EX-10.80 4 dex1080.htm US DEPARTMENT OF ENERGY COOPERATIVE AGREEMENT ASSISTANCE AGREEMENT DE-FE0004343 10/'01/2010 81.134 ADA-ES, INC. U.S. Department of Energy/’NETL 10/01/2010 Attn: RICHARD SCHLAGER Jennifer Gaudlip through LITTLETON CO 801204525...
Exhibit 10.80
1. Award No. | 2. Modification No. | 3. Effective Date | 4. CFDA No. | |||||||
DE-FE0004343 | 10/'01/2010 | 81.134 | ||||||||
5. Awarded To | Sponsoring Office | 7. Period of Performance | ||||||||
ADA-ES, INC. | U.S. Department of Energy/’NETL | 10/01/2010 | ||||||||
Attn: XXXXXXX XXXXXXXX | Xxxxxxxx Xxxxxxx | through | ||||||||
0000 XXXXXXXXX XXX, XXX. X | xxxxxxxx.xxxxxxx@xxxx.xxx.xxx | 03/31/2012 | ||||||||
LITTLETON CO 801204525 | 000 Xxxxxxxx Xxxx Xxxx | |||||||||
XX Xxx 00000 | ||||||||||
Xxxxxxxxxx XX 00000-0000 | ||||||||||
8. Type of Agreement | 9. Authority | 10. Purchase Request or Funding Document No. | ||||||||
Grant | See Page 2 | 10FE010592 | ||||||||
X Cooperative Agreement | ||||||||||
Other | ||||||||||
11. Remittance Address | 12. Total Amount | 13. Funds Obligated | ||||||||
ADA-ES, INC. | Govt. Share: | $15,000,000.00 | This action: | |||||||
Attn: XXXXXXX XXXXXXXX | $15,000,000.00 | |||||||||
0000 XXXXXXXXX XXX, XXX. X | Cost Share: | $3,750,001.00 | Total | |||||||
LITTLETON CO 801204525 | $15,000,000.00 | |||||||||
Total: | $18,750,001.00 | |||||||||
14. Principal Investigator | 15. Program Manager | 16. Administrator | ||||||||
Xxxxxx Xxxxxxxx | XXXXX X. XXXX | U.S. DOE/NETL | ||||||||
Phone: 000-000-0000 | Phone: 000-000-0000 | Pittsburgh Campus | ||||||||
000 Xxxxxxxx Xxxx Xxxx | ||||||||||
XX Xxx 00000 | ||||||||||
Xxxxxxxxxx XX 00000-0000 | ||||||||||
17. Submit Payment Requests To | 18. Paying Office | 19. Submit Reports To | ||||||||
OR for NETL (Pittsburgh) | OR for NETL (Pittsburgh) | See Attachment 3 | ||||||||
U.S. Department of Energy | U.S. Department of Energy | |||||||||
Oak Ridge Financial Service Center | Oak Ridge Financial Service Center | |||||||||
X.X. Xxx 0000 | X.X. Xxx 0000 | |||||||||
Xxx Xxxxx XX 00000 | Xxx Xxxxx XX 00000 | |||||||||
20. Accounting and Appropriation Data | ||||||||||
21. Research Title and/or Description of Project | ||||||||||
RECOVERY ACT: “EVALUATION OF SOLID SORBENTS AS AN INDUSTRIAL RETROFIT TECHNOLOGY FOR C02 CAPTURE | ||||||||||
For the Recipient | For the United States of America | |||||||||
22. Signature of Person Authorized to Sign | 25. Signature of Grants/Agreements Officer | |||||||||
/s/ Xxxxxxx Xxxxxxxx | Signature on File | |||||||||
23. Name and Title | 24. Date Signed | 26. Name of Officer | 27. Date Signed | |||||||
Xxxxxxx Xxxxxxxx, Vice President | 09/30/2010 | Xxxxxxx X. Xxxxxx | 09/17/2010 |
CONTINUATION SHEET | REFERENCE NO. OF DOCUMENT BEING CONTINUED | PAGE OF | ||||||||||||||||||||
DE-FE0004343 | 2 | 2 | ||||||||||||||||||||
NAME OF OFFEROR OR CONTRACTOR | ||||||||||||||||||||||
ADA-ES, INC. |
ITEM NO. (A) | SUPPLIES/SERVICES (B) | QUANTITY (C) | UNIT (D) | UNIT PRICE (E) | AMOUNT (F) | |||||||
DUNS Number: 133314067
Authority: | ||||||||||||
PL 95-91 DOE Organization Act, PL 111-5 American | ||||||||||||
Recovery and Reinvestment Act of 2009 and PL | ||||||||||||
109-58 Energy Policy Xxx 0000, PL 110-140 Energy | ||||||||||||
Independence and Security Act of 2007 | ||||||||||||
Responsible Parties: | ||||||||||||
DOE Program Officer | ||||||||||||
Xxxxx Xxxx Mail Stop 922-342C | ||||||||||||
US DOE/National Energy Technology Laboratory | ||||||||||||
000 Xxxxxxxx Xxxx Xxxx, X.X. Xxx 00000 | ||||||||||||
Xxxxxxxxxx, XX 00000-0000 | ||||||||||||
Phone: 000-000-0000 | ||||||||||||
E-Mail: Xxxxx.Xxxx@netl.doe.go- | ||||||||||||
DOE Administrator | ||||||||||||
Xxxxxxxx Xxxxxxx Mail Stop 921-107 | ||||||||||||
US DOE/National Energy Technology Laboratory | ||||||||||||
000 Xxxxxxxx Xxxx Xxxx, X.X. Xxx 00000 | ||||||||||||
Xxxxxxxxxx, XX 00000-0000 | ||||||||||||
Phone: 000-000-0000 | ||||||||||||
E-Mail: Xxxxxxxx.Xxxxxxx@xxxx.xxx.xxx | ||||||||||||
ADA-ES Principal Investigator | ||||||||||||
Xxxxxx Xxxxxxxx | ||||||||||||
0000 XxxxxXxxx Xxx, Xxxx X | ||||||||||||
Xxxxxxxxx, XX 00000 | ||||||||||||
Phone: 000-000-0000 | ||||||||||||
E-Mail: xxxxxxx@xxxxx.xxx | ||||||||||||
ADA-ES Business Foint of Contact | ||||||||||||
Xxxxx Xxxxxxx, Manager, Contract R&D | ||||||||||||
0000 XxxxxXxxx Xxx, Xxxx X | ||||||||||||
Xxxxxxxxx, XX 00000 | ||||||||||||
Phone: 000-000-0000 | ||||||||||||
E-Mail: xxxxxx@xxxxx.xxx | ||||||||||||
ASAP: NO: STD IMMEDIATE Extent Competed: COMPETED | ||||||||||||
Xxxxx-Xxxxx Act: YES PI: Xxxxxx Xxxxxxxx | ||||||||||||
Fund: 05899 Appr Year: 2009 Allottee: 31 Report | ||||||||||||
Entity: 220317 Object Class: 25500 Program: | ||||||||||||
1611007 Project:2003010 WFO:0000000 Local Use: | ||||||||||||
0000000 TAS Agency: 89 TAS Account: 0211 |
SPECIAL TERMS AND CONDITIONS
U.S. Department of Energy
DE-FE0004343
Table of Contents
RESOLUTION OF CONFLICTING CONDITIONS | 2 | |||
AWARD AGREEMENT TERMS AND CONDITIONS | 2 | |||
AWARD PROJECT PERIOD AND BUDGET PERIODS | 2 | |||
PAYMENT PROCEDURES - REIMBURSEMENT THROUGH THE AUTOMATED CLEARING HOUSE (ACH) VENDER INQUIRY PAYMENT ELECTRONIC REPORTING SYSTEM (VIPERS) | 2 | |||
COST SHARING | 3 | |||
REBUDGETING AND RECOVERY OF INDIRECT COSTS - REIMBURSABLE INDIRECT COSTS AND FRINGE BENEFITS | 3 | |||
USE OF PROGRAM INCOME - ADDITION | 4 | |||
STATEMENT OF FEDERAL STEWARDSHIP | 4 | |||
STATEMENT OF SUBSTANTIAL INVOLVEMENT | 4 | |||
SITE VISITS | 5 | |||
REPORTING REQUIREMENTS | 5 | |||
PUBLICATIONS | 5 | |||
FEDERAL, STATE, AND MUNICIPAL REQUIREMENTS | 6 | |||
INTELLECTUAL PROPERTY PROVISIONS AND CONTACT INFORMATION | 6 | |||
NATIONAL SECURITY: CLASSIFIABLE RESULTS ORIGINATING UNDER AN AWARD | 6 | |||
CONTINUATION APPLICATION AND FUNDING - AWARDS UNDER 10 CFR 600 | 7 | |||
LOBBYING RESTRICTIONS | 7 | |||
NOTICE REGARDING THE PURCHASE OF AMERICAN-MADE EQUIPMENT AND PRODUCTS — SENSE OF CONGRESS | 7 | |||
ENVIRONMENTAL, SAFETY AND HEALTH (ES&H) PERFORMANCE OF WORK AT DOE FACILITIES | 7 | |||
FUNDING OF BUDGET PERIODS | 8 | |||
INSOLVENCY, BANKRUPTCY OR RECEIVERSHIP | 8 | |||
PERFORMANCE OF WORK IN UNITED STATES | 8 | |||
NATIONAL ENVIRONMENTAL POLICY ACT (NEPA) REQUIREMENTS | 8 | |||
DECONTAMINATION AND/OR DECOMMISSIONING (D &D) COSTS | 9 | |||
SPECIAL PROVISIONS RELATING TO WORK FUNDED UNDER AMERICAN RECOVERY AND REINVESTMENT ACT OF 2009 (MAR 2009) | 9 | |||
REPORTING AND REGISTRATION REQUIREMENTS UNDER SECTION 1512 OF THE RECOVERY ACT | 12 | |||
REQUIRED USE OF AMERICAN IRON, STEEL, AND MANUFACTURED GOODS (COVERED UNDER INTERNATIONAL AGREEMENTS) - SECTION 1605 OF THE AMERICAN RECOVERY AND REINVESTMENT ACT OF 2009 | 12 | |||
WAGE RATE REQUIREMENTS UNDER SECTION 1606 OF THE RECOVERY ACT | 15 | |||
RECOVERY ACT TRANSACTIONS LISTED IN SCHEDULE OF EXPENDITURES OF FEDERAL AWARDS AND RECIPIENT RESPONSIBILITIES FOR INFORMING SUBRECIPIENTS | 15 | |||
XXXXX XXXXX ACT AND CONTRACT WORK HOURS AND SAFETY STANDARDS ACT | 16 | |||
RECIPIENT FUNCTIONS | 23 | |||
SUBRECIPIENT/SUBCONTRACT APPROVALS | 23 | |||
HOST SITE AGREEMENT | 24 |
Page 1 of 24
SPECIAL TERMS AND CONDITIONS
RESOLUTION OF CONFLICTING CONDITIONS
Any apparent inconsistency between Federal statutes and regulations and the terms and conditions contained in this award must be referred to the DOE Award Administrator for guidance.
