EXHIBIT 10.11
EXECUTION COPY
--------------
COGENERATION FACILITY
OPERATION AND MAINTENANCE AGREEMENT
DATED AS OF NOVEMBER 1, 1998
BETWEEN
PROJECT ORANGE ASSOCIATES, L.P.
AND
GE ENERGY PLANT OPERATIONS, INC.
TABLE OF CONTENTS
Article I
Definitions..................................................................... 1
Article II
Engagement of GE and Description of Services.................................... 8
Section 2.01 - Operation and Routine Maintenance of Facility.................. 8
Section 2.02 - Certain Requirements Applicable to the Operation and
Maintenance of the Existing Facility and the Site................... 9
Section 2.03 - Certain Requirements Applicable to the Operation and
Maintenance of the Pipeline and Right of Way........................ 10
Section 2.04 - Repair and Overhaul of the Gas Turbine Packages................ 11
Section 2.05 - Liens.......................................................... 12
Section 2.06 - Personnel Standards............................................ 12
Section 2.07 - GE Plant Manager............................................... 12
Section 2.08 - Training....................................................... 12
Section 2.09 - Preventive Maintenance Program................................. 12
Section 2.10 - Inventory System............................................... 13
Section 2.11 - Operation and Maintenance Procedures........................... 13
Section 2.12 - Administrative Procedures Manuals.............................. 13
Section 2.13 - Warranty and Insurance Claims.................................. 13
Section 2.14 - Procurement and Inventories.................................... 13
Section 2.15 - Coordination with Electric Utility, ISO and Steam User......... 14
Section 2.16 - Emergency...................................................... 15
Section 2.17 - Claims and Litigation.......................................... 15
Section 2.18 - Permits and Other Governmental Approvals....................... 15
Section 2.19 - Recalibrations................................................. 15
i
TABLE OF CONTENTS
Section 2.20 - Major System Repairs and Insured Losses........................ 15
Section 2.21 - Review and Administration of Agreements........................ 16
Section 2.22 - Inspections.................................................... 16
Section 2.23 - Hazardous Substances........................................... 16
Section 2.24 - Other.......................................................... 16
Section 2.25 - Limitation on GE's Authority................................... 16
Section 2.26 - Affiliate Matters.............................................. 17
Section 2.27 - No Disruption of Steam User's Operations....................... 17
Section 2.28 - Site Access.................................................... 17
Section 2.29 - Liability for Payments......................................... 17
Section 2.30 - Alteration of Facility......................................... 17
Article III
POA Obligations................................................................. 18
Section 3.01 - General........................................................ 18
Section 3.02 - Information.................................................... 18
Section 3.03 - Sale of Electricity and Cogeneration Services.................. 18
Section 3.04 - POA Representative............................................. 18
Section 3.05 - Fuels and Utilities............................................ 18
Section 3.06 - Procurement.................................................... 18
Section 3.07 - Annual Management Audit........................................ 18
Section 3.08 - Leased Engine Program.......................................... 19
Section 3.09 - Liens.......................................................... 19
Section 3.10 - Access......................................................... 19
Section 3.11 - General, Office and Maintenance Facilities..................... 19
ii
TABLE OF CONTENTS
Section 3.12 - Spare Parts.................................................... 19
Article IV
Budgets, Procedures, Plans and Reporting........................................ 19
Section 4.01 - POA Administrative Procedures Manual........................... 19
Section 4.02 - POA Operation and Maintenance Procedures Manual................ 20
Section 4.03 - Training Plan.................................................. 20
Section 4.04 - Annual Budget and Operating Plan............................... 20
Section 4.05 - Accounts and Reports........................................... 21
Section 4.06 - Changes to Annual Budget and Annual Operating Plan............. 23
Article V
Compensation and Payment........................................................ 24
Section 5.01 - Payments to GE................................................. 24
Section 5.02 - Reimbursable Expenses.......................................... 25
Section 5.03 - Payroll Cost................................................... 25
Section 5.04 - Training Expenses.............................................. 25
Section 5.05 - Relocation Expenses............................................ 25
Section 5.06 - Subcontractor Expenses......................................... 26
Section 5.07 - Taxes.......................................................... 26
Section 5.08 - Handling Fee................................................... 26
Section 5.09 - Costs for Consumables and Parts and Tools...................... 26
Section 5.10 - Fired-Hour Fee................................................. 27
Section 5.11 - Spare Parts Fee................................................ 27
Section 5.12 - Operating Fee.................................................. 27
Section 5.13 - Interest....................................................... 27
iii
TABLE OF CONTENTS
Section 5.14 - Accounting and Audit Rights.................................... 27
Section 5.15 - Disputed Payments.............................................. 28
Section 5.16 - Escalation..................................................... 28
Article IV
Term ........................................................................... 29
Section 6.01 - Term........................................................... 29
Section 6.02 - Renewal....................................................... 29
Section 6.03 - Facility Condition at End of Term.............................. 29
Section 6.04 - Liabilities Accrued as of the End of Term...................... 30
Article VII
Events of Default and Termination............................................... 30
Section 7.01 - GE Events and Default.......................................... 30
Section 7.02 - POA Events of Default......................................... 32
Section 7.03 - Notice of Termination.......................................... 33
Section 7.04 - Force Majeure.................................................. 33
Section 7.05 - Repair and Overhaul Obligations after Termination.............. 34
Article VIII
Insurance....................................................................... 34
Section 8.01 - Coordination of Insurance...................................... 34
Section 8.02 - Certificates; Proof of Loss................................... 34
Section 8.03 - No Limitation on Liability..................................... 34
Article IX
Indemnification................................................................. 34
Section 9.01 - By GE.......................................................... 34
Section 9.02 - By POA......................................................... 35
iv
TABLE OF CONTENTS
Article X
Liabilities of the Parties...................................................... 35
Section 10.01 - No Consequential Damages...................................... 35
Section 10.02 - Limitation of Liabilities..................................... 36
Article XI
Dispute Resolution.............................................................. 36
Section 11.01 - Arbitration................................................... 36
Section 11.02 - Demand for Arbitration....................................... 36
Section 11.03 - Qualifications................................................ 36
Section 11.04 - Decisions Final............................................... 36
Section 11.05 - Compensation of Arbitrator.................................... 36
Section 11.06 - Performance to Continue....................................... 36
Section 11.07 - Agreement Controlling......................................... 36
Article XII
Confidentiality................................................................. 37
Section 12.01 - Nondisclosure................................................. 37
Section 12.02 - Permitted Disclosure......................................... 37
Section 12.03 - Term.......................................................... 37
Article XIII
Title, Documents and Data....................................................... 37
Section 13.01 - Materials and Equipment....................................... 37
Section 13.02 - Documents.................................................... 37
Section 13.03 - Proprietary Information....................................... 38
Article XIV
Miscellaneous Provisions........................................................ 38
Section 14.01 - Assignment.................................................... 38
v
TABLE OF CONTENTS
Section 14.02 - Cooperation in Financing...................................... 38
Section 14.03 - Access........................................................ 38
Section 14.04 - Independent Contractor........................................ 39
Section 14.05 - Not for Benefit of Third Parties.............................. 39
Section 14.06 - Force Majeure................................................. 39
Section 14.07 - Amendments................................................... 39
Section 14.08 - Survival...................................................... 39
Section 14.09 - No Waiver..................................................... 40
Section 14.10 - Notices....................................................... 40
Section 14.11 - Representations and Warranties................................ 41
Section 14.12 - Counterparts.................................................. 42
Section 14.13 - Governing Laws................................................ 42
Section 14.14 - Partial Invalidity........................................... 42
Section 14.15 - Captions, Exhibits and the Table of Contents.................. 42
Section 14.16 - Entire Agreement.............................................. 42
Section 14.17 - Conflicting Provisions....................................... 42
Section 14.18 - Successors and Assigns........................................ 42
Section 14.19 - Opinion of Counsel............................................ 42
Section 14.20 - Performance During Legal Proceedings.......................... 42
Section 14.21 - Joint Effort................................................. 42
Section 14.22 - Disclaimer of Warranties...................................... 42
Section 14.23 - Standard of Reasonableness.................................... 43
vi
TABLE OF CONTENTS
Article XV
Maintenance of Inventory of Consumables and Parts and Tools..................... 43
Section 15.01 - Maintenance of Inventory of Consumables and
Parts and Tools........................................................ 43
Exhibit A-1 - Minimum Repair and Maintenance Requirements for the Existing Plant
Exhibit A-2 - Minimum Operating Requirements for the Existing Plant
Exhibit B - Minimum Pipeline Maintenance Requirements
Exhibit C - Organization Chart
Exhibit D - Budget for First Operating Year
Exhibit E - Insurance
Exhibit F - Gas Turbine Package Diagram
Exhibit G - LM5000 Lease Engine Program
Exhibit H - Maintenance Schedule
Schedule 1 - Initial Inventory of Spare Parts
Schedule 2 - Proprietary Documents
Schedule 3 - Approved Contractors
Schedule 4 - Termination Fee
vii
COGENERATION FACILITY
OPERATION AND MAINTENANCE AGREEMENT
This COGENERATION FACILITY OPERATION AND MAINTENANCE AGREEMENT (the "Agreement")
is made and entered into as of November 1, 1998, by and between PROJECT ORANGE
ASSOCIATES, L.P., a Delaware limited partnership ("POA"), and GE Energy Plant
Operations, Inc., a Delaware corporation ("GE", and together with POA, each a
"Party" and collectively the "Parties").
RECITALS
WHEREAS, POA owns a cogeneration facility in Syracuse, New York;
WHEREAS, POA and Xxxxxxx & Xxxxxxxxx Operations, Inc., a Delaware corporation
"SSOI", entered into an 80MW Facility Operation and Maintenance Agreement, dated
as of April 5, 1991 (the "Prior Agreement"), under which GE, as SSOI's assignee,
operated, maintained and repaired POA's cogeneration facility prior to November
1, 1998;
WHEREAS, in connection with the acquisition by General Electric Company of the
gas turbine division of Xxxxxxx & Xxxxxxxxx Services, Inc., SSOI assigned the
Prior Agreement to GE and GE assumed the obligations of SSOI thereunder;
WHEREAS, POA and GE have terminated the Prior Agreement, effective as of the
Commencement Date, as defined herein;
WHEREAS, POA desires to engage GE to continue to operate, maintain and repair
POA's cogeneration facility on and after the Commencement Date on the terms and
conditions set forth herein; and
WHEREAS, GE desires to so continue to operate, maintain and repair POA's
cogeneration facility on the terms and conditions set forth herein;
NOW, THEREFORE, in consideration of the premises and the mutual covenants
contained herein, and other good and valuable consideration, the receipt and
sufficiency of which are hereby acknowledged, the Parties, intending to be
legally bound, agree as follows:
ARTICLE I - DEFINITIONS
As used herein, the following terms shall have the indicated definitions:
"Additional Starts" shall have the meaning assigned to such term in Section
-----------------
5.10.
"Affiliate" shall mean, when used with reference to a specified Person, any
---------
other Person which directly or indirectly controls or is controlled by or is
under common control with the specified Person. For purposes of the foregoing,
"control", "controlled by" and "under common control" shall mean the
possession, directly or indirectly, of the power to direct or cause the
direction of
the management and policies of such Person, whether through the ownership of
voting securities or by contract or otherwise.
"Annual Budget" shall have the meaning assigned to such term in Section 4.04
-------------
"Annual Operating Plan" shall have the meaning assigned to such term in Section
---------------------
4.04.
"Change" shall have the meaning assigned to such term in Section 4.06.
------
"Change in Law" shall mean amendments, modifications or changes in existing
-------------
Legal Requirements, including changes in the enforcement or application of Legal
Requirements, or the enactment of any new Legal Requirement.
"Change Order" shall have the meaning assigned to such term in Section 4.06.
-------------
"Change Order Budget Statement" shall have the meaning assigned to such term in
-----------------------------
Section 4.06.
"Commencement Date" shall mean November 1, 1998.
-----------------
"Constructor" shall mean Century Contractors West, Inc., as the engineering,
-----------
procurement and construction contractor for the Facility pursuant to the Amended
and Restated Cogeneration Facility Turnkey Construction Contract, dated as of
April 5, 1991, as amended.
"Consumables" shall mean lubricants, chemicals, fluids, oils, supplies, filters,
-----------
fittings, connectors, seals, gaskets, hardware, wires and other such materials
(other than Parts and Tools and Spare Parts) needed in the normal course of the
operation, maintenance and repair of the Facility.
"Consumer Price Index" shall mean the Consumer Price Index for All Urban
--------------------
Consumers For All Items, as published in Table 1 in the United States Department
of Labor, Bureau of Labor Statistic's monthly publication, CPI Detailed Report,
and as adjusted after initial publication, if applicable, or if such index is no
longer published or the method of computation thereof is substantially modified,
a mutually agreeable alternative index.
"Default Rate" shall mean a rate per annum equal to the lesser of: (i) the rate
------------
publicly announced by Citibank, N.A. as its prime lending rate plus two percent
(2%) or (ii) the maximum rate that can be charged under applicable law.
"Directed Starts" shall mean all successful starts of each gas turbine, except
---------------
starts which (i) follow outages which are scheduled or planned for maintenance,
repairs or overhauls, or (ii) result from the negligence or willful misconduct
of GE or a failure of GE to perform its obligations hereunder.
"Disapproved Contractor" shall have the meaning assigned to such term in Section
----------------------
2.20(c).
"Electric Utility" shall mean Niagara Mohawk Power Corporation and its
----------------
successors and assignees.
-2-
"Electric Utility Interconnection" shall mean the electrical interconnection
--------------------------------
between the Facility and the Electric Utility's transmission system.
"EM&CP" shall mean the Environmental Management and Construction Plan, as
-----
amended from time to time, contemplated by the Pipeline Order.
"Emergency" shall mean any occurrence that requires, in the reasonable judgment
---------
of POA or GE, as the case may be, immediate action and which (i) constitutes a
serious hazard to the safety of persons or property, or (ii) may materially
interfere with the safe, economical, lawful or environmentally-sound operation
of the Facility.
