Exhibit 10.23
THIRD AMENDMENT TO COST SHARING NATIONAL
IRU AGREEMENT
THIS THIRD AMENDMENT TO COST SHARING NATIONAL IRU AGREEMENT ("Amendment")
is made and entered into as of the 27th day of March 2000, by and between LEVEL
3 COMMUNICATIONS, LLC, a Delaware limited liability company ("Grantor") and
SPLITROCK SERVICES, INC., a Delaware corporation ("Grantee"). This Amendment
modifies and amends that certain Cost Sharing National IRU Agreement dated April
26, 1999 between Grantor and Grantee (the "Agreement"). Capitalized terms used
but not defined herein shall have the meanings set forth in the Agreement.
RECITALS
--------
A. Grantee desires to obtain an IRU in fibers within and along segments of
Grantor's lateral segments and metropolitan fiber-optic networks to connect
certain Segment End Points to Grantee Points of Presence.
B. Grantor desires to convey to Grantee an IRU in the additional fibers
specified herein, subject to and in accordance with the terms and provisions set
forth in this Amendment and the Agreement.
TERMS OF AMENDMENT
------------------
Accordingly, in consideration of the foregoing and other good and valuable
consideration, the receipt and sufficiency of which is hereby acknowledged,
Grantor and Grantee hereby agree as follows:
ARTICLE 1
METROPOLITAN SEGMENTS
---------------------
1.01 The Segments described in Exhibit "A," attached hereto, are hereby
----------
added to the Grantor System, and Grantor shall deliver an IRU in, and Grantee
shall accept and pay for, an IRU in the Grantee Fibers within and along such
Segments (the "Metropolitan Grantee Fibers"). Maps of the Segments are provided
in Exhibit "A-1," attached hereto.
------------
1.02 Grantee shall make the following payments with respect to the
Metropolitan Grantee Fibers.
a. The IRU Contribution for the Metropolitan Grantee Fibers of (***) shall
be allocated on a Segment by Segment basis, as identified in Exhibit "A". The
----------
IRU Contribution shall be due from Grantee to Grantor with respect to the
Metropolitan Grantee Fibers in each Segment as follows: (***).
b. The IRU Contribution for the Metropolitan Grantee Fibers set forth in
Section 1.02(a) is unique to the Segments described herein, and the Parties
recognize that any IRU
PAGE1
NOTE: Redacted portions have been marked with (***). The redacted portions are
subject to a request for confidential treatment that has been filed with the
Securities and Exchange Commission
Contribution for additional Fibers requested by Grantee
in other metropolitan Segments shall be subject to negotiation by the Parties.
1.03 Unless otherwise provided herein, for the purposes of the Agreement,
the Metropolitan Grantee Fibers shall be treated as Grantee Fibers.
Specifically, the Parties recognize that the Monthly Charge shall apply to the
Metropolitan Grantee Fibers.
1.04 Grantee shall have the Option for the Metropolitan Grantee Fibers to
extend the IRU in additional fibers as provided in Section 3.02 of the
Agreement.
1.05 The construction specifications for the Metropolitan Grantee Fibers
are attached hereto as Exhibit "C."
----------
1.06 The fiber, conduit, and cable vault specifications for the
Metropolitan Grantee Fibers are attached hereto as Exhibit "D."
----------
1.07 The fiber testing procedures for the Metropolitan Grantee Fibers are
attached hereto as Exhibit "E."
----------
ARTICLE 2
LATERAL SEGMENTS
----------------
2.01 Grantor shall construct and install the lateral segments described in
Exhibit "B," attached hereto, for Grantee in the metropolitan markets containing
----------
the Metropolitan Grantee Fibers (the "Lateral Segments"). The estimated costs
for constructing and installing the Lateral Segments are summarized in the
tables contained in Exhibit "B." Grantee shall be solely responsible for
----------
reimbursement of all of Grantor's Costs, subject to the agreed upon split, in
constructing and installing the Lateral Segments, regardless of whether the
actual Costs are above or below the estimates contained in Exhibit "B."
