SCHEDULE OF AGREEMENTS SUBSTANTIALLY IDENTICAL IN ALL MATERIAL RESPECTS TO THE F-3, PURSUANT TO INSTRUCTION 2 TO ITEM 601 OF REGULATION S-K
Exhibit 10.2
SCHEDULE OF AGREEMENTS
SUBSTANTIALLY IDENTICAL IN ALL MATERIAL RESPECTS TO THE
AGREEMENT FILED AS EXHIBIT 10.1 TO THIS REGISTRATION STATEMENT ON FORM
F-3, PURSUANT TO INSTRUCTION 2 TO ITEM 601 OF REGULATION S-K
The subsidiaries of Teekay LNG Operating LLC listed in the table below have entered into Shipbuilding Contracts, each dated July [•], 2014, with Daewoo Shipbuilding & Marine Engineering Co., Ltd. and DY Tankers Limited. These agreements are substantially identical in all material respects to the agreement filed as Exhibit 10.1 to this Registration Statement on Form F-3, except for differences relating to the identity of the buyer, the hull number of the vessel that is the subject of each such contract and various dates for performance under each agreement.
Buyer |
Hull No. |
Second Instalment Date |
Third Instalment Date |
Fourth Instalment Date |
Target Milestone Dates |
Initial Acceptance Date |
Final Delivery Date | |||||||
DSME Hull No. 2431 L.L.C. | 2431 | 31 October 2017 | 30 April 2018 | 31 August 2018 | Steel-cutting:12 December 2017 |
31 August 2019 | 29 November 2019 | |||||||
Keel laying:11 June 2018 |
||||||||||||||
Launching: 22 September 2018 |
||||||||||||||
Cargo containment system installation: 15 June 2019 |
||||||||||||||
DSME Hull No. 2430 L.L.C. | 2430 | 30 September 2017 | 31 March 2018 | 28 July 2018 | Steel- cutting: 03 November 2017 |
31 July 2019 | 29 October 2019 | |||||||
Keel laying: 30 April 2018 |
||||||||||||||
Launching: 28 July 2018 |
||||||||||||||
Cargo containment system installation: 15 May 2019 |
||||||||||||||
DSME Hull No. 2425 L.L.C. | 2425 | 31 October 2016 |
30 April 2017 | 31 August 2017 | Steel- cutting: 28 December 2016 |
31 August 2018 |
29 November 2018 |
Keel laying: 26 June 2017 |
||||||||||||||
Launching: 23 September 2017 |
||||||||||||||
Cargo containment system installation: 15 June 2018 |
||||||||||||||
DSME Hull No. 2433 L.L.C. | 2433 | 31 December 2017 | 30 June 2018 |
31 October 2018 |
Steel- cutting: 23 March 2018 |
31 October 2019 |
29 January 2020 | |||||||
Keel laying: 24 September 2018 |
||||||||||||||
Launching: 22 December 2018 |
||||||||||||||
Cargo containment system installation: 16 August 2019 |
||||||||||||||
DSME Hull No. 2434 L.L.C. | 2434 | 31 January 2018 | 30 July 2018 | 30 November 2018 |
Steel- cutting:09 May 2018 |
30 November 2019 |
28 February 2020 | |||||||
Keel laying:12 November 2018 |
||||||||||||||
Launching: 09 February 2019 |
||||||||||||||
Cargo containment system installation: 16 September 2019 |
- 2 -