Exhibit 10.15
THE AMERICAN INSTITUTE 0F ARCHITECTS
AIA Document A1 1 1
Standard Form of Agreement
Between Owner and Contractor
where the basis of payment is the
COST OF THE WORK PLUS A FEE
with or without a Guaranteed Maximum Price
1987 EDITION
THIS DOCUMENT HAS IMPORTANT LEGAL CONSEQUENCES; CONSULTATION WITH
AN ATTORNEY IS ENCOURAGED WITH RESPECT TO ITS COMPLETION OR MODIFICATION.
The 1987 Edition of AIA Document A201, General Conditions of the Contract for
Construction, is adopted in this document by reference. Do not use with other
general conditions unless this document is modified.
This document has been approved and endorsed by The Associated General
Contractors of America.
AGREEMENT
made as of the Sixth day of January in the year of Nineteen Hundred and Ninety
Seven
BETWEEN the Owner: AMISYS Managed Care Systems, Inc.
(Name and address) 00 X. Xxxx Xxxxx
Xxxxxxxxx, XX 00000
and the Contractor: Rand Construction Corporation
(Name and address) 0000 Xxxxxxxxxx Xxxx., Xxxxx 000
Xxxxxxxxx, XX 00000
the Project is: AMISYS Managed Care Systems, Inc.
(Name and address) 00 Xxxx Xxxx Xxxxx
Xxxxxxxxx, XX 00000
the Architect is: DBI Architects, P.C.
(Name and address) 0000 X Xxxxxx, X.X.
Xxxxx 000
Xxxxxxxxxx, XX 00000
The Owner and Contractor agree as set forth below.
ARTICLE 1
---------
THE CONTRACT DOCUMENTS
1.1 The Contract Documents consist of this Agreement, Conditions of the
Contract (General, Supplementary and other Conditions), Drawings,
Specifications, Addenda issued prior to execution of this Agreement, other
documents listed in this Agreement and Modifications issued after execution of
this Agreement; these form the Contract, and are as fully a part of the Contract
as if attached to this Agreement or repeated herein. The Contract represents the
entire and integrated agreement between the parties hereto and supersedes prior
negotiations, representations or agreements, either written or oral. An
enumeration of the Contract Documents, other than Modifications, appears in
Article 16. If anything in the other Contract Documents (except for
modifications) is inconsistent with this Agreement, this Agreement shall govern.
ARTICLE 2
---------
THE WORK OF THIS CONTRACT
2.1 The Contractor shall execute the entire Work described in the Contract
Documents, except to the extent specifically indicated in the Contract Documents
to be the responsibility of others, or as follows:
Renovate the lower level (4,209 RSF), 1/2 of the first floor (10,528 RSF), and
all of the third (25,089 RSF), fourth (25,089) and fifth floors (25,089). The
project will be completed in ten phases.
ARTICLE 3
---------
RELATIONSHIP OF THE PARTIES
3.1 The Contractor accepts the relationship of trust and confidence
established by this Agreement and covenants with the Owner to cooperate with the
Architect and utilize the Contractor's best skill, efforts and judgment in
furthering the interests of the Owner: to furnish efficient business
administration and supervision; to make best efforts to furnish at all times an
adequate supply of workers and materials; and to perform the Work in the best
way and most expeditious and economical manner consistent with the interests of
the Owner. The Owner agrees to exercise best efforts to enable the Contractor to
perform the Work in the best way and most expeditious manner by furnishing and
approving in a timely way information required by the Contractor and making
payments to the Contractor in accordance with requirements of the Contract
Documents
ARTICLE 4
---------
DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION
4.1 The date of commencement is the date from which the Contract Time of
Subparagraph 4.2 is measured: it shall be the date of this Agreement, as first
written above, unless a different date is stated below or provision is made for
the date to be fixed in a notice to proceed issued by the Owner.
The commencement date is February 6, 1997
Unless the date of commencement is established by a notice to proceed issued by
the Owner, the Contractor shall notify the Owner in writing not less than five
days before commencing the Work to permit the timely filing of mortgages,
mechanic's liens and other security interests.
4.2 The Contractor shall achieve Substantial Completion of the entire Work
not later than November 1, 1997, based upon the approximate dates as follows:
Phase Date Phase Date Phase Date Phase Date
----- ---- ----- ---- ----- ---- ----- ----
1A 5/1/97 2A 6/13/97 3 8/1/97 5A 10/15/97
1B 5/1/97 2B 6/13/97 4A 10/1/97 5B 10/15/97
2C 6/13/97 4B 10/1/97
subject to adjustments of this Contract Time as provided in the Contract
Documents
(Insert provisions if any for liquidated damages relating to failure to complete
on time)
If the Contract has not achieved substantial completion of the entire work by
November 1, 1997, the Contractor agrees that it will pay a sum of $200 per day
for every day that the contract remains substantially completed.