----------
Grantor's Costs shall be documented by Grantor in commercially reasonable detail
and shall be submitted to Grantee in the form of invoices with supporting
documentation.
2.02 Grantee shall reimburse Grantor for the Costs of the construction and
installation of the Lateral Segments within fifteen (15) days after receipt of
an invoice therefor, subject to Grantee's rights to dispute such Costs.
2.03 The Parties may add Lateral Segments by letter agreement between the
Parties, pursuant to Article 25.
PAGE2
NOTE: Redacted portions have been marked with (***). The redacted portions are
subject to a request for confidential treatment that has been filed with the
Securities and Exchange Commission
IN WITNESS WHEREOF, Grantor and Grantee have executed this Amendment
as of the date first above written.
LEVEL 3 COMMUNICATIONS, LLC, a
Delaware limited liability company
By/s/Xxx Xxxxx
------------------------------------------
Title: Vice President
------------------------------------------
Date: March 29, 2000
------------------------------------------
SPLITROCK SERVICES, INC.,
a Delaware corporation
By /s/ Xxxxxxx X. XxXxxxxxxx, Xx.
------------------------------------------
Title: Senior Vice President
------------------------------------------
Date: February 29, 2000
------------------------------------------
PAGE3
NOTE: Redacted portions have been marked with (***). The redacted portions are
subject to a request for confidential treatment that has been filed with the
Securities and Exchange Commission
Exhibit "A"
Metropolitan Grantee Fibers
---------------------------
Route Segment Estimated Fiber Price Per
Route Miles Count Mile
----------------------------------------------------------------------------------------------
# From Point To Point
----------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------
Cambridge Loop 11.35 4 (***)
----------------------------------------------------------------------------------------------
A-1 Gateway Bent & 3rd 4
----------------------------------------------------------------------------------------------
X-0 Xxxx & 0xx Xxxxxxxxx and 3rd 4
----------------------------------------------------------------------------------------------
X-0 Xxxxxxxxx & 0xx Xxxxxxxxx & Xxxxxxxxx 4
----------------------------------------------------------------------------------------------
X0-0 Xxxxxxxxx & Xxxxxxxxx Bent & Xxxxxxxxx 4
----------------------------------------------------------------------------------------------
A-18 Bent & Xxxxxxxxx Gateway 4
----------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------
LOOP A & C - NYC 9.4 4 (***)
----------------------------------------------------------------------------------------------
A-1 17th Xxxxxx & 0xx Xxx Xxxx Xxx & Xx Xxxxx 0
----------------------------------------------------------------------------------------------
X-0 Xxxx Xxx & Xx Xxxxx Xxxxxx & Water 4
-----------------------------------------------------------------------------------------------
A-3 Xxxxxx & Water Xxxxxx & Gold 4
-----------------------------------------------------------------------------------------------
X-0 Xxxxxxx & Xxxxxx 00xx Xx xxxxx & 0xx Xxx 0
-----------------------------------------------------------------------------------------------
X-0 00xx Xx xxxxx & 0xx Xxxxxxx (111 8th) 4
Ave
-----------------------------------------------------------------------------------------------
B-8 Gateway (111 8th) 00xx Xx & 0xx Xxx 0
-----------------------------------------------------------------------------------------------
C-1 Gateway (100 Xxxxxxx) Maiden & Water 4
-----------------------------------------------------------------------------------------------
X-0 Xxxxxx & Xxxxx Xxxx & Xxxxxxx Xxxxx 0
-----------------------------------------------------------------------------------------------
X-0 Xxxx & Xxxxxxx Xxxxx Xxxxxxx & Xxxxxx 0
------------------------------------------------------------------------------------------------
C-4 Xxxxxx & Gold Gateway (100 Xxxxxxx) 4
------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------
LOOP A - Dallas - Inner Loop 21.7 10 (***)
------------------------------------------------------------------------------------------------
X-0 Xxxxxxx Xxxxxxx & I-35 10
------------------------------------------------------------------------------------------------
A-2 Viceroy & X-00 Xxx 00 & Xxxxxxxxx 00
------------------------------------------------------------------------------------------------
X-0 Xxx 00 & Hillcrest Irving & Oak Lawn 10
------------------------------------------------------------------------------------------------
A-4 Irving & Oak Lawn Oak Lawn & Xxxxxx 10
------------------------------------------------------------------------------------------------
A-5 Oak Lawn & Xxxxxx Oak Lawn & Maple 10
------------------------------------------------------------------------------------------------
A-6 Oak Lawn & Maple Irving & Inwood 10
------------------------------------------------------------------------------------------------
A-7 Irving & Inwood Gateway 10
------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------
TOTALS 32.4
------------------------------------------------------------------------------------------------
NOTE: The Grantee Fibers shall terminate in the nearest underground utility box
at each of the sub-segment end points identified above.