"Equipment" shall mean the items of machinery, systems, and electrical and
---------
electronic components which comprise the Facility.
"Excess Liabilities" shall have the meaning assigned to such term in Section
------------------
2.01 (d)
"Excess Starts" shall have the meaning assigned to such term in Section 5.10.
-------------
"Existing Plant" shall mean the Steam User's steam generation facility
--------------
consisting principally of four gas and oil fired steam boilers and related
apparatus, equipment and structures, including the gas house, underground oil
storage tanks and the facilities known as the Alto Plant and the Xxxxx Plant and
the land on which it is located at 000 X. Xxxxxx Xxxxxx in the City of Syracuse,
N.Y.
"Facility" shall mean: (i) POA's cogeneration facility for the production of
--------
steam and electric power located in Syracuse, N.Y. consisting of the two (2)
LM5000 gas turbines, process water treatment, related gas pipeline, steam and
electric handling installations and buildings and structures; (ii) all steam,
water and condensate lines, apparatus and equipment necessary or appropriate for
the supply of steam from the cogeneration facility to the Steam User's steam
system: (iii) all fuel lines, gas lines and electric transmission lines within
the Site (excluding all such items owned by any public utility); (iv) any
related apparatus necessary or appropriate for the operation of the cogeneration
facility; (v) the Existing Plant; (vi) the Pipeline; (vii) the Site; and (viii)
the Right-of-Way.
"Facility Agreements" shall mean collectively, as amended from time to time (i)
-------------------
this Agreement; (ii) the PPA and each other agreement that POA enters into for
the sale of electricity; (iii) the Steam Agreement; (iv) the Site Lease; (v) the
Interconnection Agreement; (vi) the Gas Transportation Agreement; (vii) the Gas
Purchase Agreement; and (viii) the Operating Agreement.
"Fired Hour Fee" shall have the meaning assigned to such term in Section 5.10.
--------------
"Force Majeure" shall mean an event or occurrence which is beyond the reasonable
-------------
control of the affected Party including: (i) acts of God; (ii) Changes in Law;
(iii) acts of war (whether or not declared), civil violence or disobedience,
sabotage or insurrection; (iv) floods, hurricanes, monsoons, earthquakes,
lightning, hail or other natural disasters; (v) explosions or fires; (vi)
accidents in transportation; (vii) injunctions or other interference through
action of a court; (viii) strikes, lockouts, walkout or similar labor
disturbance; (ix) a shortage or curtailment of utility service; or (x) the
fault, negligence, gross negligence, or willful misconduct of the other Party or
-3-
a third party not within the reasonable control of the affected Party; provided
however, that an event of Force Majeure shall not include (i) the inability of a
Party to meet its payment obligations, including an inability to obtain
financing for any obligations to be carried out hereunder; (ii) the economic
hardship of a Party or changes in market conditions; (iii) any strike, lockout,
walkout or similar labor disturbance limited to the affected Party's personnel;
(iv) an event or occurrence or the consequences of any event or occurrence which
are caused by or result from the fault, negligence, gross negligence or willful
misconduct of the affected Party or a third party within the reasonable control
of the affected Party; or (v) an event or occurrence or the consequences of any
event or occurrence which the affected Party could have reasonably foreseen and
avoided.
"GE" shall have the meaning assigned to such term in the first paragraph hereof.
--
"GE Event of Default" shall have the meaning assigned to such term in Section
-------------------
7.01
"GE Indemnified Parties" shall have the meaning assigned to such term in Section
----------------------
9.02.
"Gas Purchase Agreement" shall mean the Restated Gas Sale and Purchase
----------------------
Agreement, dated April 18, 1991, by and among POA, Noranda, Inc. and Canadian
Hunter Exploration Ltd., as amended.
"Gas Transportation Agreement" shall mean the Gas Transportation Agreement,
----------------------------
dated as of November 19, 1987, between Tennessee Gas Pipeline Company, a
division of Tennessee, Inc. and Gas Alternative Systems, Inc., as assigned to
POA and amended.
"Gas Turbine Packages" shall mean the two LM5000 gas turbines included in the
--------------------
Facility, together with the respective Brush generators, lube oil system and
equipment, start-up system and equipment, fuel and steam control valves and
systems and all auxiliary systems, equipment and enclosures associated with the
foregoing and designated as being included in the Gas Turbine Packages in
Exhibit F.
"Governmental Person" shall mean any Federal, state, county, municipal or other
-------------------
governmental authority, any political subdivision or any governmental, quasi-
governmental, judicial, public or statutory instrumentality, authority, body or
entity, or other regulatory bureau, authority, body or entity.
"Insured Loss" shall have the meaning assigned to such term in Section 2.04.
------------
"Interconnection Agreement" shall mean the Interconnection Agreement, dated as
-------------------------
of January 13, 1992, by and between POA and Electric Utility, as amended.
"ISO" shall mean the operator of the New York Power Pool or any other power
---
pool, transmission system or wholesale power exchange or market with which POA's
cogeneration facility is interconnected or into which POA sells or delivers
electricity generated by POA's cogeneration facility.
"ISO Rules" shall mean the rules and regulations of, or any agreement or
---------
agreements of POA with, the ISO.
-4-
"Leased Engine Program" shall have the meaning assigned to such term in Exhibit
---------------------
G.
"Legal Requirements" shall mean all laws, ordinances, rules, regulation, permits
------------------
and orders of all Governmental Persons, including the judicial or administrative
interpretation of any such laws, ordinances, rules, regulations, permits and
orders which are applicable to POA, GE, the Operation and Maintenance of the
Facility and/or the Facility.
"Maintenance Schedule" shall have the meaning assigned to such term in Section
--------------------
204(b).
"Major System Repair" shall mean the repair, replacement or overhaul of
------------------
Equipment, the cost of which exceeds $10,000 and is not included in the Annual
Budget. Notwithstanding the foregoing, Major System Repair shall not include (i)
Routine Maintenance (ii) repairs, replacements and overhauls required as a
result of the negligence or willful misconduct of GE or any failure of GE to
perform its obligations under this Agreement, or (iii) repairs, replacements or
overhauls included within the Repair and Overhaul of the Gas Turbine Packages.
"Minimum Electric Output" shall have the meaning assigned to such term in
-----------------------
Section 7.0l(a)(iv).
"On-Peak Capacity Factor" shall have the meaning assigned to such term in
-----------------------
Section 7.0l(a)(iv).
"Off-Peak Capacity Factor" shall have the meaning assigned to such term in
------------------------
Section 7.01 (a)(iv).
"Operate and Maintain the Facility" shall have the meaning assigned to such term
---------------------------------
in Section 2.01(a).
"Operating Agreement" shall mean the Operating Agreement between Steam User and
--------------------
Project Orange Associates, L.P., dated as of February 27, 1990, as amended.
"Operating Fee" shall have the meaning assigned to such term in Section 5.12.
-------------
"Operating Year" shall mean (i) with respect to the first Operating Year, that
--------------
period of time beginning on the Commencement Date and ending on December 31,
1999, (ii) with respect to subsequent Operating Years (other than the last
Operating Year), the calendar year commencing on January 1 and ending December
31, and (iii) with respect to the last Operating Year, that period of time from
January 1 and ending on the date of expiration or termination of this Agreement.
"Parts and Tools" shall mean all of the parts, materials, assemblies,
---------------
components, tools, supplies and equipment (other than Spare Parts) necessary to
Operate and Maintain the Facility and the Equipment as required by this
Agreement.
"Payroll Cost" shall have the meaning assigned to such term in Section 5.03.
------------
"Per-Hour Fee" shall have the meaning assigned to such term in Section 5.10.
------------
"Permits" shall mean all of the permits, licenses, certificates, rights,
-------
approvals and other similar requirements, including those issued by Governmental
Persons, including: (i) with respect to
-5-
GE, necessary to Operate and Maintain the Facility; and (ii) with respect to
POA, to build, own and operate and maintain the Facility and to perform its
obligations hereunder.
"Person" shall mean a natural person, corporation, partnership, limited
------
liability company, trust, Governmental Person or any other legal entity.
"Pipeline" shall mean the pipeline located upon the Right-of-Way and the Site
--------
for the transmission of natural gas from facilities of the Tennessee Gas
Pipeline Division of Tenneco, Inc. ("Tennessee") to the Facility, including the
interconnections to the Tennessee facilities and the Facility and associated
equipment such as odorization equipment, test points and other peripheral
equipment contemplated by the Pipeline Order.
"Pipeline Order" shall mean the opinion and order of the New York Public Service
--------------
Commission No. 89-17, issued June 5, 1989 in Case No. 88-T-082.
"Plant Manager" shall have the meaning assigned to such term in Section 2.07.
-------------
"POA" shall have the meaning assigned to such term in the first paragraph
---
hereof.
"POA Administrative Procedures Manual" shall have the meaning assigned to such
------------------------------------
term in Section 4.01.
"POA Event of Default" shall have the meaning assigned to such term in Section
--------------------
7.02,
"POA Indemnified Parties" shall have the meaning assigned to such term in
-----------------------
Section 9.01.
"POA Operation and Maintenance Procedures Manual" shall have the meaning
-----------------------------------------------
assigned to such term in Section 4.02.
"POA Representative" shall have the meaning assigned to such term in Section
------------------
3.04.
"PPA" shall mean the Power Put Agreement entered into as of September 19, 1986,
---
between POA and Electric Utility, which became effective on June 30, 1998.
"Preventive Maintenance Program" shall have the meaning assigned to such term in
------------------------------
Section 2.09.
"Prior Agreement" shall have the meaning assigned to such term in the second
---------------
WHEREAS clause in the preface hereto.
"Prudent Utility Practices" shall mean those practices, methods, equipment,
-------------------------
specifications, and standards of safety and performance which are commonly used
by operators of facilities similar to the Facility which, in the exercise of
reasonable judgment and in light of the facts known at the time the decision was
made, are considered good, safe and prudent practice in connection with the
operation and maintenance of such facilities.
"Records" shall have the meaning assigned to such term in Section 5.14.
-------
"Reimbursable Expenses" shall have the meaning assigned to such term in Section
---------------------
5.02.
-6-
"Relocation Expenses" shall have the meaning assigned to such term in Section
-------------------
5.05.
"Repair and Overhaul of the Gas Turbine Packages" shall have the meaning
-----------------------------------------------
assigned to such term in Section 2.04.
"Right-of-Way" shall mean the land across and through which the Pipeline passes,
------------
as more particularly described in Exhibit B to the Gas Pipeline Turnkey
Construction Agreement, dated as of April 5, 1991 between POA and OBG Technical
Services, Inc., as amended, and the Pipeline Order.
"Routine Maintenance" shall mean the inspection, cleaning and taking of other
-------------------
protective measures with respect to the Equipment (other than Equipment included
in the Gas Turbine Packages) to keep it in good working order and to prevent it
from prematurely deteriorating, breaking down or wearing out, including the
replacement of minor parts which (i) normally have a relatively short life, (ii)
can be expected to fail, deteriorate or wear out as a result of normal use of
the Equipment, or (iii) normally need to be replaced after dismantlement of the
Equipment, such as gaskets, seals, filters, fuses, bulbs and batteries.
"Site shall mean that certain parcel of land situated in the City of Syracuse,
----
County of Onondaga, State of New York, which has been leased to POA by the Steam
User pursuant to the Site Lease, together with the site of the Existing Plant.
"Site Lease" shall mean a lease agreement dated as of February 27, 1990 between
----------
POA and Steam User, as amended by letters dated May 1, 1990, June 22, 1990 and
August 29, 1990, and an amendment dated as of December 31, 1990, and as the same
may be further amended from time to time thereafter.
"Spare Parts" shall have the meaning assigned to such term in Section 2.14(c).
-----------
"Spare Parts Fee" shall have the meaning assigned to such term in Section 5.11.
---------------
"Steam Delivers Point" shall mean the point at which the steam delivery line or
--------------------
lines from the Facility interconnect with the Steam User's steam distribution
system.
"Steam Agreement" shall mean that certain Steam Contract, dated as of February
---------------
27, 1986, between POA and the Steam User, a copy of which has been provided to
GE, as amended from time to time.
"Steam User" shall mean Syracuse University, a New York educational corporation.
----------
"Subcontractor Expenses" shall have the meaning assigned to such term in Section
----------------------
5.06.
"Taxes" shall mean all levies, fees, charges, duties, tariffs and taxes,
-----
including sales taxes, value added taxes, use taxes, excise taxes and stamp
taxes, imposed by a Governmental Person.
"Term" shall have the meaning assigned to such term in Section 6.01.
----
-7-
"Training Expenses" shall have the meaning assigned to such term in Section
-----------------
5.04.
"Training Plan" shall have the meaning assigned to such term in Section 4.03.
-------------
"Transition Period" shall have the meaning assigned to such term in Section
-----------------
7.01(d).
"Wages" shall have the meaning assigned to such term in Section 5.03.
-----
ARTICLE II - ENGAGEMENT OF GE AND DESCRIPTION OF SERVICES
Section 2.01 Operation and Routine Maintenance of the Facility. (a) Beginning
on the Commencement Date and continuing throughout the Term, GE shall
continuously operate the Facility and perform all required Routine Maintenance
on a 24 hours/day, 7 days/week, 365 days/year basis (collectively, "Operate and
Maintain the Facility"). GE shall Operate and Maintain the Facility in
accordance with POA's instructions and the standards set forth in subsection
(viii) below so as to:
(i) cause POA to fully perform its obligations under the Facility
Agreements;
(ii) minimize the costs and expenses incurred by POA for, or in
connection with, the ownership, operation, maintenance, repair,
overhaul and replacement of the Facility and the Equipment and the
parts thereof;
(iii) cause all warranties and guarantees of the Facility and the
Equipment to remain in effect and coverage thereof not to be
reduced;
(iv) maximize the useful life of the Facility;
(v) cause the maintained portions of the Facility to be at least equal
in quality and class to the quality and class of such portions of
the Facility prior to the damage or wear and tear which necessitated
such maintenance;
(vi) cause all insurance coverage applicable to the Facility and to POA
to remain in effect;
(vii) cause the Facility and the operation thereof to comply with and
conform to all Legal Requirements; and
(viii) cause the Facility and the operation, maintenance, repair and
overhaul thereof to conform to Prudent Utility Practice, the IS0
Rules, the Operation and Maintenance Procedures Manual, the
Administrative Procedures Manual, the Annual Operating Plan, the
Annual Budget and all operating and maintenance manuals,
instructions and recommendations for the Facility and the Equipment.
