work as determined by multiplying the percentage completion of each portion of the Work by the share of the Contract Sum allocated to that portion of the Work in the schedule of values, less retainage of ten percent (10%). Pending final determination of cost to the Owner of changes in the Work, amounts not in dispute shall be included as provided in Subparagraph 7.3.8 of AIA Document A201-1997; | ||
.2 | Add that portion of the Contract Sum properly allocable to materials and equipment delivered and suitably stored at the site for subsequent incorporation in the completed construction (or, if approved in advance by the Owner, suitably stored off the site at a location agreed upon in writing), less retainage of ten percent (10%); | ||
.3 | Subtract the aggregate of previous payments made by the Owner; and | ||
.4 | Subtract amounts, if any, for which the Architect has withheld or nullified a Certificate for Payment as provided in Paragraph 9.5 of AIA Document A201-1997. |
5.1.7 The progress payment amount determined in accordance with Subparagraph 5.1.6 shall be further modified under the following circumstances:
.1 | Add, upon Substantial Completion of the Work, a sum sufficient to increase the total payments to the full amount of the Contract Sum, less such amounts as the Architect shall determine for incomplete Work, retainage applicable to such work and unsettled claims; and (Subparagraph 9.8.5 of AIA Document A201-1997 requires release of applicable retainage upon Substantial Completion of Work with consent of surety, if any.) | ||
.2 | Add, if final completion of the Work is thereafter materially delayed through no fault of the Contractor, any additional amounts payable in accordance with Subparagraph 9.10.3 of AIA Document A201-1997. |
5.1.8 Reduction or limitation of retainage, if any, shall be as follows:
(If it is intended, prior to Substantial Completion of the entire Work, to reduce or limit the retainage resulting from the percentages inserted in Clauses 5.1.6.1 and 5.1.6.2 above, and this is not explained elsewhere in the Contract Documents, insert here provisions for such reduction or limitation.)
4
NOTE — There will be no retainage held on Structural Steel Materials upon installation, a value will be established for the structural steel materials. Retainage is to be held on steel field labor as listed above.
Retainage will be reduced to an amount equal to the value of uncompleted work and punch list items as determined by the Architect and Owner but will not be reduced to an amount less than $25,000.00 at any time until the requirements for Final Payment as described in Section 5.2 are met.
5.1.9 Except with the Owner’s prior approval, the Contractor shall not make advance payments to suppliers for materials or equipment which have not been delivered and stored at the site.
5.2 FINAL PAYMENT
5.2.1 Final payment, constituting the entire unpaid balance of the Contract Sum, shall be made by the Owner to the Contractor when:
.1 | the Contractor has fully performed the Contract except for the Contractor’s responsibility to correct Work as provided in Subparagraph 12.2.2 of AIA Document A201-1997, and to satisfy other requirements, if any, which extend beyond final payment; and | ||
.2 | a final Certificate for Payment has been issued by the Architect. |
5.2.2 The Owner’s final payment to the Contractor shall be made no later than 30 days after the issuance of the Architect’s final Certificate for Payment, or as follows:
ARTICLE 6 TERMINATION OR SUSPENSION
6.1 The Contract may be terminated by the Owner or the Contractor as provided in Article 14 of AIA Document A201-1997.
6.2 The Work may be suspended by the Owner as provided in Article 14 of AIA Document A201-1997.
ARTICLE 7 MISCELLANEOUS PROVISIONS
7.1 Where reference is made in this Agreement to a provision of AIA Document A201-1997 or another Contract Document, the reference refers to that provision as amended or supplemented by other provisions of the Contract Documents.
7.2
Payments due and unpaid under the Contract shall bear interest
from the date payment is due at the rate stated below; or in the
absence thereof, at the legal rate prevailing from time to time at
the place where the Project is located.
(Insert rate of interest agreed upon, if any.)
Prevailing Prime Rate +2%
(Insert rate of interest agreed upon, if any.)
Prevailing Prime Rate +2%
5
(Usury laws and requirements under the Federal Truth in Lending Act, similar state and local consumer credit laws and other regulations at the Owner’s and Contractor’s principal places of business, the location of the Project and elsewhere may affect the validity of this provision. Legal advice should be obtained with respect to deletions or modifications, and also regarding requirements such as written disclosures or waivers.)