NOTE: Redacted portions have been marked with (***). The redacted portions are
subject to a request for confidential treatment that has been filed with the
Securities and Exchange Commission
Exhibit "A"
Metropolitan Grantee Fibers
---------------------------
Route Segment (***) IRU (***) IRU Total IRU Scheduled
Contribution Contribution Contribution Completion Date
----------------------------------------------------------------------------------------------------------------------------------
# From Point To Point
----------------------------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------------------------
Cambridge Loop (***) (***) (***) (***)
----------------------------------------------------------------------------------------------------------------------------------
A-1 Gateway Bent & 3rd
----------------------------------------------------------------------------------------------------------------------------------
X-0 Xxxx & 0xx Xxxxxxxxx and 3rd
----------------------------------------------------------------------------------------------------------------------------------
X-0 Xxxxxxxxx & 0xx Xxxxxxxxx & Xxxxxxxxx
----------------------------------------------------------------------------------------------------------------------------------
X0-0 Xxxxxxxxx & Xxxxxxxxx Bent & Xxxxxxxxx
----------------------------------------------------------------------------------------------------------------------------------
A-18 Bent & Xxxxxxxxx Gateway
----------------------------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------------------------
LOOP A & C - NYC (***) (***) (***) (***)
----------------------------------------------------------------------------------------------------------------------------------
X-0 00xx Xxxxxx & 0xx Xxx Xxxx Xxx & St Xxxxx
----------------------------------------------------------------------------------------------------------------------------------
X-0 Xxxx Xxx & Xx Xxxxx Xxxxxx & Water
----------------------------------------------------------------------------------------------------------------------------------
A-3 Xxxxxx & Water Xxxxxx & Gold
----------------------------------------------------------------------------------------------------------------------------------
X-0 Xxxxxxx & Xxxxxx 00xx Xx alley & 9th Ave
----------------------------------------------------------------------------------------------------------------------------------
X-0 00xx Xx xxxxx & 0xx Xxxxxxx (111 8th)
Ave
----------------------------------------------------------------------------------------------------------------------------------
B-8 Gateway (111 8th) 00xx Xx & 0xx Xxx
----------------------------------------------------------------------------------------------------------------------------------
C-1 Gateway (100 Xxxxxxx) Maiden & Water
----------------------------------------------------------------------------------------------------------------------------------
X-0 Xxxxxx & Xxxxx Xxxx & Xxxxxxx Xxxxx
----------------------------------------------------------------------------------------------------------------------------------
X-0 Xxxx & Xxxxxxx Xxxxx Xxxxxxx & Church
----------------------------------------------------------------------------------------------------------------------------------
X-0 Xxxxxx & Xxxx Xxxxxxx (100 Xxxxxxx)
----------------------------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------------------------
LOOP A - Dallas - Inner Loop (***) (***) (***) (***)
----------------------------------------------------------------------------------------------------------------------------------
X-0 Xxxxxxx Xxxxxxx & I-35
----------------------------------------------------------------------------------------------------------------------------------
X-0 Xxxxxxx & X-00 Xxx 00 & Xxxxxxxxx
----------------------------------------------------------------------------------------------------------------------------------
X-0 Xxx 00 & Hillcrest Irving & Oak Lawn
----------------------------------------------------------------------------------------------------------------------------------
A-4 Irving & Oak Lawn Oak Lawn & Xxxxxx
----------------------------------------------------------------------------------------------------------------------------------
A-5 Oak Lawn & Xxxxxx Oak Lawn & Maple
----------------------------------------------------------------------------------------------------------------------------------
A-6 Oak Lawn & Maple Irving & Inwood
----------------------------------------------------------------------------------------------------------------------------------
A-7 Irving & Inwood Gateway
----------------------------------------------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------------------------------------------
TOTALS (***) (***) (***)
----------------------------------------------------------------------------------------------------------------------------------
NOTE: The Grantee Fibers shall terminate in the nearest underground utility box
at each of the sub-segment end points identified above.