AWARD AGREEMENT TERMS AND CONDITIONS
This award/agreement consists of the Grant and Cooperative Agreement cover page, plus the following:
a. Special terms and conditions.
b. Attachments:
Attachment No. | Title | |
1 | Intellectual Property Provisions | |
2 | Statement of Project Objectives | |
3 | Federal Assistance Reporting Checklist | |
4 | Budget Pages | |
5 | Responsible Parties | |
6 | Wage Rate Determination (RESERVED) |
c. Applicable program regulations
x. XXX Assistance Regulations, 10 CFR 600 at xxxx://xxxx.xxxxxxxxx.xxx.
e. If the award is for research and to a university or non-profit, the Research Terms & Conditions and the DOE Agency Specific Requirements at xxxx://xxx.xxx.xxx/xxx/xxxx/xxxxxx/xxx/xxxxx.xxx.
f. Application/proposal as approved by DOE.
g. National Policy Assurances to Be Incorporated as Award Terms in effect on date of award at xxxx://xxxxxxxxxx.xxxxxx.xxx/xxxxxxxx_xxx/0000.xxx.
AWARD PROJECT PERIOD AND BUDGET PERIODS
The Project Period for this award is 10/01/2010 through 12/31/2014 consisting of the following Budget Periods.
Budget Period | Start Date | End Date | ||
1 | 10/01/2010 | 03/31/2012 | ||
2 | 04/01/2012 | 09/30/2013 | ||
3 | 10/01/2013 | 12/31/2014 |
PAYMENT PROCEDURES - REIMBURSEMENT THROUGH THE AUTOMATED CLEARING HOUSE (ACH) VENDER INQUIRY PAYMENT ELECTRONIC REPORTING SYSTEM (VIPERS)
a. Method of Payment. Payment will be made by reimbursement through ACH.
b. Requesting Reimbursement. Requests for reimbursements must be made electronically through Department of Energy’s Oak Ridge Financial Service Center (ORFSC) VIPERS. To access and use VIPERS, you must enroll at xxxxx://xxxxxx.xxx.xxx.xxx/xxxxxx.xxx. Detailed instructions on how to enroll are provided on the web site.
For non-construction awards, you must submit a Standard Form (SF) 270, “Request for Advance or Reimbursement” at xxxxx://xxxxxx.xxx.xxx.xxx/xxxxxx.xxx and attach a file containing appropriate supporting documentation. The file attachment must show the total federal share claimed on the SF 270, the non-federal share claimed for the billing period if cost sharing is required, and cumulative expenditures to date (both Federal and non-Federal) for each of the following categories: salaries/wages and fringe benefits; equipment; travel; participant/training support costs, if any; other direct costs, including subawards/contracts; and indirect costs. For construction awards, you must submit a SF 271, “Outlay Report and Request for Reimbursement for Construction Programs,” through VIPERS.
Page 2 of 24
c. Timing of submittals. Submittal of the SF 270 or SF 271 should coincide with your normal billing pattern, but not more frequently than every two weeks. Requests for reimbursement must be limited to the amount of disbursements made during the billing period for the federal share of direct project costs and the proportionate share of any allowable indirect costs incurred during that billing period.
d. Adjusting payment requests for available cash. You must disburse any funds that are available from repayments to and interest earned on a revolving fund, program income, rebates, refunds, contract settlements, audit recoveries, credits, discounts, and interest earned on any of those funds before requesting additional cash payments from DOE.
e. Payments. The DOE approving official will approve the invoice as soon as practicable but not later than 30 days after your request is received, unless the billing is improper. Upon receipt of an invoice payment authorization from the DOE approving official, the ORFSC will disburse payment to you. You may check the status of your payments at the VIPER web site. All payments are made by electronic funds transfer to the bank account identified on the ACH Vendor/Miscellaneous Payment Enrollment Form (SF 3881) that you filed.
COST SHARING
a. Total Estimated Project Cost is the sum of the Government share and Recipient share of the estimated project costs. The Recipient’s cost share must come from non-Federal sources unless otherwise allowed by law. By accepting federal funds under this award, you agree that you are liable for your percentage share of total allowable project costs, on a budget period basis, even if the project is terminated early or is not funded to its completion. This cost is shared as follows:
Budget Period (Start Date) | Budget Period 1 (10/01/2010) | Budget Period 2 (04/01/2012) | Budget Period 3 (10/01/2013) | Total Estimated Cost | ||||||||||||
DOE Share | $ | 3,099,474/80 | % | $ | 8,803,606/80 | % | $ | 3,096,920/80 | % | $ | 15,000,000/80 | % | ||||
Recipient Share | $ | 774,869/20 | % | $ | 2,200,901/20 | % | $ | 774,230/20 | % | $ | 3,750,000/20 | % | ||||
Total | $ | 3,874,343/100 | % | $ | 11,004,507/100 | % | $ | 3,871,150/100 | % | $ | 18,750,000/100 | % | ||||
Budget Period Duration in Months | 18 | 18 | 15 |
b. If you discover that you may be unable to provide cost sharing of at least the amount identified in paragraph a of this term, you should immediately provide written notification to the DOE Award Administrator indicating whether you will continue or phase out the project. If you plan to continue the project, the notification must describe how replacement cost sharing will be secured.
c. You must maintain records of all project costs that you claim as cost sharing, including in-kind costs, as well as records of costs to be paid by DOE. Such records are subject to audit.
d. Failure to provide the cost sharing required by this term may result in the subsequent recovery by DOE of some or all the funds provided under the award.
REBUDGETING AND RECOVERY OF INDIRECT COSTS - REIMBURSABLE INDIRECT COSTS AND FRINGE BENEFITS
a. If actual allowable indirect costs are less than those budgeted and funded under the award, you may use the difference to pay additional allowable direct costs during the project period. If at the completion of the award the Government’s share of total allowable costs (i.e., direct and indirect), is less than the total costs reimbursed, you must refund the difference.
Page 3 of 24
b. Recipients are expected to manage their indirect costs. DOE will not amend an award solely to provide additional funds for changes in indirect cost rates. DOE recognizes that the inability to obtain full reimbursement for indirect costs means the recipient must absorb the underrecovery. Such underrecovery may be allocated as part of the organization’s required cost sharing.
USE OF PROGRAM INCOME - ADDITION
If you earn program income during the project period as a result of this award, you may add the program income to the funds committed to the award and use it to further eligible project objectives.
STATEMENT OF FEDERAL STEWARDSHIP
DOE will exercise normal Federal stewardship in overseeing the project activities performed under this award. Stewardship activities include, but are not limited to, conducting site visits; reviewing performance and financial reports; providing technical assistance and/or temporary intervention in unusual circumstances to correct deficiencies which develop during the project; assuring compliance with terms and conditions; and reviewing technical performance after project completion to ensure that the award objectives have been accomplished.
STATEMENT OF SUBSTANTIAL INVOLVEMENT
The Recipient is responsible for:
• | Performing the activities supported by this award in accordance with the Project Management Plan, including providing the required personnel, facilities, equipment, supplies and services; |
• | Managing and controlling project activities in accordance with established processes and procedures to ensure tasks and subtasks are completed within schedule and budget constraints defined by the current Project Management Plan; |
• | Implementing an approach to identify, analyze, and respond to project risks that is commensurate with the complexity of the project; |
• | Defining and revising approaches and plans, submitting the plans to DOE for review, and incorporating DOE comments; |
• | Coordinating related project activities with external suppliers, including DOE M&O contractors, to ensure effective integration of all work elements; |
• | Attending annual program review meetings and reporting project status; |
• | Submitting technical reports and incorporating DOE comments; and |
• | Presenting the project results at appropriate technical conferences or meetings as directed by the DOE Project Officer (number of conferences/meetings will not exceed eight (8)). |
DOE is responsible for:
• | Reviewing in a timely manner project plans, including project management, testing and technology transfer plans, and recommending alternate approaches, if the plans do not address critical programmatic issues; |
• | Participating in project management planning activities, including risk analysis, to ensure DOE’s program requirements or limitations are considered in performance of the work elements; |
• | Conducting annual program review meetings to ensure adequate progress and that the work accomplishes the program and project objectives. Recommending alternate approaches or shifting work emphasis, if needed; |
• | Integrating and redirecting the work effort to ensure that project results address critical system and programmatic goals established by DOE FE, in coordination with the DOE Existing Plants Division; |
• | Promoting and facilitating technology transfer activities, including disseminating program results through presentations and publications; |
• | Serving as scientific/technical liaison between awardees and other program or industry staff; |
Page 4 of 24
• | Reviewing and approving any milestones or decision points within the Statement of Project Objectives (SOPO) that can hinder technology development. The DOE Project Officer will determine if it is in the best interest of all parties involved to continue the project. Prior to authorizing the Recipient to perform work on a subsequent task, DOE will evaluate the progress made against the standards set forth in the SOPO. If in DOE’s opinion, such progress has not been as anticipated, the Recipient hereby agrees that DOE may elect to discontinue the Cooperative Agreement at no additional cost to DOE; and |
• | Reviewing and concurring with ongoing technical performance to ensure that adequate progress has been obtained within the current activities/tasks authorized by DOE before work can commence on subsequent activities/tasks as addressed within the “CONTINUATION APPLICATION AND FUNDING” provision of the Cooperative Agreement. |
SITE VISITS
DOE’s authorized representatives have the right to make site visits at reasonable times to review project accomplishments and management control systems and to provide technical assistance, if required. You must provide, and must require your subrecipients to provide, reasonable access to facilities, office space, resources, and assistance for the safety and convenience of the government representatives in the performance of their duties. All site visits and evaluations must be performed in a manner that does not unduly interfere with or delay the work.