(b) To the extent that GE's obligations under clauses (i) through (vii) in
paragraph (a) above, conflict, GE shall perform such obligations with relative
priorities as established by POA from time to time.
-8-
(c) In the event any mode or method of operation of the Facility proposed or
directed by POA would, in GE's reasonable opinion, have any adverse effect on
the Facility or its operation, maintenance, repair or overhaul, including,
without limitation, (i) any reduction in the efficiency of the Facility, (ii)
any increase in the cost of operating the Facility or any increase in the cost
or frequency of maintenance, repairs or overhauls, (iii) any inability or
failure of the Facility to comply with Legal Requirements, or (iv) any breach of
any Facility Agreement, then GE shall promptly so inform POA.
(d) Notwithstanding the foregoing, in the event GE reasonably believes that its
Operation and Maintenance of the Facility in a manner directed by POA would
result in GE incurring liabilities in excess of the liabilities GE would
otherwise incur in connection with its Operation and Maintenance of the Facility
in accordance with this Agreement ("Excess Liabilities"), then GE shall promptly
so inform POA and shall include in such notice a description of Excess
Liabilities in reasonable detail. Provided such notice is given, GE shall have
no obligation to Operate and Maintain the Facility in such manner unless and
until POA shall have entered into an agreement with GE, in form and substance
reasonably satisfactory to GE, to indemnify, defend, and hold GE harmless from
and against Excess Liabilities which arise from such Operation and Maintenance,
whether or not described in such notice.
Section 2.02 Certain Requirements Applicable to the Operation and Maintenance
of the Existing Facility and the Site. Subject to payment when due by POA of the
Reimbursable Expenses associated therewith, GE shall
(i) maintain the Existing Plant, except the portions of the Existing
Plant described in clause (ix) below, in as good a condition as it
exists upon the Commencement Date, ordinary wear and tear excepted,
and operate and maintain the Existing Plant in a state of readiness
to make available an alternate source of steam to the Steam User at
the pressures and temperature and meeting the other requirements of
the Steam Agreement within the shortest period of time technically
and reasonably possible, but in all events within no more than six
(6) hours after the interruption of the supply of steam from the
Facility;
(ii) when the Existing Plant includes all equipment necessary to start up
from a dead start without utility power, maintain such capability;
(iii) operate, maintain and promptly repair the Existing Plant in
accordance with the minimum requirements set forth in Exhibit A and
the requirements of the Operating Agreement;
(iv) do all shoring of foundations and walls of any structures on the
Site and every other act or thing which may be necessary for the
safety and preservation thereof and any part of the Facility by
reason of any excavation or other building operation upon any
adjoining property or street, alleyway or passageway, to the extent
that GE has actual notice of such excavation or other building
operation or the circumstances thereof are such that a reasonable
person in the position of the GE would have had knowledge thereof;
(v) as and to the extent required and approved by POA, promptly repair
and overhaul the steam boilers and related apparatus and equipment
of the Existing
-9-
Plant, and their replacements, if any as contemplated under Section
7.01 of the Operating Agreement;
(vi) at least twice during each calendar year, at such time as POA may
designate upon at least 15 days' prior written notice, test the
readiness and capability of the Existing Plant to meet the steam
supply requirements of the Steam User within six (6) hours after the
interruption of the supply of steam from the Facility by operating
the Existing Plant for a period of at least eight (8) hours, and
also perform, from time to time, such additional tests as POA may
reasonably request to determine the status of the maintenance and
readiness of the Existing Plant. POA shall promptly deliver to GE a
copy of any notice from Steam User designating the time for any
tests;
(vii) not commit, or permit to be committed, any waste or any nuisance on
the Site or permit any part of the Site to be used for any
dangerous, noxious or offensive purpose, not permit any damaged
improvement to remain on the Site for an unreasonable period of
time, not allow the manufacture (except to the extent that toxic or
hazardous substances are generated or produced in connection with
the Operation and Maintenance of the Facility in accordance with
this Agreement) or disposal of any toxic or hazardous substances on
the Site or otherwise at the Facility and shall only allow the
storage or presence of toxic or hazardous substances at the Site to
the extent necessary in connection with the operation of the
Facility and if such storage or presence is in compliance with all
Legal Requirements;
(viii) except as otherwise expressly permitted in the Operating Agreement,
use and operate the Existing Plant only as an alternate source of
steam to meet the steam requirements of the Steam User pursuant to
the Steam Agreement;
(ix) provide the Steam User with the exclusive use of (A) the office on
the second floor of the Existing Plant for the Steam User's
distribution system supervisory and clerical employees, and (B) the
locker, restroom and shower facilities adjacent to the office
described in the preceding clause (A) for the Steam User's
distribution system hourly employees;
(x) provide to POA and the Steam User (A) from time to time the
operating manuals, instructions and other documents and information
for, and relating to, the operation and maintenance of the Existing
Plant then being used by GE, and (B) training of employees of the
Steam User in the operation and maintenance of the Existing Plant;
and
(xi) make available to POA and the Steam User for their inspection at all
times during normal business hours all records and documents
relating to the operation, repair, maintenance and testing of the
Existing Plant, including, without limitation, all operating logs
and records and reports of inspection and testing maintained by GE
in accordance with Exhibit A and also furnish to POA and the Steam
User copies of the annual New York State boiler inspection report on
the Existing Plant within thirty (30) days of issuance of such
report.
-10-
Section 2.03 Certain Requirements Applicable to the Operation and Maintenance
of the Pipeline and Right of Way. GE's obligation to operate, maintain and
repair the Pipeline and the Right-of-Way, shall include, but is not limited to:
(i) all action required under the Pipeline Order, including the EM&CP;
(ii) inspection of the odorization equipment and provision of odorization
chemicals, as required by the Pipeline Order;
(iii) visual inspection of the Pipeline and Right-of-Way as required by
the Pipeline Order and correction of all dangerous conditions and
conditions existing thereon which might disturb the Pipeline or
interfere with its operation such as fallen trees, exposure of the
Pipeline, vandalism and the presence or deposition on the Right of
Way of toxic or hazardous substances;
(iv) all actions set forth in Exhibit B, including "smart pigging" the
Pipeline as required by prudent industry practices, the Pipeline
Order, or the Operating and Maintenance procedures contemplated
thereby; and
(v) all other actions reasonably required to prudently operate the
Pipeline and maintain the Right-of-Way and to cause the operation
and maintenance thereof to comply with all Legal Requirements.
Section 2.04 Repair and Overhaul of the Gas Turbine Packages.
(a) GE shall perform all labor and provide all supervision; all
procurement, administration and other support services; all tools
and equipment; all parts, assemblies and systems; all Consumables
(other than lubricants), materials and supplies; all services of
subcontractors and consultants; and all testing, inspection and
start-up services necessary to perform all repairs, replacements,
overhauls and maintenance of the Gas Turbine Packages needed during
the Term, whether scheduled or unscheduled, planned or unplanned,
and whether included in the Annual Budget or not (collectively, the
"Repair and Overhaul of the Gas Turbine Packages"). Notwithstanding
the foregoing, repair of damage, to the extent such damage
constitutes a loss or damage covered under POA's Property All Risk
Insurance ("Insured Loss"), shall not be included in the repairs GE
is required to perform under this Section 2.04, provided however,
-------- -------
that GE shall pay to POA (subject to Article X) an amount equal any
deductible amount applicable to any Insured Loss, to the extent such
Insured Loss is caused by GE's negligence, willful misconduct or
failure to perform its obligations under this Agreement.
(b) All Preventative Maintenance and Servicing Checks of the Gas Turbine
Packages shall be performed in accordance with applicable
manufacturers' recommendations as revised, amended and updated from
time to time, including, but not limited to, General Electric Marine
and Industrial Engines and Service Division On-Site Operation and
Maintenance Manual for Industrial Gas
-11-
Turbines, LM5000 G Series and P Series (GEK 72550) "Preventative
Maintenance and Servicing Checks"; General Electric Marine and
Industrial Engines and Service Division Technical Manual for Power
Turbines (GEK 95450); Brush Electrical Machines Limited Service
Manual for Cylindrical Rotor A.C. Generator; Xxxxxxx 8, Xxxxxxxxx
Services, Inc. Gas Turbine Products Division Manual GEK 72550
(latest revision) and the schedule ("Maintenance Schedule") attached
hereto as Exhibit H. Where the Maintenance Schedule requires
maintenance, replacements or overhauls more often or sooner than
would be required by applicable manufacturers' recommendations, the
Maintenance Schedule shall govern, except to the extent waived by
POA in its sole discretion. Replacement and overhauls of the Gas
Turbine Packages, including but not limited to Hot Section/Combustor
overhaul or replacement and/or Power Turbine overhaul or
replacement, will be performed when necessary as determined by
borescope inspection (or visual inspection if the unit is open for
other reasons), conducted in accordance with manufacturer's
guidelines described above, by the original equipment manufacturer
or other qualified, independent inspectors.
Section 2.05 Liens. Except to the extent liens arise as a result of any
failure by POA to perform its payment obligations hereunder, GE shall not
create, permit or suffer to exist by, through or under GE, any liens or
encumbrances on the Facility. Any such lien or encumbrance by, through or under
GE and not resulting from POA's failure to perform its payment obligations under
this Agreement shall be discharged by GE within thirty (30) days of GE's receipt
of notice thereof.
Section 2.06 Personnel Standards.
(a) GE shall provide and make available as necessary, in accordance with
the GE Organizational Chart attached hereto as Exhibit C, all such
operational, professional, supervisory and managerial personnel as
are required to Operate and Maintain the Facility. Such personnel
shall be qualified, licensed (to the extent required by Legal
Requirements) and experienced in the duties to which they are
assigned. Each personnel's qualifications shall conform to the
position descriptions which are part of the POA Operations and
Maintenance Procedures Manual.
(b) Not later than 10 days prior to GE's assignment of any person to
perform work at the Site, GE shall notify POA of the assignment of
such person to perform work at the Site.
Section 2.07 GE Plant Manager. GE shall appoint a Plant Manager and shall
cause a Plant Manager to be assigned to the Facility at all times during the
Term. Appointment of the first Plant Manager and each successor Plant Manager
shall be subject to the reasonable approval of POA.
Section 2.08 Training, GE shall provide all training required for personnel
assigned to Operate and Maintain the Facility. Such training shall be conducted
in accordance with the Training Plan.
-12-
Section 2.09 Preventive Maintenance Program. GE shall implement and maintain a
program of preventive maintenance for the Facility (the "POA Preventive
Maintenance Program"). The POA Preventive Maintenance Program shall include, but
not be limited to, the regular inspection, testing, calibration and servicing of
the Facility and the Equipment and shall be implemented in accordance with the
instructions and recommendations of the Constructor and the suppliers,
manufacturers and vendors of the Equipment. As a minimum, the POA Preventive
Maintenance Program shall include the scheduling (on a forward looking basis) of
preventive maintenance for a period of eighteen (18) months and shall establish
a reporting system which shall include: (i) the scheduling and tracking of work
to be performed; (ii) documenting any problems encountered; and (iii)
documenting the work performed in a manner satisfactory to POA. The POA
Preventive Maintenance Program may be based on GE's standard preventive
maintenance program, but shall incorporate such additions and revisions thereto
which are required by the characteristics of the Facility and/or reasonably
requested by POA.
Section 2.10 Inventory System. GE has developed and is utilizing, and POA has
approved, a tracking and control system for all Consumables, Spare Parts and
Parts and Tools. GE shall utilize such system throughout the Term. A monthly
report of Consumables, Spare Parts and Parts and Tools added or removed from
inventory and the cost incurred in connection therewith shall be provided to
POA. A complete physical inventory of all items in inventory shall be taken
annually and a report thereof issued to POA within 14 days of its completion,
including a reconciliation with the preceding inventory, all in accordance with
Prudent Utility Practice and generally accepting auditing standards. Safe,
secure and segregated storage facilities shall be maintained for all items held
in inventory.
Section 2.11 Operation and Maintenance Procedures. GE shall implement and
administer the POA Operation and Maintenance Procedures Manual.
Section 2.12 Administrative Procedures Manuals. GE shall implement and
administer the POA Administrative Procedures Manual.
Section 2.13 Warranty and Insurance Claims. GE shall notify POA as soon as
reasonably practicable of any defect or other deficiency in the Facility
discovered by GE. If requested by POA, GE shall assist POA in preparing and
prosecuting warranty claims with respect to any defects or deficiencies in the
Facility or the Equipment. The prosecution of all warranty claims shall be
controlled by POA. POA, subject to the provisions of this Agreement, shall not
hold GE responsible for any lost revenues associated with a warranty claim. GE
shall assist POA in preparing and prosecuting claims against any insurance
carrier for payment of losses incurred in connection with the Facility or the
operation thereof.
Section 2.14 Procurement and Inventories.
(a) Consumables. GE shall purchase and cause to be delivered to the Site
-----------
such Consumables as are required to Operate and Maintain the Facility
in accordance with this Agreement and to keep a reasonable inventory
of Consumables at the Site.
-13-
(b) Parts and Tools. On behalf of POA. GE shall purchase and cause to be
---------------
delivered to the Site all Parts and Tools required to Operate and
Maintain the Facility in accordance with this Agreement.
(c) Spare Parts. At all times during the Term, GE shall keep the parts,
-----------
systems and assemblies listed on Schedule 1 (the "Spare Parts") at the
Site or at a location within 12 miles of the Facility. Schedule 1
shall be reviewed annually by the Parties and may be changed as the
Parties mutually agree. All right, title and interest in each Spare
Part shall remain in GE or an Affiliate of GE until such time as such
Spare Part is used or incorporated into the Facility or is paid for in
full by POA. Each Spare Part withdrawn from inventory and used or
incorporated into the Facility shall be replaced by GE as promptly as
practicable. Spare Parts in such inventory which are or become
unserviceable, including, without limitation, such items which are or
become defective, exceed their useful shelf-life or become
unserviceable due to modification of the Facility, shall be replaced
immediately upon, or prior to, becoming unserviceable if such
unserviceability was or reasonably should have been anticipated by GE,
otherwise as promptly as practicable.