PAGE4
NOTE: Redacted portions have been marked with (***). The redacted portions are
subject to a request for confidential treatment that has been filed with the
Securities and Exchange Commission
Exhibit "B"
Lateral Segments
----------------
000 Xxxx Xxxxxx, Xxxxxxxxx, XX
Estimated total cost: (***)
Estimated split cost: (***)
000 Xxxxxxxxx Xxxxxx, Xxxxxxx, XX
Estimated total cost: (***)
Estimated split cost: (***)
Assumes Grantor is on floor 2 and Grantee is on floor 3. Assumes 40 LF of new
riser to be built by Grantor and 440 LF total distance from Grantor OSX to
Grantee FTP.
000 X. 00xx Xxxxxx, Xxxxx 0000, Xxxxxx, XX
Estimated total cost: (***)
Estimated split cost: (***)
Assumes Grantor is on floor 1 and Grantee is on floor 1. Assumes 200 LF of new
riser to be built by Grantor and 250 LF total distance from Grantor OSX to
Grantee FTP.
000 Xxxx 0xx Xxxxxx, Xxx Xxxxxxx, XX
Estimated total cost: (***)
Estimated split cost: (***)
Assumes Grantor is on floor 11 and Grantee is on floor 4. Assumes 0 LF of new
riser to be built by Grantor and 440 LF total distance from Grantor OSX to
Grantee FTP.
0000 Xxxxxxxx Xxxxxxx, Xxxxx 0000, Xxxxxx, XX
Estimated total cost: (***)
Estimated split cost: (***)
Assumes Grantor is on floor 5 and Grantee is on floor 2. Assumes 1380 LF of new
riser to be built by Grantor and average of 690 LF total distance from Grantor
OSX to Grantee FTP.
General Comments on Lateral Segments:
1. The estimated costs above are for the following items as noted in respective
sections; Single Laterals, Diverse Laterals, Building Risers, Building
Distribution, Fiber Installation, POP Splicing, Miscellaneous Items. Items
not listed above have not been costed.
2. Unless otherwise noted, costs do not include any costs associated with
leasing backbone duct or fiber leased or sold in the backbone.
3. If provided, costs for racks, power and alarms do not include the cost of
any electronics.
4. Building laterals have been estimated to the closest point(s) on the local
loop backbone. Creation of logical loops or fiber rings has not been
considered.
5. These costs assume the shortest; most direct route from the current or
planned backbone at this time. Changes in lateral distances due to
subsequent and necessary backbone or lateral reroutes for any reason have
not been factored.
6. These costs assume there are no moratoriums, extraordinary restrictions,
route changes, franchise requirements or out of the ordinary construction
conditions. Any of these factors will impact costs. It is also assumed there
will be no right-of-way restrictions or associated costs.
7. Building access will need to be gained to validate estimated costs.
PAGE5
NOTE: Redacted portions have been marked with (***). The redacted portions are
subject to a request for confidential treatment that has been filed with the
Securities and Exchange Commission.
Exhibit "C"
Metropolitan (Local Loop) Network Construction Specifications
-------------------------------------------------------------
The intent of this Exhibit is to delineate the general specifications and
standards for construction of the Grantor System within the metropolitan
networks. In the event any federal, state, local or private agency having
jurisdiction shall impose higher standards, Grantor will comply and conform to
such higher standards. Grantor may deviate from the specifications and standards
described below in those instances where either (i) strict compliance is
impractical due to physical (including environmental) conditions, right-of-way
issues or code restrictions, or (ii) Grantor has acquired a portion of the
Grantor System from a third party.
