COLLABORATION AGREEMENT
COLLABORATION AGREEMENT
This Agreement is made between Phoenix Plus International Limited, a wholly owned subsidiary of Phoenix Plus Corp (hereafter referred as “PPIL”), a private Limited company incorporated in Hong Kong and WWB Corporation, a subsidiary of Abalance Corporation listed in Tokyo Stock Exchange (hereafter referred as “WWB”), a company based in Tokyo Japan, on 2 October 2019 to market and perform certain complementary business activities, particularly the solar farm project in East Coast Sabah (“Project”). The estimated Project revenue, cost and time are stipulated under Appendix 1.
1.0 | INFORMATION ON PPIL and WWB |
PPIL, principally involved in providing technical consultancy on solar power systems and consultancy on green energy solutions, with an additional focus on the commercialization of a targeted portfolio of solar products (amorphous thin film solar panels and ancillary products) and technologies for a wide range of application including electrical power production.
WWB, principally involved in the providing solar power generation and also engaged in planning, manufacturing, import and export and sale of next-generation green energy products and construction of solar panel.
PPIL and WWB shall, hereinafter be collectively referred to as the “Parties” or individually as the “Party” as the case may be.
2.0 | SALIENT TERMS OF THE AGREEMENT |
a) | Scope |
The Parties shall, in professional manner, take all steps necessary to market and perform its business activities respectively and to expand renewable energy business.
PPIL shall providing installation services and solutions for the development of solar panel in Sabah, Malaysia and WWB will providing solar energy product such as solar panels, solar inverters, solar pumps, mounting frames, trackers, accessories and others and also transferring of solar energy technology from Japan to develop sustainable renewable energy ecosystem for the project.
The Parties will collaborate to execute the solar farm project in East Coast, Sabah, in the event PPIL successful in the tender exercise of the aforesaid project.
b) | Duration |
The Agreement shall be effective as of the date set forth in this Agreement and renewed automatically every year.
c) | Termination |
In the event PPIL is successful in the tender exercise for the project, either party that wishes to terminate the agreement, shall give one (1) month notice in advance to the other party. Any unfinished projects that are awarded before such termination are deemed to be completed fully by the other party.
d) | Intellectual Property |
Information, materials, products and deliverables developed by either Party shall be the property of the respective Parties performing the work or creating the information.
3.0 | RATIONALE FOR THE AGREEMENT |
The objective of the Agreement is to tap into the know-how and technological advancement of WWB in the area of solar technologies to further enhance PPIL expertise in the solar business. With the technological know-how from WWB. PPIL is looking at building our future solar plant with greater efficiency at an optimum construction cost.
4.0 | ESTIMATED TIMEFRAME AND COMPLETION |
The agreement shall take effect as at the date of the agreement and renewed automatically every year. Either party can terminate this agreement by giving one-month notice in advance to the other party.
This Agreement is governed by Hong Kong law and the parties irrevocably submit to the exclusive jurisdiction of the Hong Kong courts to settle any dispute arising out of or in connection with this Agreement.
Authorized Signatories:-
/s/ Xxxx Tech Xxxxxx
Xxxx Tech Kheong
Director
Phoenix Plus International Limited
/s/ Ryu Junsei
Ryu Junsei
Chairman
WWB Corporation
Phoenix Plus International Limited and WWB Corporation | Appendix 1 | |||
Solar Farm Project in Sabah: Overview | ||||
Expected Xxxxxxxx | 00 Xxxxxxxx (Xx) | |||
Project term | 20 years | |||
Expected construction period | 3 years | |||
Land | 25 years lease land | |||
Land Size | 150 acres (Sandakan, Sabah) | |||
Expected cost ( Note 1) | USD 45 million | |||
Expected Revenue | USD 6 million per year | |||
Expecting Breakeven | 8 years | |||
Expected Total Revenue in 20 years | USD 120 million | |||
Note 1:Cost Breakdown
Particulars | Amount (in USD) | Percentage |
Solar Panel | 20.25 million | 45% |
Main Equipment | 4.5 million | 10% |
Balance System | 4.5 million | 10% |
Infrastructure | 6.75 million | 15% |
Interconnection | 4.5 million | 10% |
Miscellaneous & Staff Costs* | 4.5 million | 10% |
Total | USD 45 million | 100% |
*Estimated a workforce of 200-250 labors are required for the installation of the project.