ARTICLE 5
---------
CONTRACT SUM
5.1 The Owner shall pay the Contractor in current funds for the
Contractor's performance of the Contract the Contract Sum consisting of the Cost
of the Work as defined in Article 7 and the Contractor's Fee determined as
follows:
(State a lump sum percentage of Cost of the Work or other provision for
determining the Contactor's Fee, and explain how the Contractor's Fee is to be
adjusted for changes in the Work)
Performance and Payment Bond to be paid by AMISYS.
General Liability Insurance covered in Contractor's Fee.
$74,800 for General Conditions.
2 3/4% xxxx-up on subcontractor costs.
8% Markup for subcontractors approved change orders.
5.2 GUARANTEED MAXIMUM PRICE (IF APPLICABLE) No Guaranteed Maximum Price
5.2.1 The sum of the Cost of the Work and the Contractor's Fee is guaranteed
by the Contractor not to exceed Dollars ($ )
subject to additions and deductions by Change Order as provided in the Contract
Documents. Such maximum sum is referred to in the Contract Documents as the
Guaranteed Maximum Price. Costs which would cause the Guaranteed Maximum Price
to be exceeded shall be paid by the Contractor without reimbursement by the
Owner.
(Insert specific provisions if the Contractor is to participate in any savings)
5.2.2 The Guaranteed maximum Price is based upon the following alternates,
if any, which are described in the Contract Documents and are hereby accepted by
the Owner:
(State the numbers or other identification of accepted alternates, but only if a
Guaranteed Maximum Price is inserted in Subparagraph 5.2. 1. If decisions on
other alternates are to be made by the owner subsequent to the execution of such
other alternatives showing the amount for each and the date until which that
amount is valid.)
5.2.3 The amounts agreed to for unit prices, if any, are as follows:
(State unit prices only if a Guaranteed Maximum Price is inserted in
Subparagraph 5.2.1.)
N/A
ARTICLE 6
---------
CHANGES IN THE WORK
6.1 CONTRACTS WITH A GUARANTEED MAXIMUM PRICE
6.1.1 Adjustments to the Guaranteed Maximum Price on account of changes in
the Work may be determined by any of the methods listed in Subparagraph 7.3.3 of
the General Conditions.
6.1.2 In calculating adjustments to subcontracts (except those awarded with
the Owner's prior consent on the basis of cost plus a fee), the terms "cost" and
"fee" as used in Clause 7.3-3.3 of the General Conditions and the terms "costs"
and "a reasonable allowance for overhead and profit" as used in Subparagraph
7.3.6 of the General Conditions shall have the meanings assigned to them in the
General Conditions and shall not be modified by Articles 5, 7 and 8 of this
Agreement. Adjustments to subcontracts awarded with the Owner's prior consent on
the basis of cost plus a fee shall be calculated in accordance with the terms of
those subcontracts.
6.1.3 In calculating adjustments to this Contract, the terms "cost" and
"costs" as used in the above-referenced provisions of the General Conditions
shall mean the Cost of the Work as defined in Article 7 of this Agreement and
the terms "fee" and "a reasonable allowance for overhead and profit" shall mean
the Contractor's Fee as defined in Paragraph 5.1 of this Agreement.
6.2 CONTRACTS WITHOUT A GUARANTEED MAXIMUM PRICE
6.2.1 Increased costs for the items set forth in Article 7 which result from
changes in the Work shall become part of the Cost of the Work, and the
Contractor's Fee shall be adjusted as provided in Paragraph 5. 1.
6.3 ALL CONTRACTS
6.3.1 If no specific provision is made in Paragraph 5.1 for adjustment of
the Contractor's Fee in the case of changes in the Work, or if the extent of
such changes is such, in the aggregate, that application of the adjustment
provisions of Paragraph 5.1 will cause Substantial inequity to the Owner or
Contractor, the Contractor's Fee shall be equitably adjusted on the basis of the
Fee established for the original Work.
ARTICLE 7
---------
COSTS TO BE REIMBURSED
7.1
7.1.1 All work is subcontracted
7.1.2 SUBCONTRACT COSTS
Payments made by the Contractor to Subcontractors in accordance with the
requirements of the subcontracts and as approved by the owner.