1. Minimum Depths
------------------
. Minimum cover required in the placement of conduit shall be 42 inches, except
in the following instances:
. The minimum cover in borrow ditches adjacent to roads, highways,
railroads, and interstate shall be 48 inches below the clean-out line
or existing grade, whichever is greater.
. The minimum cover across streams, river washes and other waterways
shall be 48 inches below the clean-out line or existing grade,
whichever is greater.
. Where conduit crosses railroads, the conduit shall be placed at a
minimum depth of 60 inches below the base of rail or below the
paralleling drainage ditch, whichever is greater.
. At locations where conduit crosses other subsurface utilities or
other structures, the conduit shall be installed to provide a minimum
of 12 inches of vertical clearance under the foreign object while
maintaining a minimum cover of 42 inches.
. In rock, the conduit shall be placed either: (a) 8 inches deep in
rock with 36 inches minimum cover; (b) 8 inches deep in rock with a
concrete cap and 30 inches minimum cover; (c) 8 inches deep in rock
with a 1/4 inch steel plate cover and 24 inches minimum cover or (d)
in steel pipe placed on top of the rock with 18 inches minimum cover,
whichever requires the least rock excavation. HDPE conduit will be
back-filled with 2 inches of select materials (bedding) and 4 inches
of select cover in rock areas.
. In the case of the use/conversion of conduit systems purchased or
leased from third parties or salvaged conduit systems, the existing
depths shall be considered adequate.
2. Cable Marking Tape
----------------------
. Cable marking tape shall be installed above all direct buried conduit,
generally at a minimum of 12 inches below top of rough grade. Conduit
installed by means other than direct burial as well as salvaged conduit
systems or conduit systems purchased from third parties will not have cable
marking tape installed.
PAGE6
NOTE: Redacted portions have been marked with (***). The redacted portions are
subject to a request for confidential treatment that has been filed with the
Securities and Exchange Commission.
3. Conduit Construction
------------------------
. Conduits may be placed by means of trenching, plowing, xxxx and bore, or
directional bore. Conduit will generally be placed on a level grade parallel
to the surface, with only gradual changes in grade elevation.
. Steel conduit will be joined with threaded collars, welding or other industry
accepted methods.
. Railroad crossings will be encased in HDPE or steel conduit.
. All underground crossings of navigable waterways will be placed in either
HDPE or steel conduit at a minimum depth of 20 feet below the bottom of the
waterway.
. All conduits placed on DOT bridges will be bulletproof fiberglass or
galvanized steel.
. All conduits placed on bridges shall have expansion joints placed at each
structural (bridge) expansion joint or at least every 100 feet, whichever is
the shorter distance.
4. Cable Installation
----------------------
. The maximum pulling force to be applied to the fiber optic cable shall be 600
pounds.
. A pulling swivel breakaway rated at 600 pounds shall be used at all times
when pulling fiber optic cable.
. Bends of small radii (less then 20 times the outside diameter of the cable)
and twists that may damage the cable shall be avoided during cable placement.
. The cable shall be lubricated and placed in accordance with the cable
manufacturer specifications.
. All splices will be contained in a cable vault or hand hole.
. A minimum of 60 feet of slack cable will be left in all intermediate cable
vaults or hand holes.
. A minimum of 50 feet of slack cable from each cable end (100 feet total) will
be left in all splice locations.
5. Cable Vaults and Hand Holes
-------------------------------
. Cable vaults will be placed as required by local conditions and at
approximately every 3000 feet in rural areas and 500 feet in urban areas.
. Cable vaults and hand holes placed in traveled surface streets shall be a
minimum HS-20 loading rated.
. Cable vaults and hand holes not installed in traveled surface streets shall
be a minimum HS-10 loading rated.
6. Proofing of Conduits
------------------------
. Upon completion of conduit installed, conduit shall be proofed to verify
continuity and integrity of the conduit system.
. Proofing shall be accomplished by pulling or blowing a mandrel. The outside
diameter of the mandrel or pig shall be a minimum of 80 percent of the inside
diameter of the conduit.