(d) Quality of Consumables, Parts and Tools and Spare Parts. All
-------------------------------------------------------
Consumables, Parts and Tools and Spare Parts shall be of a quality at
least equal to the corresponding item they are intended to replace or
if not intended for replacement, of good quality and shall be
sufficient and adequate for the intended purpose in conformity with
applicable instructions or recommendations of equipment manufacturers,
vendors or suppliers and Prudent Utility Practice. All such items
shall be warranted in accordance with usual or typical practice. All
such items shall be inspected as appropriate upon receipt and non-
conforming items shall be rejected and returned at no cost to POA.
(e) Procurement by, or from Vendors Designated by, POA. Notwithstanding
--------------------------------------------------
the foregoing, POA may elect, by written notice to GE, to (i) procure
directly any or all Consumables and Parts and Tools or other goods and
services which would otherwise be procured by GE hereunder, or (ii)
designate the vendors or suppliers from whom GE shall procure such
goods and services. POA shall provide reasonable advance notice to GE
of its intent to so procure such goods or services or designate the
vendors or suppliers from whom GE shall procure such goods and
services.
GE may object to the use of Consumables and Parts and Tools or other
goods and services procured directly by POA or procured from vendors
designated by POA. Such objection shall not be unreasonable, shall be
made in writing and shall set forth in reasonable detail the reasons
for such objection. Thereafter, GE shall have no liability arising out
of any failure to perform its obligations hereunder to the extent such
failure is caused by deficiencies in the quality of such Consumables
and Parts and Tools or other failures of the vendors thereof to
perform their obligations under the applicable purchase agreements
which were included in the reasons for GE's objection to the use of
such Consumables and Parts and Tools or the procurement thereof from
vendors designated by POA. To the extent such POA vendors' costs are
greater than that which GE
-14-
would have paid its own vendors, such excess shall not be considered
in calculating any budget excesses under Section 7.01(a)(v).
Section 2.15 Coordination with Electric Utility, ISO and Steam User. GE shall,
at the request of POA, interface and cooperate fully with the Electric Utility
and the ISO on all matters relating to the generation, sale and delivery of
electricity from POA's cogeneration facility and the agreements under which such
sales and deliveries are made, including without limitation the PPA and the ISO
Rules. Such interface and cooperation shall include, without limitation: (i)
review and inspection of the Facility and the Electric Utility Interconnection;
(ii) assistance with, and coordination of, Electric Utility repair, maintenance
and calibration of the Electric Utility Interconnection; (iii) providing notice
of, and schedules for, scheduled and unscheduled outages, and (iv) scheduling of
the generation of electricity in accordance with the orders and directions of
the Electric Utility, the ISO and POA. Further, pursuant to the requirements of
the Steam Agreement, GE, at the request of POA, shall interface and cooperate
fully with the Steam User concerning all matters relating to the Steam Agreement
including, without limitation: (i) notification and coordination of scheduled
Facility shutdowns; and (ii) notification of unscheduled shutdowns.
Section 2.16 Emergency. GE shall report all Emergencies, including GE's response
thereto, to POA. GE shall comply with all notification procedures as then in
effect.
Section 2.17 Claims and Litigation. Subject to the provisions of Section 2.25,
at the request of POA, GE shall reasonably assist POA in connection with all
claims and causes of action alleged against or accruing in favor of POA which
are connected with or related to the operation, maintenance, repair or overhaul
of the Facility.
Section 2.18 Permits and Other Governmental Approvals. At the request of POA, GE
shall assist POA in obtaining, maintaining or renewing any Permits and providing
any information required by any Governmental Person.
Section 2.19 Recalibrations. At the request of POA, but in any event no less
frequently than specified in the Operation and Maintenance Procedures Manual
and/or the Facility Agreements, or Prudent Utility Practice if required more
frequently thereby, GE shall arrange for the testing and recalibration of all
scales, meters, gauges and other measuring devices in accordance with Prudent
Utility Practices at the Facility and the Steam Delivery Point.
Section 2.20 Major System Repairs and Insured Losses.
(a) GE shall, unless otherwise directed in writing by POA, solicit
bids for any required Major System Repairs or repairs required
due to the occurrence of Insured Losses, review and advise POA
with respect to such bids and assist in administering any
contracts entered into for the performance of or otherwise in
connection with any Major System Repairs or repairs required due
to the occurrence of Insured Losses.
(b) GE may, at its option, submit bids or proposals to perform any
Major System Repair and any repairs required due to the
occurrence of Insured Losses. POA shall evaluate such bids or
proposals on a basis consistent with its evaluation of bids and
proposals received from third parties.
-15-
(c) In the event any contractor selected by POA to perform any Major
System Repair or any repairs required due to the occurrence of an
Insured Loss is not included among, or affiliated with one of,
the contractors listed in Schedule 3 hereto or, if not so
included or affiliated, is not approved by GE for performance of
the planned work, then GE may object to the selection of such
Contractor (a "Disapproved Contractor"). Such objection shall not
be unreasonable, shall be in writing, shall be provided not later
than 10 days after POA's request for approval of any contractor
and shall specify in reasonable detail the reasons for GE's
objection. Thereafter, GE shall have no liability arising out of
any failure to perform its obligations hereunder to the extent
any such failure is attributable to any deficiency in any
Disapproved Contractor which was identified as a reason for its
objection to the selection of such Disapproved Contractor in an
objection provided in accordance with this Section.
Section 2.21 Review and Administration of Agreements. GE shall review the
Facility Agreements to familiarize itself with all provisions thereof affecting
or relating to the Operation and Maintenance of the Facility. GE shall, from
time to time at the request of POA, assist POA in administering and performing
under the Facility Agreements.
Section 2.22 Inspections. GE shall, from time to time, as and to the extent
reasonably requested by POA, perform and provide the results of inspections of
any portion of the Facility or any of the Consumables, Parts and Tools and Spare
Parts which have been purchased on behalf of POA or which are kept at the Site
or kept available for use in connection with the Operation and Maintenance of
the Facility pursuant to Section 2.14 or otherwise, and GE shall notify POA of
any defects or other deficiencies observed by GE.
Section 2.23 Hazardous Substances. As the agent of POA, GE shall arrange for the
management, transportation and/or disposal of all hazardous and toxic substances
generated or produced in connection with the operation, maintenance, repair and
overhaul of the Facility. Such management, transportation and/or disposal shall
be performed by third party independent contractors; provided, that GE shall
only retain those contractors who are properly licensed in accordance with
applicable Legal Requirements. Copies of all contracts, purchase orders, reports
and other documents prepared in connection with the management, transportation
and/or disposal of hazardous and toxic substances shall be provided to POA.
Section 2.24 Other. Consistent with the requirements of this Agreement, GE shall
provide such other assistance, services and work reasonably required or
requested by POA in connection with the Operation and Maintenance of the
Facility, including without limitation, all reporting and documentation as set
forth in Article IV.
Section 2.25 Limitation on GE's Authority. Notwithstanding any provision in this
Agreement to the contrary, the following acts may not be done or taken, or
caused to be done or taken, by GE, or by any agent, representative or contractor
of GE, without the prior written approval of POA:
-16-
(i) settle, compromise, assign, pledge, transfer or release any claim,
suit, debt, demand or judgment against, or accruing in favor of, POA;
(ii) submit any claim, dispute or controversy to arbitration or judicial
process, or stipulate to any judgment with respect thereto, or agree
or consent to do any of the foregoing;
(iii) engage in any transaction on behalf of POA except as, and then only
to the extent specifically authorized herein, or take or agree to
take any action at variance with the applicable Annual Operating Plan
or Annual Budget; or
(iv) make or incur any cost or expense which is a capital expenditure or
for any capital improvement.
Section 2.26 Affiliate Matters. The terms of any agreement between GE and any
Affiliate of GE under which payments will be made which will be Reimbursable
Expenses shall be not less favorable than the terms available from unaffiliated
Persons.
Section 2.27 No Disruption of Steam User's Operations. GE hereby acknowledges
that the Steam User operates the university adjacent to the Site, and GE hereby
agrees to Operate and Maintain the Facility so as to not interfere with the
operations or business of the Steam User except as is contemplated by the Steam
Agreement. Recognizing that the operation of the Facility poses potential risks
to surrounding persons and property and that the proper operation and
maintenance of such facilities is of significant importance in mitigating such
potential risks, GE agrees to Operate and Maintain the Facility so as to not
adversely affect the safety of the Steam User or any Persons adjacent to or in
the vicinity of the Site.
Section 2.28 Site Access. POA, authorized representatives of POA and any other
persons authorized in writing by POA shall at all times have reasonable access
to the Facility and all records retained in connection therewith. All such
persons shall have the right to be present during any maintenance or repair
work. If any such Party desires access to any places where maintenance or repair
work is being performed or from which Parts and Tools or Spare Parts are being
obtained for the Facility, GE shall use reasonable efforts to facilitate or
arrange reasonable access thereto. GE shall permit any such Party to inspect and
review all such work. POA shall hold harmless and indemnify GE for and against
all claims made against GE due to (i) injury to or death of POA's personnel or
POA's invitees (other than GE) or (ii) damage to or destruction of property,
including the Facility, or any part thereof, in either case arising from the
exercise of inspection rights under this Section 2.28, except to the extent
caused by the negligence or willful misconduct of GE.
Section 2.29 Liability for Payments. Anything in this Agreement to the contrary
notwithstanding, GE shall not be responsible for making any payments required to
be made by POA pursuant to any Facility Agreements, or any other agreement, with
respect to the Facility and/or the Site. In the event POA shall become liable or
obligated to pay any fine or penalty due to the violation of any Legal
Requirement or Permit then GE shall reimburse and indemnify POA but only to the
extent such liability or obligation results from the negligence or willful
misconduct of GE or any failure by GE to perform its obligations hereunder.
-17-
Section 2.30 Alteration of Facility. GE shall not alter, improve or add to the
Facility if such alteration, improvement or addition will change the outside
appearance of the Facility without the prior written consent of POA, which may
be granted or withheld in POA's sole discretion, regardless of whether such
alteration, improvement or addition is included in the Annual Budget.
ARTICLE III - POA OBLIGATIONS
Section 3.01 General. POA shall furnish to GE, at POA's expense, the
information, services, materials and other items described in this Article III.
All such items shall be made available at such times and in such manner as may
be required for the expeditious and orderly operation, maintenance, repair and
overhaul of the Facility by GE.
Section 3.02 Information. POA shall (i) provide all technical, operational and
other information relating to the Facility which is in the possession, or under
the control, of POA; and (ii) use its best efforts to obtain such information
from third parties, as may be reasonably required by GE in the performance of
its obligations under this Agreement.
Section 3.03 Sale of Electricity and Cogeneration Services. POA shall be
responsible for the billing and collection of amounts due for electricity and
steam and/or thermal energy in other forms sold by POA, based upon Facility
operating data supplied by GE and reports received by GE.
Section 3.04 POA Representative. Within thirty (30) days of the Commencement
Date, POA shall designate a representative (the "POA Representative") who shall
be authorized to act on behalf of POA and with whom GE may consult at all
reasonable times. Whenever this Agreement requires or provides for the approval,
consent or some other action of POA, GE may rely on the approval, consent or
other action of the POA Representative. POA may change the POA Representative at
any time and from time to time by written notice to GE.
Section 3.05 Fuels and Utilities. POA shall provide and pay for all natural gas,
fuel oil, purchased electricity, water and other utilities used by the Facility,
as well as the costs of managing, transporting and/or disposing of solid and
liquid waste and toxic and hazardous substances.
Section 3.06 Procurement. In accordance with Section 2.14(e), POA may elect, by
written notice to GE, to (i) procure directly any or all Consumables and Parts
and Tools or other goods or services which would otherwise be procured by GE
hereunder, or (ii) designate the vendors or suppliers from whom GE shall procure
such items, systems or assemblies. POA shall provide reasonable advance notice
to GE of its intent to procure Consumables and/or Parts and Tools or other goods
or services.
Section 3.07 Annual Management Audit. Subject to Section 2.28, POA may at its
discretion institute an annual management audit of the Facility. Auditors shall
be selected by POA. Annual management audits may focus on areas of concern to
POA, assess overall performance of the Services or identify areas where
improvements may be warranted. GE shall be provided a copy of audit reports for
review, comment, refutation or corrective action as applicable. Specific
subjects for audits may include, but are not limited to:
-18-
(i) trends, deficiencies or opportunities for improvement in Facility
operations;
(ii) adherence to this Agreement;
(iii) appropriateness of Facility organization and staffing;
(iv) major equipment problems encountered and progress in resolution;
(v) potential Facility capital improvements;
(vi) regulatory compliance:
(vii) accounting, procurement and inventory management practices;
(viii) maintenance effectiveness; and
(ix) energy efficiency.
Section 3.08 Leased Engine Program. POA and GE shall commence their
participation in the Leased Engine Program, as defined and on the terms and
conditions set forth in Exhibit G, as of the Commencement Date.
Section 3.09 Liens. POA shall not create, permit or suffer to exist by, through
or under POA, any liens or encumbrances on any property owned by GE or its
contractors, including the Spare Parts. Any such lien or encumbrance by, through
or under POA and not resulting from GE's default under this Agreement shall be
discharged by POA within thirty (30) days of POA's receipt of notice thereof or
POA shall otherwise provide reasonable protection for GE against any adverse
consequences of such lien.
Section 3.10 Access. From the Commencement Date, POA shall provide and ensure
GE total and unrestricted access to the Facility.
Section 3.11 General, Office and Maintenance Facilities. During the Term, POA
shall continue to provide GE with the use of office facilities located at the
Site substantially the same as or equal to the facilities being provided
immediately prior to the Commencement Date.