REPORTING REQUIREMENTS
a. Requirements. The reporting requirements for this award are identified on the Federal Assistance Reporting Checklist, DOE F 4600.2, attached to this award. Failure to comply with these reporting requirements is considered a material noncompliance with the terms of the award. Noncompliance may result in withholding of future payments, suspension, or termination of the current award, and withholding of future awards. A willful failure to perform, a history of failure to perform, or unsatisfactory performance of this and/or other financial assistance awards, may also result in a debarment action to preclude future awards by Federal agencies.
b. Dissemination of scientific/technical reports. Scientific/technical reports submitted under this award will be disseminated on the Internet via the DOE Information Bridge (xxx.xxxx.xxx/xxxxxx), unless the report contains patentable material, protected data, or SBIR/STTR data. Citations for journal articles produced under the award will appear on the DOE Energy Citations Database (xxx.xxxx.xxx/xxxxxxxxxxxxxxx).
c. Restrictions. Reports submitted to the DOE Information Bridge must not contain any Protected Personal Identifiable Information (PII), limited rights data (proprietary data), classified information, information subject to export control classification, or other information not subject to release.
PUBLICATIONS
a. You are encouraged to publish or otherwise make publicly available the results of the work conducted under the award.
b. An acknowledgment of Federal support and a disclaimer must appear in the publication of any material, whether copyrighted or not, based on or developed under this project, as follows:
Acknowledgment: “This material is based upon work supported by the Department of Energy under Award Number DE-FE0004343.”
Disclaimer: “This report was prepared as an account of work sponsored by an agency of the United States Government. Neither the United States Government nor any agency thereof, nor any of their employees, makes any warranty, express or implied, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights. Reference herein to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States Government or any agency thereof. The views and opinions of authors expressed herein do not necessarily state or reflect those of the United States Government or any agency thereof.”
Page 5 of 24
FEDERAL, STATE, AND MUNICIPAL REQUIREMENTS
You must obtain any required permits and comply with applicable federal, state, and municipal laws, codes, and regulations for work performed under this award.
INTELLECTUAL PROPERTY PROVISIONS AND CONTACT INFORMATION
a. The intellectual property provisions applicable to this award are provided as an attachment to this award or are referenced on the Assistance Agreement Face Page. A list of all intellectual property provisions may be found at xxxx://xxx.xx.xxx.xxx/xxxxxxxxx_xxxxxxxxxx_xxxxxx.xxx.
b. Questions regarding intellectual property matters should be referred to the DOE Award Administrator and the Patent Counsel designated as the service provider for the DOE office that issued the award. The IP Service Providers List is found at xxxx://xxx.xx.xxx.xxx/xxxxxxxxx/Xxxxxxxxxxxx_Xxxxxxxx_(XX)_Xxxxxxx_Xxxxxxxxx_xxx_Xxxxxxxxxxx.xxx
NATIONAL SECURITY: CLASSIFIABLE RESULTS ORIGINATING UNDER AN AWARD
a. This award is intended for unclassified, publicly releasable research. You will not be granted access to classified information. DOE does not expect that the results of the research project will involve classified information. Under certain circumstances, however, a classification review of information originated under the award may be required. The Department may review research work generated under this award at any time to determine if it requires classification.
b. Executive Order 12958 (60 Fed. Reg. 19,825 (1995)) states that basic scientific research information not clearly related to the national security shall not be classified. Nevertheless, some information concerning (among other things) scientific, technological, or economic matters relating to national security or cryptology may require classification. If you originate information during the course of this award that you believe requires classification, you must promptly:
1. Notify the DOE Project Officer and the DOE Award Administrator;
2. Submit the information by registered mail directly to the Director, Office of Classification and Information Control, SO-10.2; U.S. Department of Energy; P.O. Box A; Xxxxxxxxxx, XX 00000-0000, for classification review.
3. Restrict access to the information to the maximum extent possible until you are informed that the information is not classified, but no longer than 30 days after receipt by the Director, Office of Classification and Information Control.
c. If you originate information concerning the production or utilization of special nuclear material (i.e., plutonium, uranium enriched in the isotope 233 or 235, and any other material so determined under section 51 of the Atomic Energy Act) or nuclear energy, you must:
1. Notify the DOE Project Officer and the DOE Award Administrator;
2. Submit the information by registered mail directly to the Director, Office of Classification and Information Control, SO-10.2; U.S. Department of Energy; P. O. Box A; Xxxxxxxxxx, XX 00000-0000 for classification review within 180 days of the date the recipient first discovers or first has reason to believe that the information is useful in such production or utilization; and
3. Restrict access to the information to the maximum extent possible until you are informed that the information is not classified, but no longer than 90 days after receipt by the Director, Office of Classification and Information Control.
Page 6 of 24
d. If DOE determines any of the information requires classification, you agree that the Government may terminate the award by mutual agreement in accordance with 10 CFR 600.25(d). All material deemed to be classified must be forwarded to the DOE, in a manner specified by DOE.
e. If DOE does not respond within the specified time periods, you are under no further obligation to restrict access to the information.
CONTINUATION APPLICATION AND FUNDING - AWARDS UNDER 10 CFR 600
a. Continuation Application. A continuation application is a non-competitive application for an additional budget period within a previously approved project period. At least 90 days before the end of each budget period, you must submit to the DOE Project Officer and the DOE Award Administrator your continuation application, which includes the following information:
1. A report on your progress towards meeting the objectives of the project, including any significant findings, conclusions, or developments, and an estimate of any unobligated balances remaining at the end of the budget period. If the remaining unobligated balance is estimated to exceed 20 percent of the funds available for the budget period, explain why the excess funds have not been obligated and how they will be used in the next budget period.
2. A detailed budget and supporting justification for the upcoming budget period if additional funds are requested, a reduction of funds is anticipated, or a budget for the upcoming budget period was not approved at the time of award
3. A description of your plans for the conduct of the project during the upcoming budget period, if there are changes from the DOE approved application.
b. Continuation Funding. Continuation funding is contingent on (1) availability of funds; (2) substantial progress towards meeting the objectives of your approved application; (3) submittal of required reports; or (4) compliance with the terms and conditions of the award.
LOBBYING RESTRICTIONS
By accepting funds under this award, you agree that none of the funds obligated on the award shall be expended, directly or indirectly, to influence congressional action on any legislation or appropriation matters pending before Congress, other than to communicate to Members of Congress as described in 18 U.S.C. 1913. This restriction is in addition to those prescribed elsewhere in statute and regulation.
NOTICE REGARDING THE PURCHASE OF AMERICAN-MADE EQUIPMENT AND PRODUCTS — SENSE OF CONGRESS
It is the sense of the Congress that, to the greatest extent practicable, all equipment and products purchased with funds made available under this award should be American-made.
ENVIRONMENTAL, SAFETY AND HEALTH (ES&H) PERFORMANCE OF WORK AT DOE FACILITIES
With respect to the performance of any portion of the work under this award which is performed at a DOE-owned or controlled site, the recipient agrees to comply with all State and Federal ES&H regulations and with all other ES&H requirements of the operator of such site.
Prior to the performance on any work at a DOE-Owned or controlled site, the recipient shall contact the site facility manager for information on DOE and site specific ES&H requirements.
The recipient shall apply this term to its sub-recipients and contractors.
Page 7 of 24
FUNDING OF BUDGET PERIODS
DOE has obligated $15,000,000 for completion of the Project authorized by this agreement; however, only $3,099,474 is available for work performed by the Recipient during Budget Period 1 of the Project. For Budget Periods 2 and 3, the remainder, or $11,900,526, will be available contingent upon the submission by the Recipient of a continuation application and written approval of the continuation application by the DOE Contracting Officer.
In the event that the Recipient does not submit a continuation application for subsequent Budget Periods or DOE disapproves a continuation application for subsequent Budget Periods, the maximum DOE liability to the Recipient is the funds that are available for the current approved Budget Period. In such event, DOE reserves the right to deobligate any remaining funds.
INSOLVENCY, BANKRUPTCY OR RECEIVERSHIP
a. You shall immediately notify the DOE of the occurrence of any of the following events: (i) you or your parent’s filing of a voluntary case seeking liquidation or reorganization under the Bankruptcy Act; (ii) your consent to the institution of an involuntary case under the Bankruptcy Act against you or your parent; (iii) the filing of any similar proceeding for or against you or your parent, or its consent to, the dissolution, winding-up or readjustment of your debts, appointment of a receiver, conservator, trustee, or other officer with similar powers over you, under any other applicable state or federal law; or (iv) your insolvency due to your inability to pay your debts generally as they become due.
b. Such notification shall be in writing and shall: (i) specifically set out the details of the occurrence of an event referenced in paragraph a; (ii) provide the facts surrounding that event; and (iii) provide the impact such event will have on the project being funded by this award.
c. Upon the occurrence of any of the four events described in the first paragraph, DOE reserves the right to conduct a review of your award to determine your compliance with the required elements of the award (including such items as cost share, progress towards technical project objectives, and submission of required reports). If the DOE review determines that there are significant deficiencies or concerns with your performance under the award, DOE reserves the right to impose additional requirements, as needed, including (i) change your payment method; or (ii) institute payment controls.
d. Failure of the Recipient to comply with this term may be considered a material noncompliance of this financial assistance award by the Contracting Officer.