7.1.3 COSTS OF MATERIALS AND EQUIPMENT INCORPORATED IN THE COMPLETED
CONSTRUCTION
7.1.3.1 Costs, including transportation, of materials and equipment
incorporated or to be incorporated in the completed construction.
7.1.3.2 Costs of materials described in the preceding Clause 7.1.3.1 in excess
of those actually installed but required to provide reasonable allowance for
waste and for spoilage. Unused excess materials, if any, shall be handed over to
the Owner at the completion of the Work or, at the Owner's option, shall be sold
by the Contractor; amounts realized, if any, from such sales shall be credited
to the Owner as a deduction from the Cost of the Work.
7.1.4 COSTS OF OTHER MATERIALS AND EQUIPMENT, TEMPORARY FACILITIES AND
RELATED ITEMS
7.1.4.1 Costs, including transportation, installation, maintenance,
dismantling and removal of materials, supplies, temporary facilities, machinery,
equipment, and hand tools not customarily owned by the construction workers,
which are provided by the Contractor at the site and fully consumed in the
performance of the Work; and cost less salvage value on such items if not fully
consumed, whether sold to others or retained by the Contractor. Cost for items
previously used by the Contractor shall mean fair market value.
7.1.4.2 Rental charges for temporary facilities-, machinery, equipment, and
hand tools not customarily owned by the construction workers, which are provided
by the Contractor at the site whether rented from the Contractor or others, and
costs of transportation, installation, minor repairs and replacements,
dismantling and removal thereof. Rates and quantities of equipment rented shall
be subject to the Owner's prior approval.
7.1.4.3 Costs of removal of debris from the site.
7.1.4.4 Costs of telegrams and long-distance telephone calls, postage and
parcel delivery charges, telephone service at the site and reasonable xxxxx cash
expenses of the site office.
7.1.4.5 That portion of the reasonable travel and subsistence expenses of the
Contractor's personnel incurred while traveling in discharge of duties connected
with the Work.
7.1.5 MISCELLANEOUS COSTS
7.1.5.1 That portion directly attributable to this Contract for bonds.
7.1.5.2 Sales, use or similar taxes imposed by a governmental authority which
are related to the Work and for which the Contractor is liable.
7.1.5.3 Fees and assessments for the building permit and for other permits,
licenses and inspections for which the Contractor is required by the Contract
Documents to pay.
7.1.5.4 Fees of testing laboratories for tests required by the Contract
Documents, except those related to defective or nonconforming Work for which
reimbursement is excluded by Subparagraph 13.5.3 of the General Conditions or
other provisions of the Contract Documents and which do not fall within the
scope of Subparagraphs 7.2.2 through 7.2.4 below.
7.1.5.5 Royalties and license fees paid for the use of a particular design,
process or product specifically required by the Contract Documents; provided
that the Owner has agreed to pay such fees and royalties in advance the cost of
defending suits or claims for infringement of patent rights arising from such
requirement by the Contract Documents; payments made in accordance with legal
judgments against the Contractor resulting from such suits or claims and
payments of settlements made with the Owner's consent; provided, however, that
such costs of legal defenses, judgment and settlements shall only be payable if
owner is informed of such a suit or claim and is provided exclusive control over
the litigation and settlement there of and not be included in the calculation of
the Contractor's Fee or of a Guaranteed Maximum Price, if any, and provided that
such royalties, fees and costs are not excluded by the last sentence of
Subparagraph 3.17.1 of the General Conditions or other provisions of the
Contract Documents.
7.1.5.6 Deposits lost for causes due to Owner's fault or negligence.
7.1.6 OTHER COSTS
7.1.6.1 Other costs incurred in the performance of the Work if and to the
extent approved in advance in writing by the Owner.
7.2 EMERGENCIES: REPAIRS TO DAMAGED, DEFECTIVE OR NONCONFORMING WORK
The Cost of the Work shall also include costs described in Paragraph 7.1 which
are incurred by the Contractor-.
7.2.1 In taking action to prevent threatened damage, injury or loss in case
of an emergency affecting the safety of persons and property, as provided in
Paragraph 10.3 of the General Conditions.
ARTICLE 8
---------
COSTS NOT TO BE REIMBURSED
8.1 The Cost of the Work shall not include:
8.1.1 Salaries and other compensation of the Contractor's personnel
stationed at the Contractor's principal office or offices other than the site
office, except as specifically provided in Clauses 7.1.1.2 and 7.1.1.3 or as may
be provided in Article 14.