Section 3.12 Spare Parts. POA, at GE's request, will execute and deliver such
financing statements and other instruments as GE may reasonably request to
demonstrate and protect GE's right, title and interest in the Spare Parts,
provided however, that POA shall have no obligation to file financing statements
or other instruments with respect to any property in which POA has any ownership
interest.
ARTICLE IV - BUDGETS, PROCEDURES, PLANS AND REPORTING
Section 4.01 POA Administrative Procedures Manual. GE shall promptly, but in no
event later than six (6) months from the date hereof, prepare and submit to POA
for approval (which shall not be unreasonably withheld or delayed) an updated
administrative procedures manual (the "POA Administrative Procedures Manual")
which shall contain administrative information regarding the administrative
procedures to be followed in the operation, maintenance, repair and overhaul of
the Facility, including without limitation: (i) the organization of GE's
corporate personnel and their reporting requirements; (ii) correspondence and
review procedures; (iii) limits of authority; (iv) procurement and contracting
procedures: (v) accounting, bookkeeping and record keeping systems; (vi)
personnel procedures; and (vii) procedures for the receipt and implementation of
POA-issued directives relating to this Agreement and the operation, maintenance,
repair and overhaul of the Facility. The POA Administrative Procedures Manual
-19-
may be based on GE's standard manual, but shall include such additions,
deletions and revisions as may reasonably be required by the characteristics of
the Facility and as may reasonably be requested by POA. POA shall have the right
to require GE to make reasonable modifications from time to time to the POA
Administrative Procedures Manual that are not inconsistent with Legal
Requirements, Prudent Utility Practices, insurance policies or any Facility
Agreement. GE shall give prompt written notice to POA of any revision to the POA
Administrative Procedures Manual.
Section 4.02 POA Operation and Maintenance Procedures Manual. GE shall promptly,
but in no event later than 6 months after the date hereof, prepare and submit to
POA for its review and approval (which shall not be unreasonably withheld or
delayed) an updated manual setting forth the procedures GE will follow in
operating, maintaining, repairing and overhauling the Facility (the "POA
Operation and Maintenance Procedures Manual"). The POA Operation and Maintenance
Procedures Manual shall include, among other things, an operating program,
operating procedures, a maintenance and materials management system, maintenance
program, emergency operating procedures, an energy management program, record-
keeping procedures, reporting procedures, a safety program, a security plan,
problem identification and root cause determination procedures and position
descriptions for each person who will operate, maintain, repair and overhaul the
Facility. The Operation and Procedures Manual shall provide, among other things,
that GE shall (i) maintain accurate and detailed accident and injury reports and
shall inform its employees of safety practices and the requirements of GE's
safety program and submit a copy of those reports to POA; (ii) require all of
its employees, agents and representatives, when at the Facility, to abide by the
most current version of the GE safety procedures manual; (iii) maintain a supply
of suitable safety equipment (including fire extinguishers) and shall train its
employees in the use of such equipment; (iv) promptly take all precautions that
are reasonable to safeguard against risks of fire, injury to or death of persons
on the Site and damage to property, including the Facility; (v) make regular
safety inspections of the Facility, and, (vi) keep records of, and provide
notification to POA, of all unusual operating conditions as needed by POA to
prepare and file reports required under applicable Legal Requirements. The POA
Operation and Maintenance Procedures Manual may be based on GE's standard
manual, but shall be consistent with the operation and maintenance manuals used
at the Facility as of the date hereof and shall include such additions,
deletions and revisions as may reasonably be required by the characteristics of
the Facility and as may reasonably be requested by POA. POA shall have the right
to require GE to make reasonable modifications from time to time to those
provisions of the POA Operation and Maintenance Procedures Manual that are not
inconsistent with Legal Requirements, Prudent Utility Practices, insurance
policies or any Facility Agreement. GE shall give prompt notice to POA of any
revisions to the POA Operation and Procedures Manual.
Section 4.03 Training Plan. GE shall submit a training plan (the "Training
Plan") to POA promptly after the execution of this Agreement. The Training Plan
shall describe the minimum qualifications and experience for trainees, training
to be conducted by GE and trainee evaluation criteria. The Training Plan shall
be subject to POA's approval, which shall not be unreasonably withheld or
delayed.
Section 4.04 Annual Budget and Operating Plan.
(a) Approval of the Annual Budget. At least one hundred eighty (180) days
-----------------------------
before the start of each Operating Year, GE shall submit a proposed
operating plan for
-20-
such Operating Year (each, an "Annual Operating Plan"). The Annual
Operating Plan shall be reviewed by POA and agreed to in principle
prior to submittal of the Annual Budget. At least one hundred eighty
(180) days before the start of each Operating Year, other than the
first Operating Year, GE shall prepare and submit to POA a proposed
budget for such Operating Year (each, an "Annual Budget"). POA shall
promptly review GE's proposed Annual Budget and Annual Operating Plan
and may, upon written notice to GE, propose changes, additions,
deletions and modifications thereto. If GE accepts any changes
proposed by POA, the proposed Annual Operating Plan and proposed
Annual Budget as modified shall be adopted. If GE does not agree with
any of the changes proposed by POA, then the Parties shall meet and
work in good faith to agree upon an Annual Operating Plan and Annual
Budget. Once the Parties are in agreement, copies of the Annual
Operating Plan and the Annual Budget shall be approved in writing by
both Parties no later than one hundred fifty (150) days before the
start of the Operating Year. Once approved, the Annual Operating Plan
and the Annual Budget shall remain in effect throughout the applicable
Operating Year, subject to such change, revision, amendment and
updating in accordance with this Agreement. The Annual Budget for the
first Operating Year is attached hereto as Exhibit D.
(b) Failure to Agree Upon Annual Budget. If the Parties cannot reach
-----------------------------------
agreement on the Annual Budget for an Operating Year prior to 120 days
before the start of such Operating Year, then, until such time as
agreement is reached or the dispute is resolved, the Annual Budget for
such Operating Year shall be based on the amounts contained in the
Annual Budget for the preceding Operating Year, as adjusted with
respect to expense items to reflect the net change, if any, between
the most recently published Consumer Price Index available on the
first day of the Operating Year in question and the corresponding
Consumer Price Index in effect at the start of the immediately
preceding Operating Year.
(c) Failure to Agree Upon Annual Operating Plan. If the Parties cannot
-------------------------------------------
reach agreement on the Annual Operating Plan for an Operating Year
prior to 120 days before the start of such Operating Year, then, until
such time as agreement is reached or the dispute is resolved, the
Annual Operating Plan for such Operating Year shall be the same as the
Annual Operating Plan for the prior Operating Year, subject to
adjustment as required for the safe operation of the Facility and as
required under the applicable Facility Agreements.
Section 4.05 Accounts and Reports. From and after the Commencement Date, GE
shall furnish to POA the following reports:
(a) Weekly Reports. On the first business day of each week, GE shall
--------------
furnish to POA a report on the following events or occurrences which
occurred during the preceding week: (i) significant events related to
the operation and maintenance of the Facility; (ii) events which
adversely affected the safety of persons or property; (iii) any injury
to persons or damage to property; (iv) events which did or, in the
reasonable opinion of GE, could have had environmental significance,
including events which did or could have caused the Facility or its
operation to fail to comply with any Legal Requirement, and submittals
made which were
-21-
required by or made pursuant to any Legal Requirement; (v) inspections
or visits to the Facility by any representative, employee or agent of
any Governmental Person; (vi) status of training; (vii) visitors to
the Facility; (viii) operating statistics, including electric energy
generated, electric energy exported, steam generated, steam exported,
fuel consumed, hours of operation of the gas turbines and similar
information; (ix) events within the foregoing categories scheduled or
planned to occur within the 30 days following such week, and (x) such
other events or occurrences with respect to which POA may reasonably
request GE to include in its report.
(b) Monthly Reports. Within fifteen (15) days after the end of each
---------------
calendar month, GE shall submit to POA: (i) a monthly report in
reasonable detail covering activities conducted during such calendar
month with respect to operation and maintenance of the Facility
(including information regarding electric energy generated, electric
energy exported, steam generated, steam exported, fuel consumption,
capacity factor, availability, heat rate, and rolling average
qualifying facility status on a calendar year basis) compared to the
Annual Operating Plan for the specific month and the year to date
total, the percent of the year's Annual Operating Plan amount for such
items and any budget deviations indicated with a statement of any
individual line items of the Annual Operating Plan that have been
exceeded; capital improvements, labor relations, inventory activity,
other significant matters and any other matters with respect to which
POA may reasonably request GE to submit its report, which report shall
include a list of any significant operating problems encountered by GE
together with the remedial actions planned by GE (particularly with
respect to Major System Repair items) and a brief summary of major
activities planned over the next two (2) calendar months; (ii) a
statement setting forth all Reimbursable Expenses paid or incurred
during the month, which statement shall (A) itemize in reasonable
detail the computation of such amounts, (B) provide a summary of the
Reimbursable Expenses incurred for the specific month and the year to
date total, the percent of the Operating Year's Annual Budget amount
for such items and any budget deviations indicated and (C) a statement
of any individual line items of the Annual Budget that have been
exceeded: (iii) a summary of (A) the BTUs of steam provided to the
Steam User, (B) the BTUs of condensate returned by the Steam User (as
well as the remedial actions taken by GE with respect to condensate
returned to the Facility that failed to meet the parameters provided
in the Steam Agreement) and (C) the scheduled and unscheduled outages
of the Facility and their duration, and other data needed for thermal
billing; (iv) a summary statement of emissions data needed by POA for
any required submittal pursuant to the Permits and operation of the
Facility and a written record of Electric Utility and ISO notices and
any notices or any other reports or documents POA is required to
provide pursuant to the Facility Agreements; and (v) a statement of
any known accidents, injuries or violations of any Permits or other
Legal Requirements and any safety procedures. Notwithstanding the
foregoing, the statement required by clause (iii) of this paragraph
(b) shall be delivered to POA within two (2) business days of the end
of the calendar month.
-22-
(c) Operating Year Annual Reports. Within thirty (30) days after the end
-----------------------------
of each Operating Year, GE shall submit to POA: (i) a summary report
covering the performance of the Facility and operation and maintenance
activities conducted during the previous Operating Year, including
without limitation, information regarding (A) total kW hour of
electric energy generation and export, (B) average annual capacity and
capacity factor, (C) average on-peak capacity factor, (D) total fuel
consumption for natural gas and fuel oil, (E) average annual heat
rate, (F) number of BTUs of steam generated and exported, (G) number
of BTUs of condensate returned, (H) capital improvements made, (I)
base and overtime labor expended for both operation and maintenance,
(J) operation, maintenance, safety and other personnel training
performed, (K) any other significant matters, and (L) any other
matters with respect to which POA may reasonably request GE to submit
in its report, which report shall include a listing of any significant
operating or other problems encountered by GE along with the remedial
actions planned by GE (particularly in relation to Major System Repair
items and a summary report of major activities planned over the next
Operating Year; and (ii) a statement, certified as to its truth and
accuracy by an officer of GE, setting forth all Reimbursable Expenses
paid or incurred, which statement shall itemize and include in
reasonable detail the computation of such amounts, including a summary
of Reimbursable Expenses for the previous Operating Year and any
deviations from the Annual Budget or Annual Operating Plan for the
previous Operating Year and the reasons for such deviations.
(d) Reports and Notices Required in Connection with Electricity Generation
----------------------------------------------------------------------
and Sales. As directed by POA, GE shall prepare and provide to the
---------
Electric Utility, the ISO and/or any other purchaser of electricity
from POA, such schedules, notices, reports and other information
regarding electricity generation, Facility outages and the status of
the Facility as is required under the PPA and/or the ISO Rules.
(e) Litigation: Permit Lapses. Upon obtaining actual knowledge thereof,
-------------------------
each Party shall, as soon as reasonably practicable, submit written
notice to the other Party of: (i) any pending or threatened
litigation, disputes, actions or other material actions concerning the
Facility or the operation thereof; (ii) any lapse, modification,
termination or expiration of any Permit issued, obtained or required
for the Facility or the operation thereof; (iii) any violation of any
Permit or Legal Requirement; (iv) any refusal to grant, renew or
extend any Permit the stated reasons therefor and a summary of the
actions taken; and (v) any dispute with any Governmental Person that
may have an adverse effect on the operation of the Facility.
Notwithstanding the foregoing, POA shall only be obligated to notify
GE of matters which may either impact upon POA's performance of its
obligations under this Agreement, may result in liability of POA to GE
or for which GE may be liable.
(f) Assistance. GE shall maintain accurate and complete Facility operating
----------
records, maintenance reports and metering data. GE shall cooperate
with POA's accountants, auditors and other representatives (i) in the
preparation of the reports required to meet all Legal Requirements and
to perform POA's obligations under the Facility Agreements, and (ii)
in the preparation of POA's
-23-
periodic financial statements and reports and the Federal, state
and local income tax returns of POA and its partners.
(g) Other Information. GE shall promptly submit to POA (i) any other
-----------------
material information which in the reasonable opinion of GE concerns
new or significant aspects of the Facility or the operation,
maintenance, repair or overhaul thereof; and (ii) such other
information concerning the Facility or the operation, maintenance,
repair and overhaul thereof reasonably requested by POA.
Section 4.06 Changes to Annual Budget and Annual Operating Plan.
(a) Proposal of a Change to the Annual Budget and Operating Plan. The
------------------------------------------------------------
Parties recognize that changes to a previously approved Annual
Budget and Annual Operating Plan (each, a "Change") may be
required. POA and GE may by a written notice to the other Party
propose a Change. The written notice shall describe the proposed
Change in reasonable detail and the reasons therefor.