PERFORMANCE OF WORK IN UNITED STATES
The Recipient agrees that at least 75% of the direct labor cost for the project (including subrecipient labor) shall be incurred in the United States, unless the Recipient can demonstrate to the satisfaction of the Department of Energy that the United States economic interest will be better served through a greater percentage of the work being performed outside the United States.
NATIONAL ENVIRONMENTAL POLICY ACT (NEPA) REQUIREMENTS
You are restricted from taking any action using Federal funds, which would have an adverse effect on the environment or limit the choice of reasonable alternatives prior to DOE providing either a NEPA clearance or a final NEPA decision regarding this project. Prohibited actions include: Tasks 2.3 and 4-9 of the Statement of Project Objectives (Attachment 2). This restriction does not preclude you from: Tasks 1-3 (with the exception of Task 2.3) of the Statement of Project Objectives (Attachment 2).
If you move forward with activities that are not authorized for federal funding by the DOE Contracting Officer in advance of the final NEPA decision, you are doing so at risk of not receiving federal funding and such costs may not be recognized as allowable cost share.
Page 8 of 24
If this award includes construction activities, you must submit an environmental evaluation report/evaluation notification form addressing NEPA issues prior to DOE initiating the NEPA process.
If a Categorical Exclusion (CX) decision is made on this project, the Contracting Officer will issue a letter notifying the Recipient that the above restrictions have been lifted.
DECONTAMINATION AND/OR DECOMMISSIONING (D &D) COSTS
Notwithstanding any other terms of this Agreement, the Government shall not be responsible for or have any obligation to the recipient for (i) Decontamination and/or Decommissioning (D&D) of any of the recipient’s facilities, or (ii) any costs which may be incurred by the recipient in connection with the D&D of any of its facilities due to the performance of the work under this Agreement, whether said work was performed prior to or subsequent to the effective date of this Agreement.
SPECIAL PROVISIONS RELATING TO WORK FUNDED UNDER AMERICAN RECOVERY AND REINVESTMENT ACT OF 2009 (MAR 2009)
Preamble
The American Recovery and Reinvestment Act of 2009, Pub. L. 111-5, (Recovery Act) was enacted to preserve and create jobs and promote economic recovery, assist those most impacted by the recession, provide investments needed to increase economic efficiency by spurring technological advances in science and health, invest in transportation, environmental protection, and other infrastructure that will provide long-term economic benefits, stabilize State and local government budgets, in order to minimize and avoid reductions in essential services and counterproductive State and local tax increases. Recipients shall use grant funds in a manner that maximizes job creation and economic benefit.
The Recipient shall comply with all terms and conditions in the Recovery Act relating generally to governance, accountability, transparency, data collection and resources as specified in Act itself and as discussed below.
Recipients should begin planning activities for their first tier subrecipients, including obtaining a DUNS number (or updating the existing DUNS record), and registering with the Central Contractor Registration (CCR).
Be advised that Recovery Act funds can be used in conjunction with other funding as necessary to complete projects, but tracking and reporting must be separate to meet the reporting requirements of the Recovery Act and related guidance. For projects funded by sources other than the Recovery Act, Contractors must keep separate records for Recovery Act funds and to ensure those records comply with the requirements of the Act.
The Government has not fully developed the implementing instructions of the Recovery Act, particularly concerning specific procedural requirements for the new reporting requirements. The Recipient will be provided these details as they become available. The Recipient must comply with all requirements of the Act. If the recipient believes there is any inconsistency between ARRA requirements and current award terms and conditions, the issues will be referred to the Contracting Officer for reconciliation.
Definitions
For purposes of this term, Covered Funds means funds expended or obligated from appropriations under the American Recovery and Reinvestment Act of 2009, Pub. L. 111-5. Covered Funds will have special accounting codes and will be identified as Recovery Act funds in the grant, cooperative agreement or TIA and/or modification using Recovery Act funds. Covered Funds must be reimbursed by September 30, 2015.
Page 9 of 24
Non-Federal employer means any employer with respect to covered funds — the contractor, subcontractor, grantee, or recipient, as the case may be, if the contractor, subcontractor, grantee, or recipient is an employer; and any professional membership organization, certification of other professional body, any agent or licensee of the Federal government, or any person acting directly or indirectly in the interest of an employer receiving covered funds; or with respect to covered funds received by a State or local government, the State or local government receiving the funds and any contractor or subcontractor receiving the funds and any contractor or subcontractor of the State or local government; and does not mean any department, agency, or other entity of the federal government.
Recipient means any entity that receives Recovery Act funds directly from the Federal government (including Recovery Act funds received through grant, loan, or contract) other than an individual and includes a State that receives Recovery Act Funds.
Special Provisions
A. Flow Down Requirement
Recipients must include these special terms and conditions in any subaward.
B. Segregation of Costs
Recipients must segregate the obligations and expenditures related to funding under the Recovery Act. Financial and accounting systems should be revised as necessary to segregate, track and maintain these funds apart and separate from other revenue streams. No part of the funds from the Recovery Act shall be commingled with any other funds or used for a purpose other than that of making payments for costs allowable for Recovery Act projects.
C. Prohibition on Use of Funds
None of the funds provided under this agreement derived from the American Recovery and Reinvestment Act of 2009, Pub. L. 111-5, may be used by any State or local government, or any private entity, for any casino or other gambling establishment, aquarium, zoo, golf course, or swimming pool.
D. Access to Records
With respect to each financial assistance agreement awarded utilizing at least some of the funds appropriated or otherwise made available by the American Recovery and Reinvestment Act of 2009, Pub. L. 111-5, any representative of an appropriate inspector general appointed under section 3 or 8G of the Inspector General Act of 1988 (5 U.S.C. App.) or of the Comptroller General is authorized —
(1) to examine any records of the contractor or grantee, any of its subcontractors or subgrantees, or any State or local agency administering such contract that pertain to, and involve transactions that relate to, the subcontract, subcontract, grant, or subgrant; and
(2) to interview any officer or employee of the contractor, grantee, subgrantee, or agency regarding such transactions.
E. Publication
An application may contain technical data and other data, including trade secrets and/or privileged or confidential information, which the applicant does not want disclosed to the public or used by the Government for any purpose other than the application. To protect such data, the applicant should specifically identify each page including each line or paragraph thereof containing the data to be protected and xxxx the cover sheet of the application with the following Notice as well as referring to the Notice on each page to which the Notice applies:
Notice of Restriction on Disclosure and Use of Data
The data contained in pages — of this application have been submitted in confidence and contain trade secrets or proprietary information, and such data shall be used or disclosed only for evaluation purposes, provided that if this applicant receives an award as a result of or in connection with the submission of this application, DOE shall have the right to use or disclose the data here to the extent provided in the award.
Page 10 of 24
This restriction does not limit the Government’s right to use or disclose data obtained without restriction from any source, including the applicant.
Information about this agreement will be published on the Internet and linked to the website xxx.xxxxxxxx.xxx, maintained by the Accountability and Transparency Board. The Board may exclude posting contractual or other information on the website on a case-by-case basis when necessary to protect national security or to protect information that is not subject to disclosure under sections 552 and 552a of title 5, United States Code.
F. Protecting State and Local Government and Contractor Whistleblowers.
The requirements of Section 1553 of the Act are summarized below. They include, but are not limited to:
Prohibition on Reprisals: An employee of any non-Federal employer receiving covered funds under the American Recovery and Reinvestment Act of 2009, Pub. L. 111-5, may not be discharged, demoted, or otherwise discriminated against as a reprisal for disclosing, including a disclosure made in the ordinary course of an employee’s duties, to the Accountability and Transparency Board, an inspector general, the Comptroller General, a member of Congress, a State or Federal regulatory or law enforcement agency, a person with supervisory authority over the employee (or other person working for the employer who has the authority to investigate, discover or terminate misconduct), a court or grand jury, the head of a Federal agency, or their representatives information that the employee believes is evidence of:
- gross mismanagement of an agency contract or grant relating to covered funds;
- a gross waste of covered funds;
- a substantial and specific danger to public health or safety related to the implementation or use of covered funds;
- an abuse of authority related to the implementation or use of covered funds; or
- as violation of law, rule, or regulation related to an agency contract (including the competition for or negotiation of a contract) or grant, awarded or issued relating to covered funds.
Agency Action: Not later than 30 days after receiving an inspector general report of an alleged reprisal, the head of the agency shall determine whether there is sufficient basis to conclude that the non-Federal employer has subjected the employee to a prohibited reprisal. The agency shall either issue an order denying relief in whole or in part or shall take one or more of the following actions:
- Order the employer to take affirmative action to xxxxx the reprisal.
- Order the employer to reinstate the person to the position that the person held before the reprisal, together with compensation including back pay, compensatory damages, employment benefits, and other terms and conditions of employment that would apply to the person in that position if the reprisal had not been taken.
- Order the employer to pay the employee an amount equal to the aggregate amount of all costs and expenses (including attorneys’ fees and expert witnesses’ fees) that were reasonably incurred by the employee for or in connection with, bringing the complaint regarding the reprisal, as determined by the head of a court of competent jurisdiction.
Nonenforceablity of Certain Provisions Waiving Rights and Remedies or Requiring Arbitration: Except as provided in a collective bargaining agreement, the rights and remedies provided to aggrieved employees by this section may not be waived by any agreement, policy, form, or condition of employment, including any predispute arbitration agreement. No predispute arbitration agreement shall be valid or enforceable if it requires arbitration of a dispute arising out of this section.
Requirement to Post Notice of Rights and Remedies: Any employer receiving covered funds under the American Recovery and Reinvestment Act of 2009, Pub. L. 111-5, shall post notice of the rights and remedies as required therein. (Refer to section 1553 of the American Recovery and Reinvestment Act of 2009, Pub. L. 111-5, xxx.Xxxxxxxx.xxx, for specific requirements of this section and prescribed language for the notices.).