8.1.2 Expenses of the Contractor's principal office and offices other than
the site office.
8.1.3 Overhead and general expenses, except as may be expressly included in
Article 7.
8.1.4 The Contractor's capital expenses, including interest on the
Contractor's capital employed for the Work.
8.1.5 Rental costs of machinery and equipment, except as specifically
provided in Clause 7.1.4.2.
8.1.6 Costs due to the fault or negligence of the Contractor,
Subcontractors, anyone directly or indirectly employed by any of them, or for
whose acts any of them may be liable, including but not limited to costs for the
correction of damaged, defective or nonconforming Work, disposal and replacement
of materials and equipment incorrectly ordered or supplied, and making good
damage to property not forming part of the Work.
8.1.7 Any cost not specifically and expressly described in Article 7.
8.1.8 Costs which would cause the Guaranteed Maximum Price, if any, to be
exceeded.
ARTICLE 9
---------
DISCOUNTS, REBATES AND REFUNDS
9.1 Cash discounts obtained on payments made by the Contractor shall
accrue to the Owner if (1) before making the payment, the Contractor included
them in an Application for Payment and received payment therefor from the Owner,
or (2) the Owner has deposited funds with the Contractor with which to make
payments; otherwise, cash discounts shall accrue to the Contractor. Trade
discounts, rebates, refunds and amounts received from sales of surplus materials
and equipment shall accrue to the Owner, and the Contractor shall make
provisions so that they can be secured.
9.2 Amounts which accrue to the Owner in accordance with the provisions of
Paragraph 9.1 shall be credited to the Owner as a deduction from the Cost of the
Work.
ARTICLE 10
----------
SUBCONTRACTS AND OTHER AGREEMENTS
10.1 Those portions of the Work that the Contractor does not customarily
perform with the Contractor's own personnel shall be performed under
subcontracts or by other appropriate agreements with the Contractor. The
Contractor shall obtain bids from Subcontractors and from suppliers of materials
or equipment fabricated especially for the Work and shall deliver such bids to
the Architect. The Owner will then determine, with the advice of the Contractor
and subject to the reasonable objection of the Architect, which bids will be
accepted. The Owner may designate specific persons or entities from whom the
Contractor shall obtain bids; however, if a Guaranteed Maximum Price has been
established, the Owner may not prohibit the Contractor from obtaining bids from
others. The Contractor shall not be required to contract with anyone to whom the
Contractor has reasonable objection.
10.2 If a Guaranteed Maximum Price has been established and a specific
bidder among those whose bids are delivered by the Contractor to the Architect
(1) is recommended to the Owner by the Contractor; (2) is qualified to perform
that portion of the
Work; and (3) has submitted a bid which conforms to the requirements of the
Contract Documents without reservations or exceptions, but the Owner requires
that another bid be accepted;then the Contractor may require that a Change Order
be issued to adjust the Guaranteed Maximum Price by the difference between the
bid of the person or entity recommended to the Owner by the Contractor and the
amount of the subcontract or other agreement actually signed with the person or
entity designated by the Owner.
10.3 Subcontracts or other agreements shall conform to the payment
provisions of Paragraphs 12.7 and 12.8, and shall not be awarded on the basis of
cost plus a fee without the prior consent of the Owner.
ARTICLE 11
----------
ACCOUNTING RECORDS
11.1 The Contractor shall keep full and detailed accounts and exercise such
controls as may be necessary for proper financial management under this
Contract; the accounting and control systems shall be satisfactory to the Owner.
The Owner and the Owner's representative shall be afforded access to the
Contractor's records, books, correspondence, instructions, drawings, receipts,
subcontracts, purchase orders, vouchers, memoranda and other data relating to
this Contract, and the Contractor shall preserve these for a period of three
years after final payment, or for such longer period as may be required by law.
ARTICLE 12
----------
PROGRESS PAYMENTS
12.1 Based upon Applications for Payment submitted to the Architect by the
Contractor and Certificates for Payment issued by the Architect, the Owner shall
make progress payments on account of the Contract Sum to the Contractor as
provided below and elsewhere in the Contract Documents.
12.2 The period covered by each Application for Payment shall be one
calendar month ending on the last day of the month, or as follows:
12.3 Provided an Application for Payment is received by the Architect not
later than the last day of a month, the Owner shall make payment to the
Contractor not later than the fifteenth day of the month. If an Application for
Payment is received by, the Architect after the application date fixed above,
payment shall be made by the Owner not later than fifteen days after the
Architect receives the Application for Payment.