(b) Change Order Budget Statement. The written notice of a Change
-----------------------------
proposed by GE shall be accompanied by a Change Order Budget
Statement which shall include (a) the direct cost or cost savings
to POA of the proposed Change; (b) the time anticipated to
implement the proposed Change; (c) the indirect costs or cost
savings of the proposed Change including any loss of electricity
revenues and any increased or decreased insurance, operating,
maintenance or other costs during or following the implementation
of the proposed Change; (d)) changes in the operating efficiency of
the Facility; and (e) any other material effect on the Operation
and Maintenance or efficiency of the Facility. Upon receipt by GE
of any proposed Change from POA, GE shall use its best efforts to
prepare and submit to POA a Change Order Budget Statement with
respect to such proposed Change within 30 days of the receipt of
POA's proposed Change. No proposed Change shall be implemented
until an agreement has been executed by both Parties ("Change
Order") approving the Change and the related Change Order Budget
Statement; provided, however, that GE shall be entitled to
implement a proposed Change without the prior approval of POA if
such Change is required due to an Emergency.
(c) Agreement on Change Order. POA and GE shall diligently and in good
-------------------------
faith endeavor to reach agreement upon any proposed Change and the
related Change Order Budget Statement: (i) within 30 days after the
date of the receipt of a proposed Change and related Change Order
Budget Statement from GE or (ii) within 45 days after the date of
the receipt of a proposed Change and related Change Order Budget
Statement from POA. If a Change is required as a result of an
Emergency, then GE shall provide to POA, as soon as practicable,
notice of such Change, together with a statement describing the
Emergency. Within thirty (30) days of completion of a Change due to
an Emergency, GE shall provide POA with a Change Order and a Change
Order Budget Statement. If a Change due to an Emergency causes the
Annual Budget to be exceeded and POA believes that an Emergency did
not exist, then POA shall have the right to dispute the Change. If
POA and GE do not agree as to the resolution of such
-24-
dispute, then either Party may submit the dispute for resolution
in accordance with Article XI.
ARTICLE V - COMPENSATION AND PAYMENT
Section 5.01 Payments to GE. In consideration for the performance by GE of its
obligations hereunder, POA shall pay to GE, in the manner and at the times
specified in this Article V, the Reimbursable Expenses, the Fired-Hour Fee, the
Spare Parts Fee and the Operating Fee. GE shall render bills monthly and shall
include with its bills such original invoices, purchase orders and other
contracts and other documentation as may be reasonably required by POA to verify
the amount of, and incurrence by GE, of Reimbursable Expenses included in the
respective xxxx.
Section 5.02 Reimbursable Expenses.
(a) Reimbursable Expenses shall consist of Payroll Costs, Training
Expenses, Relocation Expenses, Subcontractor Expenses, Taxes and the
Handling Fee and, subject to the limitations set forth herein, the
costs incurred by GE for the purchase and delivery to the Site of
Consumables and Parts and Tools.
(b) GE shall invoice POA for Reimbursable Expenses as follows: No later
than fifteen (15) days following the end of each month after the
Commencement Date, GE shall submit to POA an invoice for all
Reimbursable Expenses actually incurred by GE during such month. Each
invoice shall be payable by POA promptly within 30 days of POA's
receipt thereof.
Section 5.03 Payroll Cost. Payroll Cost shall be the sum of (a) the amount of
all wages and salary which GE pays directly to its employees for labor and
services performed at the Site for or in connection with the Operation,
excluding all overtime associated with the overhaul of the Gas Turbine Packages,
and Maintenance of the Facility and the Repair and Overhaul of the Gas Turbine
Packages, up to, in any Operating Year, an amount equal to the product of 1.02
and the amount set forth in the Annual Budget for such Operating Year for wages
("Wages"), (b) an amount equal to 40% of the sum of (i) Wages paid to employees
who do not receive additional Wages for overtime and the Wages for non-overtime
hours paid to employees who receive additional Wages for overtime and, and (ii)
the straight-time portion of Wages paid for overtime hours paid to employees who
receive additional Wages for overtime, to cover GE's salary related costs, such
as benefits, payroll taxes and employment-related insurance premiums, and (c) an
amount equal to 10% of the sum of (i) Wages paid to employees who do not receive
additional Wages for overtime, (ii) Wages paid for non-overtime hours and the
straight-time portion of Wages paid for overtime hours paid to employees who
receive additional Wages for overtime, to cover GE's allocable general and
administrative costs.
Section 5.04 Training Expenses. The actual, direct costs and expenses
reasonably incurred by GE for training ("Training Expenses") shall be
Reimbursable Expenses, except that, for purposes of calculating the amount of
Reimbursable Expenses, an amount equal to such costs and expenses incurred for
training any person who is, for any reason within the control of GE, no longer
assigned full-time to the Operation and Maintenance of the Facility within 12
months of the completion of such training shall be deducted from such costs and
expenses incurred for
-25-
training any person to replace such person no longer assigned full-time to
Operate and Maintain the Facility.
Section 5.05 Relocation Expenses. The actual, direct costs and expenses
reasonably incurred by GE for the relocation of employees to the Syracuse, NY
area who are assigned full-time to the Operation and Maintenance of the Facility
("Relocation Expenses") shall be Reimbursable Expenses, except that, for
purposes of calculating the amount of Reimbursable Expenses, an amount equal to
such costs and expenses incurred to relocate any employee who is, for any reason
within the control of GE, no longer assigned full-time to the Operation and
Maintenance of the Facility within 12 months of his relocation shall be deducted
from such costs and expenses incurred in connection with the relocation of any
person to replace such person no longer assigned full-time to Operate and
Maintain the Facility. Relocation Expenses for any individual transferring to
the Facility will be limited to those authorized within GE's relocation policy
and those costs reasonably incurred for travel within the continental United
States.
Section 5.06 Subcontractor Expenses. The actual, direct costs and expenses
incurred by GE for the services of subcontractors and consultants including
subcontractors engaged to manage, transport and dispose of hazardous and toxic
substances, ("Subcontractor Expenses"), shall be Reimbursable Expenses, provided
however, that such costs shall include only reasonable costs reasonably incurred
and shall exclude (i) such costs incurred in connection with the Repair and
Overhaul of the Gas Turbine Packages, and (ii) such costs properly allocable to
GE's general and administrative costs or which are incurred for services for
which POA is obligated to compensate GE pursuant to Section 5.08 or otherwise
hereunder.
Section 5.07 Taxes. All Taxes (other than GE's franchise taxes, state, local
or federal income taxes or any other Taxes measured by GE's income) incurred by
GE under this Agreement shall be a Reimbursable Expense.
Section 5.08 Handling Fee.
(a) A fixed annual fee of $50,000 shall be a Reimbursable Expense in
consideration for all labor and services provided by GE in connection
with the purchasing of Consumables and Parts and Tools. Within fifteen
(15) days following the end of each calendar month after the
Commencement Date, GE shall submit to POA an invoice for one-twelfth
(1/12th) of the Handling Fee. POA shall pay GE the full amount of each
such invoice promptly within thirty (30) days after receipt of such
invoice, subject to the provisions of Section 5.15.
(b) A fee equal to 10% of the price paid by POA for Consumables, Parts and
Tools, and labor procured by GE for or in connection with the
performance of capital improvements, Major System Repairs or repairs
required as a result of the occurrence of Insured Losses which are not
performed by GE, shall be a Reimbursable Expense.
Section 5.09 Costs for Consumables and Parts and Tools.
(a) Consumables. The actual, direct costs incurred by GE for the purchase
-----------
of Consumables and the delivery thereof to the Site shall be
Reimbursable
-26-
Expenses, provided however, that such cost shall be limited to the
reasonable cost of Consumables which are reasonably required by GE to
Operate and Maintain the Facility. Notwithstanding the foregoing, the
cost of Consumables (other than lubricants) used for or in connection
with the Repair and Overhaul of the Gas Turbine Packages shall not be
included in Reimbursable Expenses.
(b) Parts and Tools. The actual, direct costs incurred by GE for the
---------------
purchase of Parts and Tools and the delivery thereof to the Site shall
be included in Reimbursable Expenses, provided however, that such cost
shall be limited to the reasonable cost of Parts and Tools which are
reasonably required by GE to Operate and Maintain the Facility. The
cost of Spare Parts used at or incorporated into the Facility and
included in Reimbursable Expenses shall be equal to GE's actual,
direct cost incurred to purchase such part and have it delivered to
the Site, at the time it was added to the inventory of Spare Parts.
Notwithstanding the foregoing, the cost incurred for (i) Spare Parts,
and (ii) Parts and Tools which are used for or in connection with the
Repair and Overhaul of the Gas Turbine Packages shall not be included
in Reimbursable Expenses.
Section 5.10 Fired-Hour Fee and Directed Starts. In consideration of GE's
Repair and Overhaul of the Gas Turbine Packages, POA shall pay to GE a monthly
fee (the "Fired-Hour Fee") in an amount equal to the product of $88 (the "Per-
Hour Fee") and the number of hours in the respective month each gas turbine in
the Facility operates and xxxxx fuel at firing temperatures not exceeding 1410
degrees F. The Per-Hour Fee shall increase to $92 for each hour of operation of
a gas turbine during which such gas turbine is operated, at POA's request, for
20 minutes or more at firing temperatures in excess of 1410 degrees F, up to
1430 degrees F, and shall increase to $97 for each such hour during which such
temperatures are greater than 1430 degrees F, up to 1450 degrees F, for 20
minutes or more. POA shall not require operation of either gas turbine at firing
temperatures in excess of 1450 degrees F. There shall be added to the Fired-Hour
Fee an amount equal to the product of $600 and the number of Additional Directed
Starts which occurred in the respective month, and an amount equal to the
product of $1,200 and the number of Excess Directed Starts which occurred in the
respective month. "Additional Directed Starts" shall mean the fifty-sixth
through seventy-fifth Directed Starts which occur in each Operating Year.
"Excess Directed Starts" shall mean the Directed Starts in excess of 75 which
occur in each Operating Year. POA shall not require more than 100 Directed
Starts of either gas turbine during any Operating Year.
Section 5.11 Spare Parts Fee. In consideration of GE's purchasing, delivering
and maintaining the inventory of Spare Parts as required under Section 2.14(c),
POA shall pay to GE an annual fee of $50,000 ("Spare Parts Fee"). Within
fifteen (15) days following the end of each calendar month after the
Commencement Date, GE shall submit to POA an invoice for one-twelfth (1/12th) of
the Spare Parts Fee. POA shall pay GE the full amount of each such invoice
promptly within thirty (30) days afler receipt of such invoice, subject to the
provisions of Section 5.15.
Section 5.12 Operating Fee. For each Operating Year, POA shall pay to GE an
Operating Fee for the Operation and Maintenance of the Facility. The amount of
the Operating Fee shall be three hundred fifty thousand dollars ($350,000) per
Operating Year or a pro rata portion of such amount for Operating Years which
consist of less than 12 months. Within fifteen (15) days following the end of
each calendar month after the Commencement Date, GE shall submit
-27-
to POA an invoice for one-twelfth (l/12th) of the Operating Fee. POA shall pay
GE the full amount of each such invoice promptly within thirty (30) days after
receipt of such invoice, subject to the provisions of Section 5.15.
Section 5.13 Interest. Except for any amounts in dispute as provided for in
Section 5.15, any amount owed to one Party by the other Party after the date
such amount is due shall accrue interest each day from such date that such
amount is not paid at the Default Rate. Such accrual shall take place
automatically, and no failure or delay by any Party to invoice the other Party
for such interest shall be deemed a waiver of the right to collect such
interest.
Section 5.14 Accounting and Audit Rights. GE shall keep and maintain, in
accordance with generally accepted accounting principles consistently applied,
receipts, memoranda, vouchers, inventories and accounts of every kind and nature
pertaining to the Reimbursable Expenses, as well as complete summaries and
reports setting forth all reimbursable man-hours expended, payroll costs
incurred and the monthly salary and hourly rate of each and every employee whose
wages constitute a Reimbursable Expense hereunder (collectively "Records")
sufficient to reflect accurately and completely all Reimbursable Expenses. GE
shall keep and preserve the Records for a period of at least three (3) years
from and after the close of the Operating Year in which such costs were
incurred. POA, its representatives and any firm of independent auditors
appointed by POA shall have access, upon reasonable advance written notice to
GE, to the Records maintained by GE for the purposes of auditing and verifying
the Reimbursable Expenses. POA shall have the right to reproduce all or part of
the Records. If, pursuant to any audit and review, it is determined that any
amount previously paid by GE did not constitute a Reimbursable Expense due and
payable by POA, then POA may recover such amount from GE with interest thereon
from the date of payment to the date of repayment at the Default Rate.
Section 5.15 Disputed Payments. If a Party disputes any amounts included in
any invoice provided to such Party by the other Party, such Party shall give
written notice to the other Party of each disputed amount and shall pay the full
amount of such invoice that is not in dispute within the time periods set forth
herein for such payment, The Parties shall endeavor diligently and in good faith
to resolve any issue with respect to the amount remaining in dispute within
thirty (30) days after the date of the other Party's receipt of the notice of
disputed amount. If an agreement is not reached within such thirty (30) day
period, the Parties will continue to try to resolve such dispute: provided,
however, that either Party may instead submit the dispute to resolution pursuant
to Article XI. If as a result of the dispute resolution a Party is required to
pay moneys to the other Party, then such moneys shall accrue interest at the
Default Rate as of the date originally due.
Section 5.16 Escalation. Each of the Operating Fee, Fired-Hour Fee, Handling
Fee, Spare Parts Fee and the fees for Directed Starts set forth in Section 5.10
shall be increased annually. For each Operating Year after the first Operating
Year, the escalated fee shall be equal to the product of (i) the ratio of the
Consumer Price Index in effect as of January 1st of the preceding Operating Year
over such index for the next preceding January 1st, and (ii) the fee for the
then-expiring Operating Year.
-28-
ARTICLE VI -TERM
Section 6.01 Term.
(a) GE shall Operate and Maintain the Facility beginning on the
Commencement Date and continuing until April 1, 2008, unless such
date is extended or this Agreement is terminated as provided herein
(the period of time during which GE is so obligated to Operate and
Maintain the Facility being referred to herein as the "Term"),
provided however, subject to Sections 7.01(c), 7.03 and 7.05, GE's
-------- -------
obligation to Repair and Overhaul each Gas Turbine Package shall
continue until the completion of the next major overhaul thereof
following April 1, 2008 and POA's obligation to pay the Fired-Hour Fee
with respect to each Gas Turbine Package shall continue until the
completion of each such respective major overhaul.