G. Reserved
Page 11 of 24
H. False Claims Act
Recipient and sub-recipients shall promptly refer to the DOE or other appropriate Inspector General any credible evidence that a principal, employee, agent, contractor, sub-grantee, subcontractor or other person has submitted a false claim under the False Claims Act or has committed a criminal or civil violation of laws pertaining to fraud, conflict of interest, bribery, gratuity or similar misconduct involving those funds.
I. Information in Support of Recovery Act Reporting
Recipient may be required to submit backup documentation for expenditures of funds under the Recovery Act including such items as timecards and invoices. Recipient shall provide copies of backup documentation at the request of the Contracting Officer or designee.
J. Availability of Funds
Funds appropriated under the Recovery Act and obligated to this award are available for reimbursement of costs until September 30, 2015.
REPORTING AND REGISTRATION REQUIREMENTS UNDER SECTION 1512 OF THE RECOVERY ACT
(a) This award requires the recipient to complete projects or activities which are funded under the American Recovery and Reinvestment Act of 2009 (Recovery Act) and to report on use of Recovery Act funds provided through this award. Information from these reports will be made available to the public.
(b) The reports are due no later than ten calendar days after each calendar quarter in which the recipient receives the assistance award funded in whole or in part by the Recovery Act.
(c) Recipients and their first-tier recipients must maintain current registrations in the Central Contractor Registration (xxxx://xxx.xxx.xxx) at all times during which they have active federal awards funded with Recovery Act funds. A Dun and Bradstreet Data Universal Numbering System (DUNS) Number (xxxx://xxx.xxx.xxx) is one of the requirements for registration in the Central Contractor Registration.
(d) The recipient shall report the information described in section 1512(c) of the Recovery Act using the reporting instructions and data elements that will be provided online at xxxx://xxx.XxxxxxxXxxxxxxxx.xxx and ensure that any information that is pre-filled is corrected or updated as needed.
REQUIRED USE OF AMERICAN IRON, STEEL, AND MANUFACTURED GOODS (COVERED UNDER INTERNATIONAL AGREEMENTS)—SECTION 1605 OF THE AMERICAN RECOVERY AND REINVESTMENT ACT OF 2009
(a) Definitions. As used in this award term and condition—
Designated country —
(1) A World Trade Organization Government Procurement Agreement country (Aruba, Austria, Belgium, Bulgaria, Canada, Chinese Taipei (Taiwan), Cyprus, Czech Republic, Denmark, Estonia, Finland, France, Germany, Greece, Hong Kong, Hungary, Iceland, Ireland, Israel, Italy, Japan, Korea (Republic of), Latvia, Liechtenstein, Lithuania, Luxembourg, Malta, Netherlands, Norway, Poland, Portugal, Romania, Singapore, Slovak Republic, Slovenia, Spain, Sweden, Switzerland, and United Kingdom;
(2) A Free Trade Agreement (FTA) country (Australia, Bahrain, Canada, Chile, Costa Rica, Dominican Republic, El Salvador, Guatemala, Honduras, Israel, Mexico, Morocco, Nicaragua, Oman, Peru, or Singapore);
(3) A United States-European Communities Exchange of Letters (May 15, 1995) country: Austria, Belgium, Bulgaria, Cyprus, Czech Republic, Denmark, Estonia, Finland, France, Germany, Greece, Hungary, Ireland, Italy, Latvia, Xxxxxxxxx, Xxxxxxxxxx, Xxxxx, Xxxxxxxxxxx, Poland, Portugal, Romania, Slovak Republic, Slovenia, Spain, Sweden, and United Kingdom; or
(4) An Agreement between Canada and the United States of America on Government Procurement country (Canada).
Page 12 of 24
Designated country iron, steel, and/or manufactured goods
(1) Is wholly the growth, product, or manufacture of a designated country; or
(2) In the case of a manufactured good that consist in whole or in part of materials from another country, has been substantially transformed in a designated country into a new and different manufactured good distinct from the materials from which it was transformed.
Domestic iron, steel, and/or manufactured good
(1) Is wholly the growth, product, or manufacture of the United States; or
(2) In the case of a manufactured good that consists in whole or in part of materials from another country, has been substantially transformed in the United States into a new and different manufactured good distinct from the materials from which it was transformed. There is no requirement with regard to the origin of components or subcomponents in manufactured goods or products, as long as the manufacture of the goods occurs in the United States.
Foreign iron, steel, and/or manufactured good means iron, steel and/or manufactured good that is not domestic or designated country iron, steel, and/or manufactured good.
Manufactured good means a good brought to the construction site for incorporation into the building or work that has been
(1) Processed into a specific form and shape; or
(2) Combined with other raw material to create a material that has different properties than the properties of the individual raw materials.
Public building and public work means a public building of, and a public work of, a governmental entity (the United States; the District of Columbia; commonwealths, territories, and minor outlying islands of the United States; State and local governments; and multi-State, regional, or interstate entities which have governmental functions). These buildings and works may include, without limitation, bridges, dams, plants, highways, parkways, streets, subways, tunnels, sewers, mains, power lines, pumping stations, heavy generators, railways, airports, terminals, docks, piers, wharves, ways, lighthouses, buoys, jetties, breakwaters, levees, and canals, and the construction, alteration, maintenance, or repair of such buildings and works.
Steel means an alloy that includes at least 50 percent iron, between .02 and 2 percent carbon, and may include other elements.
(b) Iron, steel, and manufactured goods.
(1) The award term and condition described in this section implements-
(i) Section 1605(a) of the American Recovery and Reinvestment Act of 2009 (Pub. L. 111-5) (Recovery Act), by requiring that all iron, steel, and manufactured goods used in the project are produced in the United States; and
(ii) Section 1605(d), which requires application of the Buy American requirement in a manner consistent with U.S. obligations under international agreements. The restrictions of section 1605 of the Recovery Act do not apply to designated country iron, steel, and/or manufactured goods. The Buy American requirement in section 1605 shall not be applied where the iron, steel or manufactured goods used in the project are from a Party to an international agreement that obligates the recipient to treat the goods and services of that Party the same as domestic goods and services. As of January 1, 2010, this obligation shall only apply to projects with an estimated value of $7,804,000 or more.
(2) The recipient shall use only domestic or designated country iron, steel, and manufactured goods in performing the work funded in whole or part with this award, except as provided in paragraphs (b)(3) and (b)(4) of this section.
(3) The requirement in paragraph (b)(2) of this section does not apply to the iron, steel, and manufactured goods listed by the Federal Government as follows:
TO BE DETERMINED
(4) The award official may add other iron, steel, and manufactured goods to the list in paragraph (b)(3) of this section if the Federal Government determines that—
(i) The cost of domestic iron, steel, and/or manufactured goods would be unreasonable. The cost of domestic iron, steel, and/or manufactured goods used in the project is unreasonable when the cumulative cost of such material will increase the overall cost of the project by more than 25 percent;
Page 13 of 24
(ii) The iron, steel, and/or manufactured good is not produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality; or
(iii) The application of the restriction of section 1605 of the Recovery Act would be inconsistent with the public interest.
(c) Request for determination of inapplicability of section 1605 of the Recovery Act or the Buy American Act.
(1)(i) Any recipient request to use foreign iron, steel, and/or manufactured goods in accordance with paragraph (b)(4) of this section shall include adequate information for Federal Government evaluation of the request, including—
(A) A description of the foreign and domestic iron, steel, and/or manufactured goods;
(B) Unit of measure;
(C) Quantity;
(D) Cost;
(E) Time of delivery or availability;
(F) Location of the project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign iron, steel, and/or manufactured goods cited in accordance with paragraph (b)(4) of this section.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed cost comparison table in the format in paragraph (d) of this section.
(iii) The cost of iron, steel, or manufactured goods shall include all delivery costs to the construction site and any applicable duty.
(iv) Any recipient request for a determination submitted after Recovery Act funds have been obligated for a project for construction, alteration, maintenance, or repair shall explain why the recipient could not reasonably foresee the need for such determination and could not have requested the determination before the funds were obligated. If the recipient does not submit a satisfactory explanation, the award official need not make a determination.
(2) If the Federal Government determines after funds have been obligated for a project for construction, alteration, maintenance, or repair that an exception to section 1605 of the Recovery Act applies, the award official will amend the award to allow use of the foreign iron, steel, and/or relevant manufactured goods. When the basis for the exception is nonavailability or public interest, the amended award shall reflect adjustment of the award amount, redistribution of budgeted funds, and/or other appropriate actions taken to cover costs associated with acquiring or using the foreign iron, steel, and/or relevant manufactured goods. When the basis for the exception is the unreasonable cost of the domestic iron, steel, or manufactured goods, the award official shall adjust the award amount or redistribute budgeted funds, as appropriate, by at least the differential established in 2 CFR 176.110(a).
(3) Unless the Federal Government determines that an exception to section 1605 of the Recovery Act applies, use of foreign iron, steel, and/or manufactured goods other than designated country iron, steel, and/or manufactured goods is noncompliant with the applicable Act.
Page 14 of 24
(d) Data. To permit evaluation of requests under paragraph (b) of this section based on unreasonable cost, the applicant shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Items Cost Comparison
Description | Unit of measure | Quantity | Cost (dollars)* | |||||||||
Item 1: | _________ | _________ | _________ | |||||||||
Foreign steel, iron, or manufactured good | _________ | _________ | _________ | |||||||||
Domestic steel, iron, or manufactured good | ||||||||||||
Item 2: | ||||||||||||
Foreign steel, iron, or manufactured good | _________ | _________ | _________ | |||||||||
Domestic steel, iron, or manufactured good | _________ | _________ | _________ |
[List name, address, telephone number, email address, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.]
[Include other applicable supporting information.]
[*Include all delivery costs to the construction site.]
WAGE RATE REQUIREMENTS UNDER SECTION 1606 OF THE RECOVERY ACT
(a) Section 1606 of the Recovery Act requires that all laborers and mechanics employed by contractors and subcontractors on projects funded directly by or assisted in whole or in part by and through the Federal Government pursuant to the Recovery Act shall be paid wages at rates not less than those prevailing on projects of a character similar in the locality as determined by the Secretary of Labor in accordance with subchapter IV of chapter 31 of title 40, United States Code.