12.4 With each Application for Payment the Contractor shall submit
payrolls, xxxxx cash accounts, receipted invoices or invoices with check
vouchers attached, and any other evidence required by the Owner or Architect to
demonstrate that cash disbursements already made by the Contractor on account of
the Cost of the Work equal or exceed (1) progress payments already received by
the Contractor; less (2) that portion of those payments attributable to the
Contractor's Fee; plus (3) payrolls for the period covered by the present
Application for Payment; plus (4) retainage provided in Subparagraph 12.5.4, if
any, applicable to prior progress payments.
12.5 CONTRACTS WITH A GUARANTEED MAXIMUM PRICE N/A
12.5.1 Each Application for Payment shall be based upon the most recent
schedule of values submitted by the Contractor in accordance with the Contract
Documents. The schedule of values shall allocate the entire Guaranteed Maximum
Price among the various portions of the Work, except that the Contractor's Fee
shall be shown as a single separate item. The schedule of values shall be
prepared in such form and supported by such data to substantiate its accuracy as
the Architect may require. This schedule, unless objected to by the Architect,
shall be used as a basis for reviewing the Contractor's Applications for
Payment.
12.5.2 Applications for Payment shall show the percentage completion of each
portion of the Work as of the end of the period covered by the Application for
Payment. The percentage completion shall be the lesser of (1) the percentage of
that portion of the Work which has actually been completed or (2) the percentage
obtained by dividing (a) the expense which has actually been incurred by the
Contractor on account of that portion of the Work for which the Contractor has
made or intends to make actual payment prior to the next Application for Payment
by (b) the share of the Guaranteed Maximum Price allocated to that portion of
the Work in the schedule of values.
12.5.3 Subject to other provisions of the Contract Documents, the amount of
each progress payment shall be computed as follows:
12.5.3.1 Take that portion of the Guaranteed Maximum Price properly allocable
to completed Work as determined by multiplying the percentage completion of each
portion of the Work by the share of the Guaranteed Maximum Price allocated to
that portion of the Work in the schedule of values. Pending final determination
of cost to the Owner of changes in the Work, amounts not in dispute may be
included as provided in Subparagraph 7.3.7 of the General Conditions, even
though the Guaranteed Maximum Price has not yet been adjusted by Change Order.
12.5.3.2 Add that portion of the Guaranteed Maximum Price properly allocable to
materials and equipment delivered and suitably stored at the site for subsequent
incorporation in the Work or, if approved in advance by the Owner, suitably
stored off the site at a location agreed upon in writing.
12.5.3.3 Add the Contractor's Fee, less retainage of percent( %). The
Contractor's Fee shall be computed upon the Cost of the Work described in the
two preceding Clauses at the rate stated in Paragraph 5.1 or, if the
Contractor's Fee is stated as a fixed sum in that Paragraph, shall be an amount
which bears the same ratio to that fixed-sum Fee as the Cost of the Work in the
two preceding Clauses bears to a reasonable estimate of the probable Cost of the
Work upon its completion.
12.5.3.4 Subtract the aggregate of previous payments made by the Owner.
12.5.3.5 Subtract the shortfall, if any, indicated by the Contractor in the
documentation required by Paragraph 12.4 to substantiate prior Applications for
Payment, or resulting from errors subsequently discovered by the Owner's
accountants in such documentation.
12.5.3.6 Subtract amounts, if any, for which the Architect has withheld or
nullified a Certificate for Payment as provided in Paragraph 9.5 of the General
Conditions.
12.5.4 Additional retainage, if any, shall be as follows:
(If it is intended to retain additional amounts from progress payments to the
Contractor beyond (1) the retainage from the Contractor's Fee provided in Clause
12.5.3.3, (2) the retainage from Subcontractors provided in Paragraph 12.7
below, and (3) the retainage, if any, provided by other provisions of the
Contract, insert provision for such additional retainage here. Such provision,
if made, should also describe any arrangement for limiting or reducing the
amount retained after the Work reaches a certain state of completion.)
12.6 CONTRACTS WITHOUT A GUARANTEED MAXIMUM PRICE
12.6.1 Applications for Payment shall show the Cost of the Work actually
incurred by the Contractor through the end of the period covered by the
Application for Payment and for which the Contractor has made or intends to make
actual payment prior to the next Application for Payment.