(b) Notwithstanding the foregoing, in the event a major overhaul of a Gas
Turbine Package is completed on or after June 30, 2005, at POA's
option, POA may terminate payment of the Fired Hour Fee with respect
to such Gas Turbine Package upon the completion of such major
overhaul, and in such event, GE's obligation to Repair and Overhaul
such Gas Turbine Package shall terminate upon the completion of such
major overhaul.
Section 6.02 Renewal. POA may extend the Term for up to eight (8) additional
consecutive years by providing notice of such extension to GE at any time prior
to January 1, 2008.
Section 6.03 Facility Condition at End of Term.
(a) GE shall leave the Facility, or cause the Facility to be left at the
end of the Term, in the same condition as on July 1, 1992, normal wear
and tear and any other degradation for which GE is not responsible
excepted. All Consumables and Parts and Tools for which POA has paid
shall be left at the Facility. All Consumables, Parts and Tools,
operating and maintenance manuals, files, programs, texts, procedures
and any other items furnished as a Reimbursable Expense will be left
at the Facility and will become or remain, subject to Article III, the
property of POA without additional charge. POA also shall have the
right, but not the obligation, in its sole discretion, to directly
assume and become liable for any contracts or obligations that GE may
have undertaken with third parties in connection with the Operation
and Maintenance of the Facility by GE. GE shall execute all documents
and take all other reasonable steps requested by POA that may be
required to assign to and vest in POA, and POA shall execute all
documents and take all other reasonable steps requested by GE that may
be required to release GE from all rights, benefits, interests and
title in connection with such contracts or obligations.
(b) Upon the expiration or other termination of this Agreement, GE shall,
without charge or cost to POA, transfer to POA and leave at or deliver
to the Site a supply of Spare Parts which would reasonably be required
thereafter in connection with the operation and maintenance of POA's
cogeneration facility
-29-
having a then fair market value of not less than $250,000,
escalated from June 1992 to the date of such expiration or
termination in accordance with the change over such period in the
Consumer Price Index.
Section 6.04 Liabilities Accrued as of the End of Term. Liabilities or
obligations of the Parties which have accrued on or prior to any termination or
expiration of this Agreement shall not be affected thereby, and this Agreement
shall remain in effect, notwithstanding such termination or expiration, to the
extent required to enable each Party to enforce its rights hereunder.
ARTICLE VII - EVENTS OF DEFAULT AND TERMINATION
Section 7.01 GE Events of Default.
(a) Any one or more of the following events shall constitute a GE Event of
Default hereunder:
(i) The failure of GE to pay any amount due POA hereunder for
thirty (30) days after written notice specifying the amount to
be paid, or a failure by GE to substantially perform any of its
material obligations under this Agreement which failure
continues for thirty (30) days after written notice from POA
specifying (A) in detail the default complained of, and (B)
that such notice is a notice of default pursuant to this
Section 7.01; provided, however, that if the default is curable
but impracticable to cure within thirty (30) days, as long as
GE shall commence and diligently prosecute the curing of the
default to completion, GE shall have such period of time as
reasonably necessary to cure the default, but in no event more
than one hundred twenty (120) days from the date notice of
default shall have been given by POA.
(ii) GE files a voluntary petition in bankruptcy or is adjudicated a
bankrupt or insolvent, or files any petition or answer seeking
any reorganization, arrangement, composition, readjustment,
liquidation, dissolution or similar relief under the present or
future Federal, state or other bankruptcy or insolvency statute
or law, or seeks, consents to or acquiesces in the appointment
of any bankruptcy or insolvency trustee, receiver or liquidator
of GE or of all or any substantial part of its properties.
(iii) The commencement of any action, case or proceeding against GE
seeking (A) any reorganization, arrangement, composition,
readjustment, liquidation, dissolution or similar relief under
any insolvency laws, or (B) the appointment, without the
consent or acquiescence of GE, of any trustee, receiver or
liquidator of GE or of all or substantially all of its
properties, which proceeding or appointment shall continue
unstayed for a period of sixty (60) days.
(iv) Except to the extent caused by Force Majeure, Utility
interruption, or POA direction, in any Operating Year On-Peak
Capacity Factor is less than
-30-
88% or Off-Peak Capacity Factor is less than 88%. On-Peak
Capacity Factor and Off-Peak Capacity Factor shall be
fractions, expressed as percentages, the numerators of which
shall be the number of kwhrs actually generated by the Facility
during the respective Operating Year during On-Peak Hours and
Off-Peak Hours, respectively, excluding kwhrs generated during
ramp-up and ramp-down periods within the limitations thereof
set forth in the POA Operations and Maintenance Procedures
Manual, and the denominator of which shall be the number of
kwhrs the Facility would have generated during such Operating
Year during On-Peak Hours and Off-Peak Hours, respectively, if
the Facility had operated during all hours (excluding hours
included in ramp-up and ramp-down periods within the
limitations thereof set forth in the POA Operations and
Maintenance Procedures Manual) when operation was requested by
POA, at the output level specified by POA (within the
limitations of the cogeneration facility). On Peak Hours and
Off-Peak Hours shall be the hours defined as such in the PPA.
For purposes hereof, POA may not require operation of the
Facility during the times when maintenance or overhauls which
would preclude operation are scheduled to be performed in the
Annual Operating Plan or otherwise as agreed in writing between
GE and POA.
(v) Except to the extent caused by Force Majeure, the performance
of the Major System Repairs or resulting from excess POA vendor
costs under Section 2.14(e), the Reimbursable Expenses actually
paid by POA with respect to any Operating Year, net of any
insurance proceeds allocable to payment of such Reimbursable
Expenses which are received by POA or paid on behalf of POA,
exceed the amount budgeted therefore in the respective Annual
Budget, as changed from time to time pursuant to Section 4.06
hereof, by more than 10%.
(vi) GE fails to deliver steam from the Facility in accordance with
the Steam Agreement at the levels of production required by the
Steam User for a period of ten (10) consecutive days or a total
of thirty (30) days in any Operating Year.
(vii) GE takes any action, or fails to take any reasonable action,
which action or failure to act has a material adverse effect on
the status of the Facility as a QF.
(viii) GE incurs liabilities to POA hereunder in any Operating Year,
(net of any amounts recoverable under any policies of insurance
or from third parties as a result of the events which have
given rise to such liabilities) which, in the aggregate, are
equal to or exceed the maximum liability of GE under Section
10.02 hereof; provided, however, that such liabilities shall
not include any liabilities to the extent resulting from POA's
failure to perform any of its obligations hereunder.
-31-
(ix) GE takes any action, or fails to take any reasonable action,
and such action or failure to act results in the breach of any
Facility Agreement by POA.
(b) The Operating Fee shall remain payable with respect to any cure
periods applicable to any GE Event of Default, provided that during
such cure periods GE continues to substantially perform its
obligations hereunder, including actual operation, maintenance and
repair of the Facility, otherwise the Operating Fee shall not be
payable with respect to such cure periods.
(c) Upon the occurrence of any GE Event of Default and the failure of GE
to cure such GE Event of Default within the applicable cure period, if
any, POA may terminate this Agreement upon (5) five days written
notice to GE, Without prejudice to any claim for damages POA may have
against GE for GE's breach of this Agreement, or any other claim POA
may have against GE, GE shall remain liable to POA for all outstanding
amounts due to POA hereunder at the time of such termination. Upon the
termination of this Agreement pursuant to the previous, POA may take
possession of and utilize any materials, plant, tools, equipment and
property of any kind furnished by GE to the Facility (excluding (A)
the Spare Parts (B) any materials, plant, tools, equipment and
property furnished under the Leased Engine Program, and (C) any
materials, plant, tools, equipment and property furnished pursuant to
GE's performance of its obligations under Section 7.05) and necessary
to operate, maintain or repair the Facility. GE shall be and shall
remain liable for (i) the amount by which the sum of all reasonable
costs incurred by POA in performing the obligations of GE hereunder
exceed the amounts which would have been payable to GE hereunder, and
(ii) all actual losses, costs, claims and damages incurred by POA in
connection with GE's default (exclusive of any incidental or
consequential damages, for which GE shall not be liable); provided
however, that (x) the operation, maintenance and/or repair of the
Facility thereafter by or on behalf of POA is carried out in
accordance with the provisions of this Agreement to the extent such
provisions relate to such operation and/or maintenance and/or repair
and (y) the maximum liability of GE shall not exceed the amount set
forth in Section 10.02.
(d) Notwithstanding the foregoing, at POA's option, GE shall continue to
operate and maintain the Facility after a termination of this
Agreement as a result of an GE Event of Default for such period of
time (the "Transition Period") as POA may direct, up to 180 days,
according to the terms of this Agreement.
Section 7.02 POA Events of Default.
(a) Any one or more of the following events shall constitute a POA Event
of Default hereunder:
(i) The failure of POA to pay any amount due to GE hereunder which
failure continues for thirty (30) days after written notice
from GE specifying (A) the amount required to be paid, and (B)
that such notice is a notice of default pursuant to this
Section 7.02. Notwithstanding the foregoing,
-32-
interest on any past due amounts shall accrue beginning on the
day after the original date such amount was due;
(ii) If POA fails to substantially perform any of its material
obligations under this Agreement (other than the obligation to
make any payment due hereunder) which failure continues for
thirty (30) days after written notice from GE specifying (A) in
detail the default complained of, and (B) that such notice is a
notice of default pursuant to this Section 7.02; provided,
however, that if the default is curable but impracticable to
cure within thirty (30) days, as long as POA shall commence and
diligently prosecute the curing of the default to completion,
POA shall have such period of time reasonably necessary to cure
the default not to exceed one hundred twenty (120) days from
the date notice of default shall have been given by GE;
(iii) POA files a voluntary petition in bankruptcy or shall be
adjudicated a bankrupt or insolvent, or shall file any petition
or answer seeking any reorganization, arrangement, composition,
readjustment, liquidation, dissolution or similar relief under
the present or future Federal, state or other bankruptcy or
insolvency statute or law, or seeks, consents to or acquiesces
in the appointment of any bankruptcy or insolvency trustee,
receiver or liquidator of POA or of all or any substantial part
of its properties; or
(iv) The commencement of any action, case or proceeding against POA
seeking (A) any reorganization, arrangement, composition,
readjustment, liquidation, dissolution or similar relief under
any insolvency laws, or (B) the appointment, without the
consent or acquiescence of POA, of any trustee, receiver or
liquidator of POA of all or substantially all of its
properties, which proceeding or appointment shall continue
unstayed for a period of sixty (60) days.
(b) Upon the occurrence of a POA Event of Default, GE may, by written
notice to POA, terminate this Agreement immediately with respect to a
POA Event of Default pursuant to Section 7.02(a)(i) hereof, and with
respect to any other POA Event of Default, as of a date set forth in
such notice which shall be not less than thirty (30) days from the
date of such notice. Without prejudice to any claim for damages GE may
have against POA for POA's breach of this Agreement, or any other
claim GE may have against POA, POA shall remain liable to GE for all
outstanding amounts due to GE hereunder at the time of such
termination.
Section 7.03 Notice of Termination. POA may terminate this Agreement at any
time in its sole discretion, provided however, that upon such termination, POA
shall pay GE a fee (the "Termination Fee") equal to the applicable sum or pro-
rated annual portion thereof set forth on the attached Schedule 4. POA and GE
agree that the sums set forth in Schedule 4 represent reasonable compensation to
GE for POA's termination of this Agreement.
Section 7.04 Force Majeure. In the event of the occurrence of a Force Majeure
which results in (i) the total interruption of operation of the cogeneration
facility, (ii) the reduction of electric
-33-
output of the cogeneration facility by 20 MW or more, (iii) an increase in the
heat rate of the cogeneration facility by 25% or more, in any case for a
continuous period of one hundred eighty (180) days or more, without limiting its
rights hereunder, POA shall have the option, exercisable on thirty (30) days
advance written notice to GE, to suspend operation of the Facility and suspend
performance by both Parties of this Agreement for the duration of such Force
Majeure, during which suspension, GE shall have no continuing obligations with
respect to the Facility, and POA shall have no payment or other obligation to
GE. Periods during which POA requests that the cogeneration facility not be
operated shall not be excluded from periods during which any condition specified
in clause (i), (ii) or (iii) exists for purposes of determining the duration and
continuity of such condition under the preceding sentence. In the event of any
such suspension, GE shall promptly take such actions as are reasonably necessary
to secure the Facility from deterioration for the duration of such Force
Majeure, the parties shall pay to each other within fifteen (15) days after the
effective date of such suspension any sums due pursuant to the other provisions
of this Agreement, and, within fifteen (15) days after receipt of a properly
documented invoice therefor, POA shall pay to GE GE's accountable costs of
suspending operation of and securing the Facility, including reasonable employee
relocation and/or severance arrangements and other demobilization costs. POA
shall give GE thirty (30) days advance written notice of POA's intention to lift
any suspension of the Parties' obligations pursuant to this Section 7.04.
Section 7.05 Repair and Overhaul Obligations after Termination.
Notwithstanding the provisions of Section 7.01 and 7.03, in the event POA
terminates this Agreement pursuant thereto (i) GE shall remain obligated to
Repair and Overhaul, in accordance with the terms of this Agreement otherwise
applicable thereto, each Gas Turbine Package through the completion of its next
major overhaul after the effective date of such termination, and (ii) POA shall
remain obligated to pay the Fired Hour Fee for each Gas Turbine Package through
the completion of its next major overhaul after the effective date of such
termination.
ARTICLE VIII - INSURANCE
Section 8.01 Coordination of Insurance. POA and GE shall obtain and maintain
in effect insurance coverages of the types, in the amounts, with the deductibles
and as otherwise provided in Exhibit E.
Section 8.02 Certificates; Proof of Loss. On or before the date or dates on
which insurance coverages are required to become effective hereunder, each Party
shall furnish certificates of insurance to the other Party evidencing the
insurance coverage required of such Party pursuant to this Agreement. The Party
maintaining each insurance policy hereunder shall make all proofs of loss under
each such policy and shall take all other action reasonably required to ensure
collection from insurers for any loss covered under any such policy.