Pursuant to Reorganization Plan No. 14 and the Xxxxxxxx Act, 40 U.S.C. 3145, the Department of Labor has issued regulations at 29 CFR parts 1, 3, and 5 to implement the Xxxxx-Xxxxx and related Acts. Regulations in 29 CFR 5.5 instruct agencies concerning application of the standard Xxxxx-Xxxxx contract clauses set forth in that section. Federal agencies providing grants, cooperative agreements, and loans under the Recovery Act shall ensure that the standard Xxxxx-Xxxxx contract clauses found in 29 CFR 5.5(a) are incorporated in any resultant covered contracts that are in excess of $2,000 for construction, alteration or repair (including painting and decorating).
(b) For additional guidance on the wage rate requirements of section 1606, contact your awarding agency. Recipients of grants, cooperative agreements and loans should direct their initial inquiries concerning the application of Xxxxx-Xxxxx requirements to a particular federally assisted project to the Federal agency funding the project. The Secretary of Labor retains final coverage authority under Reorganization Plan Number 14.
RECOVERY ACT TRANSACTIONS LISTED IN SCHEDULE OF EXPENDITURES OF FEDERAL AWARDS AND RECIPIENT RESPONSIBILITIES FOR INFORMING SUBRECIPIENTS
(a) To maximize the transparency and accountability of funds authorized under the American Recovery and Reinvestment Act of 2009 (Pub. L. 111—5) (Recovery Act) as required by Congress and in accordance with 2 CFR 215.21 “Uniform Administrative Requirements for Grants and Agreements” and OMB Circular A—102 Common Rules provisions, recipients agree to maintain records that identify adequately the source and application of Recovery Act funds. OMB Circular A—102 is available at xxxx://xxx.xxxxxxxxxx.xxx/xxx/xxxxxxxxx/x000/x000.xxxx.
Page 15 of 24
(b) For recipients covered by the Single Audit Act Amendments of 1996 and OMB Circular A—133, “Audits of States, Local Governments, and Non-Profit Organizations,” recipients agree to separately identify the expenditures for Federal awards under the Recovery Act on the Schedule of Expenditures of Federal Awards (SEFA) and the Data Collection Form (SF—SAC) required by OMB Circular A—133. OMB Circular A—133 is available at xxxx://xxx.xxxxxxxxxx.xxx/xxx/xxxxxxxxx/x000/x000.xxxx. This shall be accomplished by identifying expenditures for Federal awards made under the Recovery Act separately on the SEFA, and as separate rows under Item 9 of Part III on the SF—SAC by CFDA number, and inclusion of the prefix “ARRA-” in identifying the name of the Federal program on the SEFA and as the first characters in Item 9d of Part III on the SF—SAC.
(c) Recipients agree to separately identify to each subrecipient, and document at the time of subaward and at the time of disbursement of funds, the Federal award number, CFDA number, and amount of Recovery Act funds. When a recipient awards Recovery Act funds for an existing program, the information furnished to subrecipients shall distinguish the subawards of incremental Recovery Act funds from regular subawards under the existing program.
(d) Recipients agree to require their subrecipients to include on their SEFA information to specifically identify Recovery Act funding similar to the requirements for the recipient SEFA described above. This information is needed to allow the recipient to properly monitor subrecipient expenditure of ARRA funds as well as oversight by the Federal awarding agencies, Offices of Inspector General and the Government Accountability Office.
XXXXX XXXXX ACT AND CONTRACT WORK HOURS AND SAFETY STANDARDS ACT
Definitions: For purposes of this article, Xxxxx Bacon Act and Contract Work Hours and Safety Standards Act, the following definitions are applicable:
(1) “Award” means any grant, cooperative agreement or technology investment agreement made with Recovery Act funds by the Department of Energy (DOE) to a Recipient. Such Award must require compliance with the labor standards clauses and wage rate requirements of the Xxxxx-Xxxxx Act (DBA) for work performed by all laborers and mechanics employed by Recipients (other than a unit of State or local government whose own employees perform the construction) Subrecipients, Contractors and subcontractors.
(2) “Contractor” means an entity that enters into a Contract. For purposes of these clauses, Contractor shall include (as applicable) prime contractors, Recipients, Subrecipients, and Recipients’ or Subrecipients’ contractors, subcontractors, and lower-tier subcontractors. “Contractor” does not mean a unit of State or local government where construction is performed by its own employees.”
(3) “Contract” means a contract executed by a Recipient, Subrecipient, prime contractor or any tier subcontractor for construction, alteration, or repair. It may also mean (as applicable) (i) financial assistance instruments such as grants, cooperative agreements, technology investment agreements, and loans; and, (ii) Sub awards, contracts and subcontracts issued under financial assistance agreements. “Contract” does not mean a financial assistance instrument with a unit of State or local government where construction is performed by its own employees.
(4) “Contracting Officer” means the DOE official authorized to execute an Award on behalf of DOE and who is responsible for the business management and non-program aspects of the financial assistance process.
(5) “Recipient” means any entity other than an individual that receives an Award of Federal funds in the form of a grant, cooperative agreement or technology investment agreement directly from the Federal Government and is financially accountable for the use of any DOE funds or property, and is legally responsible for carrying out the terms and conditions of the program and Award.
Page 16 of 24
(6) “Subaward” means an award of financial assistance in the form of money, or property in lieu of money, made under an award by a Recipient to an eligible Subrecipient or by a Subrecipient to a lower- tier subrecipient. The term includes financial assistance when provided by any legal agreement, even if the agreement is called a contract, but does not include the Recipient’s procurement of goods and services to carry out the program nor does it include any form of assistance which is excluded from the definition of “Award” above.
(7) “Subrecipient” means a non-Federal entity that expends Federal funds received from a Recipient to carry out a Federal program, but does not include an individual that is a beneficiary of such a program.
(a) Xxxxx Xxxxx Act
(1) Minimum wages.
(i) All laborers and mechanics employed or working upon the site of the work (or under the United States Housing Act of 1937 or under the Housing Act of 1949 in the construction or development of the project), will be paid unconditionally and not less often than once a week, and without subsequent deduction or rebate on any account (except such payroll deductions as are permitted by regulations issued by the Secretary of Labor under the Xxxxxxxx Act (29 CFR part 3) ), the full amount of wages and bona fide fringe benefits (or cash equivalents thereof) due at time of payment computed at rates not less than those contained in the wage determination of the Secretary of Labor which is reserved for attachment hereto and shall be made a part hereof upon determination of a host site for the project, regardless of any contractual relationship which may be alleged to exist between the Contractor and such laborers and mechanics.
Contributions made or costs reasonably anticipated for bona fide fringe benefits under section 1(b)(2) of the Xxxxx-Xxxxx Act on behalf of laborers or mechanics are considered wages paid to such laborers or mechanics, subject to the provisions of paragraph (a)(1)(iv) of this section; also, regular contributions made or costs incurred for more than a weekly period (but not less often than quarterly) under plans, funds, or programs which cover the particular weekly period, are deemed to be constructively made or incurred during such weekly period. Such laborers and mechanics shall be paid the appropriate wage rate and fringe benefits on the wage determination for the classification of work actually performed, without regard to skill, except as provided in § 5.5(a)(4). Laborers or mechanics performing work in more than one classification may be compensated at the rate specified for each classification for the time actually worked therein: Provided, That the employer’s payroll records accurately set forth the time spent in each classification in which work is performed. The wage determination (including any additional classification and wage rates conformed under paragraph (a)(1)(ii) of this section) and the Xxxxx-Xxxxx poster (WH-1321) shall be posted at all times by the Contractor and its subcontractors at the site of the work in a prominent and accessible place where it can be easily seen by the workers.
(ii)(A) The Contracting Officer shall require that any class of laborers or mechanics, including helpers, which is not listed in the wage determination and which is to be employed under the Contract shall be classified in conformance with the wage determination. The Contracting Officer shall approve an additional classification and wage rate and fringe benefits therefore only when the following criteria have been met:
(1) The work to be performed by the classification requested is not performed by a classification in the wage determination; and
(2) The classification is utilized in the area by the construction industry; and
(3) The proposed wage rate, including any bona fide fringe benefits, bears a reasonable relationship to the wage rates contained in the wage determination.
Page 17 of 24
(B) If the Contractor and the laborers and mechanics to be employed in the classification (if known), or their representatives, and the Contracting Officer agree on the classification and wage rate (including the amount designated for fringe benefits where appropriate), a report of the action taken shall be sent by the Contracting Officer to the Administrator of the Wage and Hour Division, U.S. Department of Labor, Xxxxxxxxxx, XX 00000. The Administrator, or an authorized representative, will approve, modify, or disapprove every additional classification action within 30 days of receipt and so advise the Contracting Officer or will notify the Contracting Officer within the 30-day period that additional time is necessary.
(C) In the event the Contractor, the laborers or mechanics to be employed in the classification or their representatives, and the Contracting Officer do not agree on the proposed classification and wage rate (including the amount designated for fringe benefits, where appropriate), the Contracting Officer shall refer the questions, including the views of all interested parties and the recommendation of the Contracting Officer, to the Administrator for determination. The Administrator, or an authorized representative, will issue a determination within 30 days of receipt and so advise the Contracting Officer or will notify the Contracting Officer within the 30-day period that additional time is necessary.
(D) The wage rate (including fringe benefits where appropriate) determined pursuant to paragraphs (a)(1)(ii)(B) or (C) of this section, shall be paid to all workers performing work in the classification under this Contract from the first day on which work is performed in the classification.
(iii) Whenever the minimum wage rate prescribed in the Contract for a class of laborers or mechanics includes a fringe benefit which is not expressed as an hourly rate, the Contractor shall either pay the benefit as stated in the wage determination or shall pay another bona fide fringe benefit or an hourly cash equivalent thereof.