12.6.2 Subject to other provisions of the Contract Documents, the amount of
each progress payment shall be computed as follows:
12.6.2.1 Take the Cost of the Work as described in Subparagraph 12.6. 1.
12.6.2.2 Add the Contractor's Fee, less retainage of Ten percent (10%). The
Contractor's Fee shall be computed upon the Cost of the Work described in the
preceding Clause 12.6.2.1 at the rate stated in Paragraph 5.1 or, if the
Contractor's Fee is stated as a fixed sum in that Paragraph, an amount which
bears the same ratio to that fixed-sum Fee as the Cost of the Work in the
preceding Clause bears to a reasonable estimate of the probable Cost of the Work
upon its completion.
12.6.2.3 Subtract the aggregate of previous payments made by the Owner.
12.6.2.4 Subtract the shortfall, if any, indicated by the Contractor in the
documentation required by Paragraph 12.4 or to substantiate prior Applications
for Payment or resulting from errors subsequently discovered by the Owner or
Owner's representatives in such documentation.
12.6.2.5 Subtract amounts, if any, for which the Architect has withheld or
withdrawn a Certificate for Payment as provided in the Contract Documents.
12.6.3 Additional retainage, if any, shall be as follows:
12.7 Except with the Owner's prior approval, payments to Subcontractors
included in the Contractor's Applications for Payment shall not exceed an amount
for each Subcontractor calculated as follows:
12.7.1 Take that portion of the Subcontract Sum properly allocable to
completed Work as determined by multiplying the percentage completion of each
portion of the Subcontractor's Work by the share of the total Subcontract Sum
allocated to that portion in the Subcontractor's schedule of values, less
retainage of Ten percent (10%). Pending final determination of amounts to be
paid to the Subcontractor for changes in the Work, amounts not in dispute may hb
included as provided in Subparagraph 7.3.7 of the General Conditions even though
the Subcontract Sum has not yet been adjusted by Change Order.
12.7.2 Add that portion of the Subcontract Sum properly allocable to
materials and equipment delivered and suitability stored at the site for
subsequent incorporation in the Work or, if approved in advance by the Owner,
suitably stored off the site at a location agreed upon in writing, less
retainage of Ten percent (10 %).
12.7.3 Subtract the aggregate of previous payments made by the Contractor to
the Subcontractor.
12.7.4 Subtract amounts, if any, for which the Architect has withheld or
nullified a Certificate for Payment by the owner to the Contractor for reasons
which are the fault of the Subcontractor.
12.7.5 Add, upon Substantial and satisfactory Completion of the entire Work
of the Contractor. a sum sufficient to increase the total payments to the
Subcontractor to One Hundred percent (100 %) of the Subcontract Sum, less
amounts, if any, for incomplete Work and unsettled claims; and, if final
completion of the entire Work is thereafter materially delayed through no fault
of the Subcontractor and all of the work of the subcontractor has been
satisfactorily completed, add any additional amounts payable on account of Work
of the Subcontractor in accordance with Subparagraph 9.10.3 of the General
Conditions. (If it is intended, prior to Substantial Completion of the entire
Work of the Contractor, to reduce or limit the retainage from Subcontractors
resulting from the percentages inserted in Subparagraphs 12.7.1 and 12.7.2
above, and this is not explained elsewhere in the Contract Documents, insert
here provisions for such reduction or limitation.)
The Subcontract Sum is the total amount stipulated in the subcontract to be paid
by the Contractor to the Subcontractor for the Subcontractor's performance of
the subcontract.
12.8 Except with the Owner's prior approval the Contractor shall not make
advance payments to suppliers for materials or equipment which have not been
delivered and stored at the site.
12.9 In taking action on the Contractor's Applications for Payment, the
Architect shall be entitled to rely on the accuracy and completeness of the
information furnished by the Contractor and shall not be deemed to represent
that the Architect has made a detailed examination, audit or arithmetic
verification of the documentation submitted in accordance with Paragraph 12.4 or
other supporting data; that the Architect has made exhaustive or continuous on-
site inspections or that the Architect has made examinations to ascertain how or
for what purposes the Contractor has used amounts previously paid on account of
the Contract. Such examinations, audits and verifications, if required by the
Owner, will be performed by the Owner or Owner's representatives acting in the
sole interest of the Owner.