7.3
The Owner’s representative is:
(Name, address and other information)
(Name, address and other information)
Xx. Xxxx Xxxxx
0000 Xxxx Xxxx Xxxx
Xxxxx 000
Xxxx Xxxx, XX 00000
0000 Xxxx Xxxx Xxxx
Xxxxx 000
Xxxx Xxxx, XX 00000
7.4
The Contractor’s representative is:
(Name, address and other information)
Xx. Xxxxxx Xxxxxx
0000 Xxxxxxx Xxxxxx Xx
Xxxxxxxxx, XX 00000
(Name, address and other information)
Xx. Xxxxxx Xxxxxx
0000 Xxxxxxx Xxxxxx Xx
Xxxxxxxxx, XX 00000
7.5 Neither the Owner’s nor the Contractor’s representative shall be changed without ten days’ written notice to the other party.
7.6 Other provisions:
Contractor Xxxx-up for work performed by its own forces on changes to the scope of work is cost + 12% (twelve percent).
Contractor Xxxx-up for work performed by sub-contractors on changes to the scope of work is cost + 8% (eight percent).
Sub-Contractor Xxxx-up for work performed by its own forces on changes to the scope of work is cost +10% (ten percent) Overhead + 15% (fifteen percent) Fee.
ARTICLE 8 ENUMERATION OF CONTRACT DOCUMENTS
8.1 The Contract Documents, except for Modifications issued after execution of this Agreement, are enumerated as follows:
8.1.1 The Agreement is this executed 1997 edition of the Standard Form of Agreement Between Owner and Contractor, AIA Document A101-1997.
8.1.2 The General Conditions are the 1997 edition of the General Conditions of the Contract for Construction, AIA Document A201-1997.
6
8.1.3 | The Supplementary and other Conditions of the Contract are those contained in the Project Manual dated July 26, 2004 ___, and are as follows: |
Document
|
Title | Pages |
See Attached Appendix IV — List of Drawings; Specifications & Technical Documents
8.1.4
The Specifications are those contained in the Project Manual
dated as in Subparagraph 8.1.3, and are as follows:
(Either List the Specifications here or refer to an exhibit attached to this Agreement.)
(Either List the Specifications here or refer to an exhibit attached to this Agreement.)
Section
|
Title | Pages |
See Attached Appendix IV — List of Drawings, Specifications & Technical Documents
8.1.5
The Drawings are as follows, and are dated
______ unless a different date is shown below:
(Either list the Drawings here or refer to an exhibit attached to this Agreement.)
Number
|
Title | Date |
See Attached Appendix IV — List of Drawings, Specifications & Technical Documents.
8.1.6 The Addenda, if any, are as follows:
Number
|
Date | Pages |
See Attached Appendix IV — List of Drawings; Specifications & Technical Documents
Portions of Addenda relating to bidding requirements are not part of the Contract
Documents unless the bidding requirements are also enumerated in this Article 8.
8.1.7 Other documents, if any forming part of the Contract Documents are as follows:
7
(List here any additional documents that are intended to form part of the Contract Documents. AIA Document A201-1997 provides that bidding requirements such as advertisement or invitation to bid, Instructions to Bidders, sample forms and the Contractor’s bid are not part of the Contract Documents unless enumerated in this Agreement. They should be listed here only if intended to be part of the Contract Documents.)
Appendix I — Budget Breakdown (for reference only)
Appendix II — Clarifications & Qualifications
Appendix III — Alternates and Allowances
Appendix IV — List of Drawings; Specifications and Technical Documents
This Agreement is entered into as of the day and year first written above and is executed in at least three original copies, of which one is to be delivered to the Contractor, one to the Architect for use in the administration of the Contract; and the remainder to the Owner.
/s/ Xxxxxxx X. Xxxxx
|
/s/ Xxxxxx X. Xxxxxx | |
OWNER (Signature)
|
CONTRACTER (Signature) | |
Xxxxxxx X. Xxxxx
|
Xxxxxx X. Xxxxxx V.P. | |
(Printed name and title)
|
(Printed name and title) |