(iv) If the Contractor does not make payments to a trustee or other third person, the Contractor may consider as part of the wages of any laborer or mechanic the amount of any costs reasonably anticipated in providing bona fide fringe benefits under a plan or program, Provided, That the Secretary of Labor has found, upon the written request of the Contractor, that the applicable standards of the Xxxxx-Xxxxx Act have been met. The Secretary of Labor may require the Contractor to set aside in a separate account assets for the meeting of obligations under the plan or program.
(2) Withholding. The Department of Energy or the Recipient or Subrecipient shall upon its own action or upon written request of an authorized representative of the Department of Labor withhold or cause to be withheld from the Contractor under this Contract or any other Federal contract with the same prime contractor, or any other federally-assisted contract subject to Xxxxx-Xxxxx prevailing wage requirements, which is held by the same prime contractor, so much of the accrued payments or advances as may be considered necessary to pay laborers and mechanics, including apprentices, trainees, and helpers, employed by the Contractor or any subcontractor the full amount of wages required by the Contract. In the event of failure to pay any laborer or mechanic, including any apprentice, trainee, or helper, employed or working on the site of the work (or under the United States Housing Act of 1937 or under the Housing Act of 1949 in the construction or development of the project), all or part of the wages required by the Contract, the Department of Energy, Recipient, or Subrecipient, may, after written notice to the Contractor, sponsor, applicant, or owner, take such action as may be necessary to cause the suspension of any further payment, advance, or guarantee of funds until such violations have ceased.
Page 18 of 24
(3) Payrolls and basic records.
(i) Payrolls and basic records relating thereto shall be maintained by the Contractor during the course of the work and preserved for a period of three years thereafter for all laborers and mechanics working at the site of the work (or under the United States Housing Act of 1937, or under the Housing Act of 1949, in the construction or development of the project). Such records shall contain the name, address, and social security number of each such worker, his or her correct classification, hourly rates of wages paid (including rates of contributions or costs anticipated for bona fide fringe benefits or cash equivalents thereof of the types described in section 1(b)(2)(B) of the Xxxxx-Xxxxx Act), daily and weekly number of hours worked, deductions made and actual wages paid. Whenever the Secretary of Labor has found under 29 CFR 5.5(a)(1)(iv) that the wages of any laborer or mechanic include the amount of any costs reasonably anticipated in providing benefits under a plan or program described in section 1(b)(2)(B) of the Xxxxx-Xxxxx Act, the Contractor shall maintain records which show that the commitment to provide such benefits is enforceable, that the plan or program is financially responsible, and that the plan or program has been communicated in writing to the laborers or mechanics affected, and records which show the costs anticipated or the actual cost incurred in providing such benefits. Contractors employing apprentices or trainees under approved programs shall maintain written evidence of the registration of apprenticeship programs and certification of trainee programs, the registration of the apprentices and trainees, and the ratios and wage rates prescribed in the applicable programs.
(ii) | (A) The Contractor shall submit weekly for each week in which any Contract work is performed a copy of all payrolls to the Department of Energy if the agency is a party to the Contract, but if the agency is not such a party, the Contractor will submit the payrolls to the Recipient or Subrecipient (as applicable), applicant, sponsor, or owner, as the case may be, for transmission to the Department of Energy. The payrolls submitted shall set out accurately and completely all of the information required to be maintained under 29 CFR 5.5(a)(3)(i), except that full social security numbers and home addresses shall not be included on weekly transmittals. Instead the payrolls shall only need to include an individually identifying number for each employee (e.g., the last four digits of the employee’s social security number). The required weekly payroll information may be submitted in any form desired. Optional Form WH-347 is available for this purpose from the Wage and Hour Division Web site at xxxx://xxx.xxx.xxx/xxx/xxx/xxxxx/xx000xxxxx.xxx or its successor site. The prime Contractor is responsible for the submission of copies of payrolls by all subcontractors. Contractors and subcontractors shall maintain the full social security number and current address of each covered worker, and shall provide them upon request to the Department of Energy if the agency is a party to the Contract, but if the agency is not such a party, the Contractor will submit them to the Recipient or Subrecipient (as applicable), applicant, sponsor, or owner, as the case may be, for transmission to the Department of Energy, the Contractor, or the Wage and Hour Division of the Department of Labor for purposes of an investigation or audit of compliance with prevailing wage requirements. It is not a violation of this section for a prime contractor to require a subcontractor to provide addresses and social security numbers to the prime contractor for its own records, without weekly submission to the sponsoring government agency (or the Recipient or Subrecipient (as applicable), applicant, sponsor, or owner). |
(B) Each payroll submitted shall be accompanied by a “Statement of Compliance,” signed by the Contractor or subcontractor or his or her agent who pays or supervises the payment of the persons employed under the Contract and shall certify the following:
(1) That the payroll for the payroll period contains the information required to be provided under § 5.5 (a)(3)(ii) of Regulations, 29 CFR part 5, the appropriate information is being maintained under § 5.5 (a)(3)(i) of Regulations, 29 CFR part 5, and that such information is correct and complete;
Page 19 of 24
(2) That each laborer or mechanic (including each helper, apprentice, and trainee) employed on the Contract during the payroll period has been paid the full weekly wages earned, without rebate, either directly or indirectly, and that no deductions have been made either directly or indirectly from the full wages earned, other than permissible deductions as set forth in Regulations, 29 CFR part 3;
(3) That each laborer or mechanic has been paid not less than the applicable wage rates and fringe benefits or cash equivalents for the classification of work performed, as specified in the applicable wage determination incorporated into the Contract.
(C) The weekly submission of a properly executed certification set forth on the reverse side of Optional Form WH-347 shall satisfy the requirement for submission of the “Statement of Compliance” required by paragraph (a)(3)(ii)(B) of this section.
(D) The falsification of any of the above certifications may subject the Contractor or subcontractor to civil or criminal prosecution under section 1001 of title 18 and section 3729 of title 31 of the United States Code.
(iii) The Contractor or subcontractor shall make the records required under paragraph (a)(3)(i) of this section available for inspection, copying, or transcription by authorized representatives of the Department of Energy or the Department of Labor, and shall permit such representatives to interview employees during working hours on the job. If the Contractor or subcontractor fails to submit the required records or to make them available, the Federal agency may, after written notice to the Contractor, sponsor, applicant, or owner, take such action as may be necessary to cause the suspension of any further payment, advance, or guarantee of funds. Furthermore, failure to submit the required records upon request or to make such records available may be grounds for debarment action pursuant to 29 CFR 5.12.
(4) Apprentices and trainees—
(i) Apprentices. Apprentices will be permitted to work at less than the predetermined rate for the work they performed when they are employed pursuant to and individually registered in a bona fide apprenticeship program registered with the U.S. Department of Labor, Employment and Training Administration, Office of Apprenticeship Training, Employer and Labor Services, or with a State Apprenticeship Agency recognized by the Office, or if a person is employed in his or her first 90 days of probationary employment as an apprentice in such an apprenticeship program, who is not individually registered in the program, but who has been certified by the Office of Apprenticeship Training, Employer and Labor Services or a State Apprenticeship Agency (where appropriate) to be eligible for probationary employment as an apprentice. The allowable ratio of apprentices to journeymen on the job site in any craft classification shall not be greater than the ratio permitted to the Contractor as to the entire work force under the registered program. Any worker listed on a payroll at an apprentice wage rate, who is not registered or otherwise employed as stated above, shall be paid not less than the applicable wage rate on the wage determination for the classification of work actually performed. In addition, any apprentice performing work on the job site in excess of the ratio permitted under the registered program shall be paid not less than the applicable wage rate on the wage determination for the work actually performed. Where a Contractor is performing construction on a project in a locality other than that in which its program is registered, the ratios and wage rates (expressed in percentages of the journeyman’s hourly rate) specified in the Contractor’s or subcontractor’s registered program shall be observed. Every apprentice must be paid at not less than the rate specified in the registered program for
Page 20 of 24
the apprentice’s level of progress, expressed as a percentage of the journeymen hourly rate specified in the applicable wage determination. Apprentices shall be paid fringe benefits in accordance with the provisions of the apprenticeship program. If the apprenticeship program does not specify fringe benefits, apprentices must be paid the full amount of fringe benefits listed on the wage determination for the applicable classification. If the Administrator determines that a different practice prevails for the applicable apprentice classification, fringes shall be paid in accordance with that determination. In the event the Office of Apprenticeship Training, Employer and Labor Services, or a State Apprenticeship Agency recognized by the Office, withdraws approval of an apprenticeship program, the Contractor will no longer be permitted to utilize apprentices at less than the applicable predetermined rate for the work performed until an acceptable program is approved.
(ii) Trainees. Except as provided in 29 CFR 5.16, trainees will not be permitted to work at less than the predetermined rate for the work performed unless they are employed pursuant to and individually registered in a program which has received prior approval, evidenced by formal certification by the U.S. Department of Labor, Employment and Training Administration. The ratio of trainees to journeymen on the job site shall not be greater than permitted under the plan approved by the Employment and Training Administration. Every trainee must be paid at not less than the rate specified in the approved program for the trainee’s level of progress, expressed as a percentage of the journeyman hourly rate specified in the applicable wage determination. Trainees shall be paid fringe benefits in accordance with the provisions of the trainee program. If the trainee program does not mention fringe benefits, trainees shall be paid the full amount of fringe benefits listed on the wage determination unless the Administrator of the Wage and Hour Division determines that there is an apprenticeship program associated with the corresponding journeyman wage rate on the wage determination which provides for less than full fringe benefits for apprentices. Any employee listed on the payroll at a trainee rate who is not registered and participating in a training plan approved by the Employment and Training Administration shall be paid not less than the applicable wage rate on the wage determination for the classification of work actually performed. In addition, any trainee performing work on the job site in excess of the ratio permitted under the registered program shall be paid not less than the applicable wage rate on the wage determination for the work actually performed. In the event the Employment and Training Administration withdraws approval of a training program, the Contractor will no longer be permitted to utilize trainees at less than the applicable predetermined rate for the work performed until an acceptable program is approved.