ARTICLE 13
----------
FINAL PAYMENT
13.1 Final payment shall be made by the Owner to the Contractor when (1)
the Contract has been fully performed by the Contractor except for the
Contractor's responsibility to correct defective or nonconforming Work, as
provided in Subparagraph 12.2.2 of the General Conditions, and to satisfy other
requirements, if any, which necessarily survive final payment; (2) a final
Application for Payment and a final accounting for the Cost of the Work have
been submitted by the Contractor and reviewed by the Owner's accountants; and
(3) a final Certificate for Payment has then been issued by the Architect; such
final payment shall be made by the Owner not more than 30 days after the
issuance of the Architect's final Certificate for Payment, or as follows:
13.2 The amount of the final payment shall be calculated as follows:
13.2.1 Take the sum of the Cost of the Work substantiated by the Contractor's
final accounting and the Contractor's Fee; but not more than the Guaranteed
Maximum Price, if any.
13.2.2 Subtract amounts, if any, for which the Architect withholds, in whole
or in part, a final Certificate for Payment as provided in Subparagraph 9.5.1 of
the General Conditions or other provisions of the Contract Documents.
13.2.3 Subtract the aggregate of previous payment made by the Owner.
If the aggregate of previous payments made by the Owner exceeds the amount due
the Contractor, the Contractor shall reimburse the difference to the Owner.
13.3 The Owner's accountants will review and report in writing on the
Contractor's final accounting within 30 days after delivery of the final
accounting to the Architect by the Contractor. Based upon such Cost of the Work
as the Owner's accountants report to be substantiated by the Contractor's final
accounting, and provided the other conditions of Paragraph 13.1 have been met,
the Architect will, within seven days after receipt of the written report of the
Owner's accountants, either issue to the Owner a final Certificate for Payment
with a copy to the Contractor, or notify the Contractor and Owner in writing of
the Architect's reasons for withholding a certificate as provided in
Subparagraph 9.5.1 of the General Conditions. The time periods stated in this
Paragraph 13.3 supersede those stated in Subparagraph 9.4.1 of the General
Conditions.
13.4 If the Owner's accountants report the Cost of the Work as
substantiated by the Contractor's final accounting to be less than claimed by
the Contractor, the Contractor shall be entitled to demand arbitration of the
disputed amount without a further decision of the Architect. Such demand for
arbitration shall be made by the Contractor within 30 days after the
Contractor's receipt of a copy of the Architect's final Certificate for Payment;
failure to demand arbitration within this 30-day period shall result in the
substantiated amount reported by the Owner's accountants becoming binding on the
Contractor. Such Arbitration shall be held in Rockville, Maryland in accordance
with the rules of the American Arbitration Association before a single
arbitrator.
13.5 If, subsequent to final payment and at the Owner's request, the
Contractor incurs costs described in Article 7 and not excluded by Article 8 to
correct defective or nonconforming Work, the Owner shall reimburse the
Contractor such costs and the Contractor's Fee applicable thereto on the same
basis as if such costs had been incurred prior to few payment, but not in excess
of the Guaranteed Maximum Price, if any. If the Contractor has participated in
savings as provided in Paragraph 5.2, the amount of such savings shall be
recalculated and appropriate credit given to the Owner in determining the net
amount to be paid by the Owner to the Contractor.
ARTICLE 14
----------
MISCELLANEOUS PROVISIONS
14.1 Where reference is made in this Agreement to a provision of the
General Conditions or another Contract Document, the reference refers to that
provision as amended or supplemented by other provisions of the Contract
Documents.
14.2 Payments due and unpaid under the Contract shall bear interest from
the date payment is due at the rate stated below, or in the absence thereof, at
the legal rate prevailing from time to time at the place where the Project is
located.
(Insert rate of interest agreed upon, if any.)
2 % Above Prime
(Usury laws and requirements under the Federal Thumb in Lending Act, similar
state and local consumer credit laws and other regulations at the Owner's and
Contractor's principle places of business, the location of the Project and
elsewhere may affect the validity of this provision. Legal advice should be
obtained with respect to deletions and modifications, and also regarding
requirements such as written disclosures or waivers.)
14.3 Other provisions:
Contractor shall not assign this Agreement or subcontract its responsibility
without the prior written consent of the Owner. The Owner may assign this
agreement to a successor in interest to its assets.
This agreement shall be governed by and construed in accordance with the laws of
the State of Maryland.
ARTICLE 15
----------
TERMINATION OR SUSPENSION
15.1 The Contract may be terminated by the Contractor as provided in
Article 14 of the General Conditions-. however, the amount to be paid to the
Contractor under Subparagraph 14.1.2 of the General Conditions shall not exceed
the amount the Contractor would be entitled to receive under Paragraph 15.3
below.
15.2 If a Guaranteed Maximum Price is established in Article 5, the
Contract may be terminated by the Owner for cause as provided in Article 14 of
the General Conditions; however, the amount, if any, to be paid to the
Contractor under Subparagraph 14.2.4 of the General Conditions shall not cause
the Guaranteed Maximum Price to be exceeded, nor shall it exceed the amount the
Contractor would be entitled to receive under Paragraph 15.3 below.
