AGREEMENT MN River Water Supply Facility Granite Falls Energy, LLC Granite Falls, MN
EXHIBIT 10.19
AGREEMENT
MN River Water Supply Facility
Granite Falls Energy, LLC
Granite Falls, MN
Granite Falls, MN
THIS AGREEMENT is dated as of the 16th day of August in the year 2006 by
and between Granite Falls Energy, LLC (hereinafter called OWNER) and Rice Lake Construction
Group (hereinafter called CONTRACTOR).
OWNER and CONTRACTOR, in consideration of the mutual covenants hereinafter set forth, agree as
follows:
ARTICLE 1. WORK.
CONTRACTOR shall complete all Work as specified or indicated in the Contract Documents. The Work is
generally described as follows:
A. | Construction of pumping station and building and associated work. | ||
B. | Construction of river intake structure. | ||
C. | Construction of piping from pumping station to river intake structure. | ||
D. | Installation of pumps, piping, electrical, controls and associated equipment and work for the pumping station. |
ARTICLE 2. ENGINEER.
The Project has been designed by Xxxxxx & Xxxx, Inc., Consulting Engineers, 0000 Xxxxxxx Xxxxx,
Xxxxxxx, XX 00000, who is hereinafter called ENGINEER and who is to act as OWNER’S representative,
assume all duties and responsibilities and have the rights and authority assigned to ENGINEER in
the Contract Documents in connection with completion of the Work in accordance with the Contract
Documents.
ARTICLE 3. CONTRACT TIME.
3.1. The project will be operational by December 31, 2006. Final restoration work will be completed
by May 2007.
ARTICLE 4. CONTRACT PRICE.
4.1. OWNER shall pay CONTRACTOR for completion of the Work in accordance with the Contract
Documents in current funds as follows:
Lump Sum of $2,133,000.00 (Two million one hundred thirty-three thousand and no/100 DOLLARS) | |||
(With Bid Schedule Attachment) |
M21.38035 — Granite Falls Energy, LLC |
AGREEMENT | |||
MN River Water Supply Facility-Granite Falls, MN |
PAGE 1 |
ARTICLE 5. PAYMENT PROCEDURES.
CONTRACTOR shall submit Applications for Payment on a monthly basis for the work completed.
Applications for Payment will be processed by ENGINEER to the OWNER. The OWNER shall pay the
approved application within 30 days of receipt. The OWNER shall pay up to 95 percent of the
contract amount. The remaining 5 percent shall be paid upon final approval of the project by the
ENGINEER and OWNER.
ARTICLE 6. CONTRACTOR’S REPRESENTATIONS.
In order to induce OWNER to enter into this Agreement, CONTRACTOR makes the following
representations:
6.1. CONTRACTOR has familiarized itself with the nature and extent of the Contract Documents, Work,
site, locality, and all local conditions and Laws and Regulations that in any manner may affect
cost, progress, performance or furnishing of the Work.
6.2. CONTRACTOR has studied carefully all reports of explorations and tests of subsurface
conditions and drawings of physical conditions.
6.3. CONTRACTOR has reviewed and checked all information and data shown or indicated on the
Contract Documents with respect to existing Underground Facilities at or contiguous to the site and
assumes responsibility for the accurate location of said Underground Facilities.
6.4. CONTRACTOR has correlated the results of all such observations, examinations, investigations,
explorations, tests, reports and studies with the terms and conditions of the Contract Documents.
ARTICLE 7. ADDITIONAL WORK POLICY
7.1 All additional work shall be approved by the OWNER prior to performing the work.
IN WITNESS WHEREOF, OWNER and CONTRACTOR have signed this Agreement in triplicate. One counterpart
each has been delivered to OWNER, CONTRACTOR and ENGINEER. All portions of the Contract Documents
have been signed or identified by OWNER and CONTRACTOR or identified by ENGINEER on their behalf.
This Agreement will be effective on August 16, 2006 (which is the Effective Date of the
Agreement).
OWNER: Granite Falls Energy, LLC | CONTRACTOR: Rice Lake Construction Group | |||||||||
By: |
/s/ Xxxx Xxxxxxxxx | By: | /s/ Xxxx Xxxxxxx | |||||||
Project Manager GLE | Xxxx Xxxxxxx |
M21.38035 — Granite Falls Energy, LLC |
AGREEMENT | |||
MN River Water Supply Facility-Granite Falls, MN |
PAGE 2 |
Rice Lake Construction Group — Pumping Station and River Intake Work
Item | ||||||||||||||||
No. | Item | Est. Qty. | Unit | Unit Price | Amount | |||||||||||
1
|
Mobilization | 1 | LS | 76,000.00 | $ | 76,000.00 | ||||||||||
2
|
Raw Water Intake Screen | 1 | LS | 28,000.00 | 28,000.00 | |||||||||||
3
|
Pumping Station Wet Well Structure | 1 | LS | 814,000.00 | 814,000.00 | |||||||||||
4
|
Electrical/Control/Standby Generator | 1 | LS | 238,000.00 | 138,000.00 | |||||||||||
5
|
Raw Water Connecting Piping from Intake Screen to Pumping Structure | 1 | LS | 710,000.00 | 710,000.00 | |||||||||||
0
|
Xxxxxxx Xxxxxxx Xxxxxxxx | 0 | LS | 154,000.00 | 154,000.00 | |||||||||||
7
|
Equipment (i.e. pumps, air compressors, etc.) | 1 | LS | 121,000.00 | 121,000.00 | |||||||||||
8
|
Process Piping, Valves, Meters, etc. | 1 | LS | 92,000.00 | 92,000.00 | |||||||||||
TOTAL BID | $ | 2,133,000.00 |