PAGE7
NOTE: Redacted portions have been marked with (***). The redacted portions are
subject to a request for confidential treatment that has been filed with the
Securities and Exchange Commission.
7. Compliance
--------------
. All work will be done in accordance with federal, state, local and applicable
private rules and laws regarding safety and environmental issues, including
those set forth by OSHA and the EPA. In addition, all work and the resulting
fiber system will comply with the current requirements of all governing
entities (FCC, NEC, DEC, and other national, state, and local codes).
8. As-Built Drawings
---------------------
. As-built drawings for conduit sales will contain a minimum of the following:
. Information showing the location of running line, relative to
permanent landmarks.
. Cable vault and hand hole locations.
. Conduit information (type, length, etc.).
. Notation of all deviations from specifications (depth, etc.).
. ROW detail (type, centerline distances, boundaries, waterways, road
crossings, known utilities and obstacles).
. Fiber optic cable data (type, manufacturer, reel IDs, sequentials,
slack coils, splice points, etc.).
. Drawings will be updated with actual field data during and after
construction.
. Metro area scale shall not exceed 1 inch = 200 feet.
. Rural area scale shall not exceed 1 inch = 500 feet.
. All deviations from specification (depth, etc.).
. As-built drawings will be provided within 90 days after the
Acceptance Date in electronic format.
. As-built drawings for fiber sales will contain a minimum of the following:
. Maps depicting which streets the Grantee fiber route travels.
. Grantee logical loop configurations and fiber assignments per loop.
. Fiber assignments to all buildings Grantor provides connectivity for
Grantee.
. As-built drawings will be provided within 90 days after the
Acceptance Date in electronic format.
PAGE8
NOTE: Redacted portions have been marked with (***). The redacted portions are
subject to a request for confidential treatment that has been filed with the
Securities and Exchange Commission.
Exhibit "D"
-----------
Fiber and Conduit Specifications
--------------------------------
The intent of this Exhibit is to delineate the specifications for the Grantee
Fibers and the conduit housing the Cable. Deviations from these specifications
may occur if Grantor acquires a portion of the Grantor System from a third party
pursuant to the Agreement.
Fiber
-----
In the metropolitan segments, single mode fiber will be used. In any case where
the routes for Grantor's long-haul and metropolitan networks converge, Grantor
shall have the right to elect to install either non-zero dispersion-shifted
optical fiber or single mode fiber. Grantor may substitute alternative fibers
if and only if such alternative fibers have performance specifications which are
at least equal to the specifications set forth below.
Non-Zero Dispersion -Shifted Optical Fiber
------------------------------------------
. Attenuation at 1550 nm = 0.25 dB/km max
. Attenuation at 1625 nm = 0.25 dB/km max
. Total Dispersion = 2.0 - 6.0 ps/nm-km for 1530 nm to 1565nm
4.5 - 11.2 ps/nm-km for 1565nm to 1625nm
. Effective Area (Aeff) = 72 /\m2, typical
. Polarization Mode Dispersion = 0.20 ps max per fiber, typical 0.08 ps link
value
. Mode Field Diameter = 9.20 to 10.00 m at 1550 nm
. Cladding Diameter = 125.0 +- 1.0 m
. Core/Clad Concentricity less than = 0.5 m
Single Mode Fiber
-----------------
. Attenuation at 1310 nm = 0.40 dB/km max
. Attenuation at 1550 nm = 0.30 dB/km max
. Zero Dispersion wavelength = 1312nm typical
. Wavelength cutoff less than 1260nm typical
. Dispersion slope = less than .0902ps typical
. Polarization Mode dispersion = 0.20 ps max per fiber, 0.10 ps link value
. Mode Field Diameter = 9.2+- 0.4 m at 1310 nm & 10.4 +-0.8 at 1550 nm
. Cladding Diameter = 125.0 +- 1.0 m
. Core/Clad Concentricity less than =0.5 m
Conduit
-------
. OSP Conduit SDR 11
. 1-1/4" (inside diameter)
. High density polyethylene (HDPE) duct
. Tensile yield 3200 psi
. Flexural modulus 110,000 psi
. Smoothwall inside & outer
. Empty (no rope or tape)
. Unlubricated
PAGE9
NOTE: Redacted portions have been marked with (***). The redacted portions are
subject to a request for confidential treatment that has been filed with the
Securities and Exchange Commission.