15.3 If no Guaranteed Maximum Price is established in Article 5, the
Contract may be terminated by the Owner for cause as provided in Article 14 of
the General Conditions; however, the Owner shall then pay the Contractor an
amount calculated as follows.
15.3.1 Take the Cost of the Work incurred by the Contractor to the date of
termination.
15.3.2 Add the Contractor's Fee computed upon the Cost of the Work to the
date of termination at the rate stated in Paragraph 5.1 or, if the Contractor's
Fee is stated as a fixed sum in that Paragraph, an amount which bears the same
ratio to that fixed-sum Fee as the Cost of the Work at the time of termination
bears to a reasonable estimate of the probable Cost of the Work upon its
completion.
15.3.3 Subtract the aggregate of previous payments made by the Owner.
The Owner shall also pay the Contractor fair compensation, either by purchase or
rental at the election of the Owner, for any equipment owned by the Contractor
which the Owner elects to retain and which is not otherwise included in the Cost
of the Work under Subparagraph 15.3.1. To the extent that the Owner elects to
take legal assignment of subcontracts and purchase orders (including rental
agreements), the Contractor shall, as a condition of receiving the payments
referred to in this Article 15, execute and deliver all such papers and take all
such steps, including the legal assignment of such subcontracts and other
contractual rights of the Contractor, as the Owner may require for the purpose
of fully vesting in the Owner the rights and benefits of the Contractor under
such subcontracts or purchase orders.
15.4 The Work may be suspended by the Owner as provided in Article 14 of
the General Conditions; in such case, the Guaranteed Maximum Price, if any,
shall be increased as provided in Subparagraph 14.3.2 of the General Conditions
except that the term "cost of performance of the Contract" in that Subparagraph
shall be understood to mean the Cost of the Work and the term "profit" shall be
understood to mean the Contractor's Fee as described in Paragraphs 5.1 and 6.3
of this Agreement.
15.5 Should the contract be terminated by the Owner for cause, payment of
additional funds to contractor under paragraph 15.3 or otherwise shall not
affect any rights Owner may have under law to damages due to contractor actions
that give rise to the termination.
ARTICLE 16
----------
ENUMERATION OF CONTRACT DOCUMENTS
16.1 The Contract Documents, except for Modifications issued after
execution of this Agreement, are enumerated as follows:
16.1.1 The Agreement is this executed Standard Form of Agreement Between
Owner and Contractor, AIA Document A111, 1987 Edition.
16.1.2 The General Conditions are the General Conditions of the Contract for
Construction, AIA Document A201, 1987 Edition.
16.1.3 The Supplementary and other Conditions of the Contract are those
contained in the Project Manual dated and are as follows:
Document Title Pages
AIA A201 General Condition, Current Edition
16.1.4 The Specifications are those contained in the Project Manual dated as
in Paragraph 16.1-3, and are as follows: (Either list the specifications here or
refer to an exhibit attached to this agreement)
Section Title Pages
Bid/Construction Documents and specifications shall be issued and must be
approved by Owner for each phase of work.
16.1.5 The Drawings are as follows, and are dated unless a
different date is shown below:
(Either list the Drawings here or refer to an exhibit attached to this
agreement.)
Number Title Date
Bid/Contract Documents shall be issued and must be approved by Owner for each
phase of work.
16.1.6 The Addenda, if any, are as follows:
Number Date Pages
N/A
Portions of Addenda relating to bidding requirements are not part of the
Contract Documents unless the bidding requirements are also enumerated in this
Article 16.
16.1.7 Other Documents, if any, forming part of the Contract documents are as
follows:
(List here any documents which are intended to form part of the Contract
Documents. The General Conditions provide that bidding requirements such as
advertisement or invitation to bid. Instructions to bidders, sample forms and
the Contractor's bid are not part of the Contract Documents unless enumerated in
this Agreement. They should be listed here only if intended to be part of the
Contract Documents.)
This Agreement is entered into as of the day and year first written above and is
executed in at least three original copies of which one is to be delivered to
the Contractor, one to the Architect for use in the administration of the
Contract, and the remainder to the Owner.
OWNER CONTRACTOR
------------------------------------ ------------------------------------
(Signature) (Signature)
Xxxxx X. Xxxxxxx, President
------------------------------------ ------------------------------------
(Printed name and title) (Printed name and title)