(iii) Equal employment opportunity. The utilization of apprentices, trainees and journeymen under this part shall be in conformity with the equal employment opportunity requirements of Executive Order 11246, as amended and 29 CFR part 30.
(5) Compliance with Xxxxxxxx Act requirements. The Contractor shall comply with the requirements of 29 CFR part 3, which are incorporated by reference in this Contract.
(6) Contracts and Subcontracts. The Recipient, Subrecipient, the Recipient’s and Subrecipient’s contractors and subcontractor shall insert in any Contracts the clauses contained herein in(a)(1) through (10) and such other clauses as the Department of Energy may by appropriate instructions require, and also a clause requiring the subcontractors to include these clauses in any lower tier subcontracts. The Recipient shall be responsible for the compliance by any subcontractor or lower tier subcontractor with all of the paragraphs in this clause.
(7) Contract termination: debarment. A breach of the Contract clauses in 29 CFR 5.5 may be grounds for termination of the Contract, and for debarment as a contractor and a subcontractor as provided in 29 CFR 5.12.
(8) Compliance with Xxxxx-Xxxxx and Related Act requirements. All rulings and interpretations of the Xxxxx-Xxxxx and Related Acts contained in 29 CFR parts 1, 3, and 5 are herein incorporated by reference in this Contract.
Page 21 of 24
(9) Disputes concerning labor standards. Disputes arising out of the labor standards provisions of this Contract shall not be subject to the general disputes clause of this Contract. Such disputes shall be resolved in accordance with the procedures of the Department of Labor set forth in 29 CFR parts 5, 6, and 7. Disputes within the meaning of this clause include disputes between the Recipient, Subrecipient, the Contractor (or any of its subcontractors) and the contracting agency, the U.S. Department of Labor, or the employees or their representatives.
(10) Certification of eligibility.
(i) By entering into this Contract, the Contractor certifies that neither it (nor he or she) nor any person or firm who has an interest in the Contractor’s firm is a person or firm ineligible to be awarded Government contracts by virtue of section 3(a) of the Xxxxx-Xxxxx Act or 29 CFR 5.12(a)(1).
(ii) No part of this Contract shall be subcontracted to any person or firm ineligible for award of a Government contract by virtue of section 3(a) of the Xxxxx-Xxxxx Act or 29 CFR 5.12(a)(1).
(iii) The penalty for making false statements is prescribed in the U.S. Criminal Code, 18 U.S.C. 1001.
(b) Contract Work Hours and Safety Standards Act. As used in this paragraph, the terms laborers and mechanics include watchmen and guards.
(1) Overtime requirements. No Contractor or subcontractor contracting for any part of the Contract work which may require or involve the employment of laborers or mechanics shall require or permit any such laborer or mechanic in any workweek in which he or she is employed on such work to work in excess of forty hours in such workweek unless such laborer or mechanic receives compensation at a rate not less than one and one-half times the basic rate of pay for all hours worked in excess of forty hours in such workweek.
(2) Violation; liability for unpaid wages; liquidated damages. In the event of any violation of the clause set forth in paragraph (b)(1) of this section the Contractor and any subcontractor responsible therefore shall be liable for the unpaid wages. In addition, such Contractor and subcontractor shall be liable to the United States (in the case of work done under contract for the District of Columbia or a territory, to such District or to such territory), for liquidated damages. Such liquidated damages shall be computed with respect to each individual laborer or mechanic, including watchmen and guards, employed in violation of the clause set forth in paragraph (b)(1) of this section, in the sum of $10 for each calendar day on which such individual was required or permitted to work in excess of the standard workweek of forty hours without payment of the overtime wages required by the clause set forth in paragraph (b)(1) of this section.
(3) Withholding for unpaid wages and liquidated damages. The Department of Energy or the Recipient or Subrecipient shall upon its own action or upon written request of an authorized representative of the Department of Labor withhold or cause to be withheld, from any moneys payable on account of work performed by the Contractor or subcontractor under any such contract or any other Federal contract with the same prime Contractor, or any other federally-assisted contract subject to the Contract Work Hours and Safety Standards Act, which is held by the same prime contractor, such sums as may be determined to be necessary to satisfy any liabilities of such Contractor or subcontractor for unpaid wages and liquidated damages as provided in the clause set forth in paragraph (b)(2) of this section.
Page 22 of 24
(4) Contracts and Subcontracts. The Recipient, Subrecipient, and Recipient’s and Subrecipient’s contractor or subcontractor shall insert in any Contracts, the clauses set forth in paragraph (b)(1) through (4) of this section and also a clause requiring the subcontractors to include these clauses in any lower tier subcontracts. The Recipient shall be responsible for compliance by any subcontractor or lower tier subcontractor with the clauses set forth in paragraphs (b)(1) through (4) of this section.
(5) The Contractor or subcontractor shall maintain payrolls and basic payroll records during the course of the work and shall preserve them for a period of three years from the completion of the Contract for all laborers and mechanics, including guards and watchmen, working on the Contract. Such records shall contain the name and address of each such employee, social security number, correct classifications, hourly rates of wages paid, daily and weekly number of hours worked, deductions made, and actual wages paid. The records to be maintained under this paragraph shall be made available by the Contractor or subcontractor for inspection, copying, or transcription by authorized representatives of the Department of Energy and the Department of Labor, and the Contractor or subcontractor will permit such representatives to interview employees during working hours on the job.
RECIPIENT FUNCTIONS
(1) This delegation of Department of Energy (DOE) functions to the Recipient applies only to DBA effort performed by Subrecipients and Contractors under this award. Those functions are not delegated to the Recipient for any DBA effort performed by employees of the Recipient under this award. On behalf of the Department of Energy (DOE), Recipient shall perform the following functions:
(a) Obtain, maintain, and monitor all DBA certified payroll records submitted by the Subrecipients and Contractors at any tier under this Award;
(b) Review all DBA certified payroll records for compliance with DBA requirements, including applicable DOL wage determinations;
(c) Notify DOE of any non-compliance with DBA requirements by Subrecipients or Contractors at any tier, including any non-compliances identified as the result of reviews performed pursuant to paragraph (b) above;
(d) Address any Subrecipient and any Contractor DBA non-compliance issues; if DBA non-compliance issues cannot be resolved in a timely manner, forward complaints, summary of investigations and all relevant information to DOE;
(e) Provide DOE with detailed information regarding the resolution of any DBA non-compliance issues;
(f) Perform services in support of DOE investigations of complaints filed regarding noncompliance by Subrecipients and Contractors with DBA requirements;
(g) Perform audit services as necessary to ensure compliance by Subrecipients and Contractors with DBA requirements and as requested by the Contracting Officer; and
(h) Provide copies of all records upon request by DOE or DOL in a timely manner.
(2) All records maintained on behalf of the DOE in accordance with paragraph (1) above are federal government (DOE) owned records. DOE or an authorized representative shall be granted access to the records at all times.
(3) In the event of, and in response to any Freedom of Information Act, 5 U.S.C. 552, requests submitted to DOE, Recipient shall provide such records to DOE within 5 business days of receipt of a request from DOE.
NETL SPECIAL TERMS AND CONDITIONS
SUBRECIPIENT/SUBCONTRACT APPROVALS
a. At Risk Notice: The Recipient must obtain written approval by the Contracting Officer for reimbursement of costs associated with subrecipient/subcontractors/activities listed in paragraph b. below. No funds shall be expended on the subcontracts supporting the tasks identified in paragraph b. below unless DOE approval is provided. DOE does not guarantee or assume any obligation to reimburse costs incurred by the Recipient or subrecipient/subcontractor for these tasks, until approval is provided in writing by the Contracting Officer.
Page 23 of 24
b. Contracting Officer approval as set out above is requested for the following anticipated subcontractors/consultants:
Competitive selection of the following subcontractors under this agreement. The DOE Contracting Officer may require detailed budget information concerning these selections prior to providing written approval.
Subcontractors/Consultants Description | Budget Period 1 (10/01/2010) | Budget Period 2 (04/01/2012) | Budget Period 3 (10/01/2013) | Task(s) | ||||||||||||||
A | Design full-scale process equipment and conduct process modeling efforts | $ | 745,000 | $ | 69,998 | $ | 115,000 | 2 | ||||||||||
B | Independent assessment of pilot performance and assessment of full-scale design | — | — | $ | 411,687 | 7,9 | ||||||||||||
C | Coordinate environmental regulation compliance and permitting | $ | 50,000 | — | — | 1 | ||||||||||||
D | Structural Engineering and Foundation Installation | $ | 100,000 | $ | 225,000 | — | 3,6 | |||||||||||
E | Emissions testing and removal performance validation | — | — | $ | 30,000 | 7 | ||||||||||||
F | Fabrication and Installation of 1MW pilot at test location | — | $ | 3,065,000 | 5,6 | |||||||||||||
G | Scale up of sorbent production process and sorbent cost reduction goals | — | $ | 1,500,000 | — | 4 | ||||||||||||
H | Design of stream circuitry to interface the plant with the 1MW pilot | $ | 30,000 | — | 3 | |||||||||||||
Total Anticipated Costs | $ | 925,000 | $ | 4,859,998 | $ | 556,687 |
c. Upon written approval by the Contracting Officer, the Recipient may then receive payment for subcontract efforts with the selected and DOE approved subrecipient/subcontractor for allowable costs incurred, or DOE will recognize costs incurred toward cost share requirements, if any, in accordance with the payment provisions contained in this agreement.
d. Termination or Suspension: If the above requirement is not fully complied with to the satisfaction of the Contracting Officer, the Contracting Officer may unilaterally terminate or suspend the activity proposed to be undertaken by the subrecipient/subcontractor. The Recipient agrees that DOE has the unilateral right to deobligate the amounts obligated or to redirect the funding to other efforts. If an effort is terminated or suspended, the Recipient shall not be reimbursed for costs incurred which were incurred at the Recipient’s risk as described in paragraph a. above.
HOST SITE AGREEMENT
Recipient shall provide a copy of the host-site agreement to DOE before any work is performed or any costs incurred at the host site location.
Page 24 of 24