Exhibit "E"
METROPOLITAN (LOCAL LOOP) NETWORK FIBER ACCEPTANCE TESTING PROCEDURES
----------------------------------------------------------------------
AND STANDARDS
-------------
The intent of this Exhibit is to identify the fiber acceptances testing
procedures and standards used within the Grantor's metropolitan networks.
Deviations from these specifications may occur if Grantor acquires a portion of
the Grantor System from a third party pursuant to the Agreement.
1. All splices shall be fusion spliced. Mechanical splices are only allowed
during temporary restoration and will be replaced with fusion splices.
2. Fibers shall be terminated with Ultra SC-PC connectors (typical return loss
of 0.50 dB).
3. After end-to-end connectivity on the fibers has been completed, bi-
directional OTDR span and power meter testing will be completed. Grantor
shall perform tests after the fiber cable is installed and the splicing
enclosures have been completed and are in their final resting configuration
with the cable vault or hand hole covers closed. This ensures that no micro
or macro bending problems with the cable or fiber strands will contribute to
the loss/attenuation measurements.
4. Power meter tests shall be completed to verify and insure that no fibers have
been crossed at any of the splice points within the network. Grantor shall
test and record power level readings on all fiber strands in both directions
of transmission (bi-directionally) using the 1310 & 1550 nm wavelengths.
5. All OTDR and power meter tests shall be completed as follows:
a. All OTDR traces shall be taken from both ends of a section (between
adjacent Locations) and recorded using the 1310 & 1550 nm wavelength.
Loss/attenuation measurements for each splice point from both directions
shall be taken and recorded.
b. The end-to-end loss value as measured with an industry-accepted laser
source and power meter should have an attenuation rating of less than or
equal to the following:
(1) At 1310 nm: (0.40 dB/km x km of cable) + (number of connectors x
0.50) + (0.10 x number of splices).
(2) At 1550 nm: (0.30 dB/km x km of cable) + (number of connectors x
0.50) + (0.10 x number of splices).
c. Grantor's loss/attenuation objective for each fiber optic splice is 0.10
dB when measured in one direction with an OTDR test set (excluding
connector loss, which is typically 0.50 dB per mated connector pair). If
after three attempts this parameter is not met, the splice will be marked
as Out-Of-Spec (OOS) and the splice will remain provided the average
loss/attenuation value of all splices on an individual fiber basis shall
not exceed 0.10 dB for the entire ring or subsystem.
d. For bi-directional OTDR testing, the distance from Location "A" and
Location "Z" shall be recorded for each splice point. The loss/attenuation
at each splice point shall be recorded at both wavelengths (1310 nm & 1550
nm) in each direction. Grantor shall then average the two readings to
obtain the final average splice loss/attenuation for each splice point of
each fiber strand within the fiber optic cable.
e. Each fiber strand color must be recorded along with its buffer tube color
or the ribbon color. The laser source transmit power level using the 1310
& 1550 nm wavelengths will always be recorded together with the receive
power level reading at the receiving end of the test.
PAGE10
NOTE: Redacted portions have been marked with (***). The redacted portions are
subject to a request for confidential treatment that has been filed with the
Securities and Exchange Commission.
6. OTDR traces will be taken and splice loss measurements recorded. Grantor
will store OTDR traces on electronic media. Loss measurements will be
recorded using an industry-accepted laser source and a power meter. Copies
of all data sheets and tables and one set of diskettes with all traces will
be available to Grantee.
7. Following emergency restoral, Grantor personnel shall perform span test
documenting end-to-end attenuation measurement of each fiber and will be
completed in both directions at 1310 & 1550 nm wavelengths. Upon permanent
repair, new splice loss readings should be no greater than the original
splice loss specifications.