Exhibit 4.53
SECOND AMENDMENT OF THE SUPPLY CONTRACT FOR THE PROCUREMENT AND INSTALLATION OF
RING JASUKA BACKBONE NO. K. TEL. 61/HK.920/UTA-00/2006, DATED 16 MARCH 2006
Parties: 1. TELKOM; and
2. NEC - Siemens Consortium ("NSC").
Preceding Contracts: 1. Supply Contract for Ring JASUKA Backbone No.
K.TEL.93/HK.910/UTA-00/2005 dated 10 June 2005;
2. First Amendment of Main Contract No. X.XXX
10/HK.920/UTA-00/2006, dated 6 February 2006.
Scope of Works: The Parties in the Design Review Meeting for Ring JASUKA
Backbone on 21 - 22 June 2005, 1-5 August 2005 and 29 -
31 August 2005, agreed to amend the scope of works as
implemented in the main contract which shall include but
not limited to:
1. Change of specification of marine route survey and
marine installation;
2. Change of cable length according to land and marine
route survey;
3. Change of traffic matrix;
4. Addition of transponder;
5. Change of power supply; and
6. Change of Training.
Time for Completion: 1. Each Sub-system of RING-I shall be completed within
two hundred fifty six (256) days from EDC for
Sub-system #1 - #3 or not later than 21 February
2006;
2. Each Sub-system of RING-II shall be completed within
two hundred eighty four (284) days from EDC for
Sub-system #1 or not later than 21 March 2006 and
within three hundred forty five (345) days from EDC
for Sub-systems #2 - #4 or not later than 21 May
2006.
Term of Payment: The payment shall be made through direct transfer.
Transfer fee shall be the responsibility of NSC.