Section 8.03 No Limitation on Liability. Neither the requirement to provide
nor the provision of any insurance coverage hereunder shall limit the liability
of either Party to the other Party under this Agreement.
-34-
ARTICLE IX - INDEMNIFICATION
Section 9.01 By GE. To the maximum extent permitted by law and subject to the
limitations set forth in Article X, GE shall indemnify, defend and hold harmless
POA and its partners, shareholders, officers, directors, employees,
representatives and agents (the "POA Indemnified Parties"), from and against any
and all suits, actions, liabilities, legal proceedings, claims, demands, losses,
costs and expenses of every kind and character whatsoever, including without
limitation, reasonable attorneys' fees and expenses, for injury to or death of
third parties or loss or damage to property of third parties to the extent
arising out of or in connection with (i) any failure on the part of GE to
perform its obligations under this Agreement or (ii) any negligent acts or
omissions, willful misconduct or violations of Steam User's safety procedures by
GE, its employees, agents, representatives or independent contractors or any
other person acting for or on behalf of GE (other than a POA Indemnified Party).
It is understood and agreed by the Parties that any costs or expenses incurred
by GE pursuant to its indemnity obligations under this Section 9.01, including
without limitation, the cost of deductibles with respect to the insurance
maintained by GE or POA pursuant to Article VIII, shall not constitute
Reimbursable Expenses.
Section 9.02 By POA. To the maximum extent permitted by law, and subject to
the limitations set forth in Article X, POA shall indemnify, defend and hold
harmless GE, its shareholders, officers, directors, employees, agents and
representatives (the "GE Indemnified Parties"), from and against any and all
suits, actions, liabilities, legal proceedings, claims, demands, loses, costs
and expenses of every kind or character whatsoever, including without
limitation, reasonable attorneys' fees and expenses for injury to or death of
third parties or loss or damage to property of third parties to the extent
arising out of or in connection with (i) any failure on the part of POA to
perform its obligations under this Agreement or (ii) any negligent acts or
omissions or willful misconduct of POA or anyone acting on POA's behalf (other
than an GE Indemnified Party) or (iii) except to the extent arising out of any
failure of GE to properly handle and arrange for the disposal of hazardous
substances by independent third party contractors as provided in Section 2.23
any liability arising in connection with the transportation and disposal of
hazardous substances.
ARTICLE X - LIABILITIES OF THE PARTIES
Section 10.01 No Consequential Damages. (a) Notwithstanding any provision
contained in this Agreement to the contrary, neither Party nor its partners,
shareholders, officers, directors, principals, agents, subcontractors, vendors,
employees or its Affiliates shall be liable to the other Party hereunder for
consequential, incidental, special or indirect loss or damage, including without
limitation, cost of capital, loss of goodwill, loss of revenue or cost of
replacement power. The Parties further agree that the waivers and the
disclaimers of liability, indemnities, releases from liability and limitations
on liability expressed in this Agreement shall survive the termination or
expiration and shall apply (unless otherwise expressly indicated), whether in
contract, equity, tort or otherwise, even in the event of the fault, negligence
(including without limitation, the sole negligence), strict liability or breach
of warranty of the Party indemnified, released or whose liabilities are limited,
and shall extend to the officers, directors, principals, partners, agents,
subcontractors, vendors, employees or Affiliates of such Party.
-35-
(b) Neither the cost of repairing or replacing the Facility or any part
thereof, or any Equipment or any parts thereof, which are damaged due to the
negligence or willful misconduct of GE or any failure of GE to perform its
obligations hereunder, nor fines or penalties imposed on POA as a result of the
failure of the Facility or the operation thereof, or of POA, to conform to or
comply with any environmental permit or operating permit requirements due to the
negligence or willful misconduct of GE shall be deemed to be consequential,
incidental, special or indirect damage.
Section 10.02 Limitation of Liabilities. Notwithstanding any provision
contained in this Agreement to the contrary, for any Operating Year, GE shall
not be liable to POA (whether by contract, warranty, tort or otherwise) for any
amount that exceeds the amount of the Operating Fee for the Operating Year in
which the claim is made. If a claim(s) is made after the end of the Term, then
the claim(s) shall be deemed to have been made in the last Operating Year of the
Term.
ARTICLE XI - DISPUTE RESOLUTION
Section 11.01 Arbitration. If there is a dispute arising under, out of or in
connection with the making, performance or execution of this Agreement, then the
dispute shall be submitted to the American Arbitration Association in New York,
New York for arbitration. Any such arbitration shall be conducted in accordance
with the principles set forth in this Article XI and the rules of the American
Arbitration Association.
Section 11.02 Demand for Arbitration. Upon written demand of either Party, the
Parties shall meet and attempt to appoint a single arbitrator. If the Parties
are unable to agree on a single arbitrator, or if one of the Parties fails to
meet within ten (10) days of a written demand being forwarded, then either Party
may apply to have the arbitrator appointed by the American Arbitration
Association.
Section 11.03 Qualifications. The arbitrator selected to act hereunder shall be
qualified by education or training to pass upon the particular question or
questions in dispute. No arbitrator shall be an officer, director, employee,
agent or consultant of either Party or any of its respective Affiliates.
Section 11.04 Decisions Final. The decision of the arbitrator shall be in
writing and signed by the arbitrator and shall be final and binding upon the
Parties as to any question or questions so submitted to arbitration and the
Parties shall be bound by such decision and perform the terms and conditions
thereof.
Section 11.05 Compensation of Arbitrator. The compensation and expenses of the
arbitrator (unless determined by the arbitrator to be payable by the non-
prevailing Party or in some other manner) shall be paid in equal proportions by
GE and POA.
Section 11.06 Performance to Continue. All performance required by either Party
under this Agreement shall continue during arbitration proceedings.
Section 11.07 Agreement Controlling. In all respects not provided for elsewhere
in this Article XI, the rules of the American Arbitration Association shall
govern any dispute hereunder
-36-
submitted to arbitration. If there is a conflict between the provisions of this
Agreement and such rules, the provisions of this Agreement shall prevail.
ARTICLE XII - CONFIDENTIALITY
Section 12.01 Nondisclosure. Neither Party shall disclose to third parties any
information regarding the business affairs, finances, technology or processes
received from the other Party pursuant to or in connection with this Agreement
or the Facility Agreements without the express written consent of the other
Party. This restriction shall not apply to information that (i) was already in
the possession of the receiving Party prior to receipt from the disclosing
Party, (ii) now or hereafter becomes a part of the public domain through no
fault of the receiving Party, (iii) corresponds in substance to information
heretofore or hereafter furnished by third Parties without restriction on
disclosure or (iv) with respect to any disclosure by POA, any information which
is or becomes the property of POA pursuant to this Agreement. Each Party will
release, indemnify and hold harmless the other Party from any and all liability
arising from its improper use or dissemination of confidential or proprietary
information protected hereunder.
Section 12.02 Permitted Disclosure. Any Party required by law to disclose
information that is otherwise required to be maintained in confidence pursuant
to Section 12.01, or where disclosure is required in connection with the
assertion of any claim or defense in judicial or administrative proceedings
involving a Party, may make disclosure notwithstanding the provisions of Section
12.01; provided, however, that the Party making the disclosure shall immediately
notify the other Party of the requirement and the terms thereof prior to the
submission and shall cooperate to the maximum extent practicable to minimize the
disclosure of the information. The Party disclosing such information shall use
its reasonable efforts to obtain proprietary or confidential treatment of such
information by the third party to whom the information is disclosed, and will,
to the extent such remedies are available, seek protective orders limiting the
dissemination and use of the information. This Agreement does not alter the
rights of either Party to challenge any law requiring the disclosure.
Section 12.03 Term. The confidentiality obligation of the Parties pursuant to
Section 12.01 shall remain in full force and effect for a period of five (5)
years after the date of the expiration or termination of this Agreement.
ARTICLE XIII -TITLE, DOCUMENTS AND DATA
Section 13.01 Materials and Equipment. Title to all Consumables, Parts and
Tools and other items purchased or obtained by GE, the cost of which is a
Reimbursable Expense, shall pass and vest in POA upon payment or reimbursement
of the cost thereof by POA to GE; provided, however, that such transfer of title
shall in no way affect GE's obligations as set forth in the other provisions of
this Agreement. GE shall execute and deliver such bills of sale and other
documents reasonably requested by POA to effect and confirm transfer of title to
Consumables, Parts and Tools and such other items as provided hereby.
Section 13.02 Documents. Except for the materials and documents listed in
Schedule 2, GE shall grant POA a royalty-free license to use at the Facility all
materials and documents prepared or developed by or on behalf of GE in
connection with the Facility or the performance of the Services, including
without limitation, all manuals, data, designs, drawings, plans,
-37-
computer software, specifications, reports and accounts, and for which GE has
been compensated. All such materials and documents, together with any materials
and documents furnished by POA to GE or to its employees, representatives,
agents or contractors, shall be delivered to POA upon expiration or termination
of this Agreement and before final payment is made to GE. In addition, all such
materials and documents shall be available for review by POA at all reasonable
times during development of, and promptly upon completion of, such materials and
documents. All such materials and documents required to be submitted for the
approval of POA shall be prepared and processed in accordance with the
requirements and specifications set forth in the Administrative Procedures
Manual. However, POA's approval of materials and documents submitted by GE shall
not relieve GE of its responsibility for the correctness thereof or of its
obligation to meet all the requirements of this Agreement.
Section 13.03 Proprietary Information. Where materials or documents prepared or
developed by GE or its employees, agents, representatives or contractors contain
proprietary information, systems, techniques or know-how previously known to GE
or its employees, agents, representatives or contractors or previously acquired
by GE or its contractors from third Parties, GE or its employees, agents,
representatives or contractors shall have the unrestricted right to use or
dispose of such information, systems, techniques or know-how as they see fit.
However, where such information, systems, techniques or know-how are
specifically developed, created or acquired by GE or its employees, agents,
representatives or contractors in the performance of the Services at the
Facility, then GE and its employees, agents, representatives or contractors
shall have the right to use in the performance of the Services, but not to
disclose to others, such information, systems, techniques or know-how, unless
approved by POA in writing, while POA shall have the unrestricted right to use
and disclose to others any and all such information, systems, techniques and
know-how. GE agrees that it shall take all reasonable steps in order that its
employees, representatives, agents and contractors adhere to the provisions of
this Article XIII. Appropriate clauses to carry out the purpose and intent of
this Article XIII shall be included in all contracts and agreements entered into
by GE in connection with the performance of this Agreement.
ARTICLE XIV - MISCELLANEOUS PROVISIONS
Section 14.01 Assignment. Except as set forth below, no assignment of this
Agreement by either Party may be made without the prior written approval of the
other Xxxxx; provided, however, that this Agreement may be assigned by POA
without the consent of GE in connection with any financing or refinancing of the
Facility. Any assignment that does not comply with the provisions of this
Section 14.01 shall be null and void.
Section 14.02 Cooperation in Financing. GE will, at POA's request, execute and
deliver such consents, assignments, memoranda and other instruments as POA may
reasonably require in connection with any financing or refinancing of the
Facility on a project finance sale/leaseback basis, including without
limitation, instruments to ensure that the Facility and its components are not
subject to the interests of GE's creditors and to otherwise enable POA to create
and perfect security interests in the Facility and this Agreement.
Section 14.03 Access. For purposes of inspection and review, POA and its
respective representatives at all reasonable times shall have access to the
Facility, all Facility operation and documents, materials, records and accounts
relating to the operation, maintenance and repair of the Facility including
Overhaul of the Gas Turbine Packages other than GE's personnel
-38-
files and accounting information related solely to GE's financial condition or
transactions which do not affect the amount of Reimbursable Expenses. During any
such inspection or review of the Facility, POA and its invitees and
representatives shall comply with all of GE's safety and security procedures,
and POA and its respective representatives shall conduct such inspection and
reviews in such a manner as to cause minimum interference with GE's activities.
GE also shall cooperate with POA in allowing other visitors access to the
Facility under conditions mutually agreeable to the Parties.
Section 14.04 Independent Contractor. Except as otherwise expressly set forth
in this Agreement, GE shall be an independent contractor with respect to the
performance of this Agreement. Neither GE nor its employees, agents,
subcontractors, vendors or suppliers or the employees of any such parties
employed in the Operation and Maintenance of the Facility shall be deemed to be
agents, representatives, employees or servants of POA, except to the extent of
any express agency created hereunder pursuant to the authority granted to GE
under Article II. Except as otherwise expressly provided herein, this Agreement
shall not constitute GE as the legal representative or agent of POA, nor shall
GE have the right or authority to assume, create or incur any liability or
obligation, express or implied, against, in the name of or on behalf of POA.
This Agreement is not intended to create, and shall not be construed to create a
relationship of partnership or an association for profit between POA and GE.
Section 14.05 Not for Benefit of Third Parties. Except as otherwise expressly
provided herein, this Agreement and each and every provision is for the
exclusive benefit of the Parties hereto and is not for the benefit of any third
party.
Section 14.06 Force Majeure. In the event that a Party is rendered unable, by
reason of an event of Force Majeure, to perform, wholly or in part, any
obligation or commitment set forth in this Agreement, then, provided such Party
gives prompt written notice describing the particulars of such event, including
the nature of the occurrence and its expected duration, and continues to furnish
daily reports with respect thereto during the period of the Force Majeure, the
obligations of such Party shall be suspended to the extent and for the period
such Party is rendered unable to perform such obligations by such Force Majeure
condition; provided, however, that (i) the suspension of such obligations shall
be of no greater scope and of no longer duration than is required by the Force
Majeure and (ii) the Party whose performance is being excused shall use its
reasonable efforts to perform its obligations hereunder and use its reasonable
efforts to remedy its inability to perform. The Force Majeure event will not
excuse either Party from making payments to the other Party. If a Force Majeure
continues for more than six (6) consecutive months, either Party may terminate
this Agreement, upon one hundred eighty (180) days' prior written notice,
provided such notice may not be given prior to the end of such six (6) month
period.
Section 14.07 Amendments. Neither this Agreement nor any of the terms may be
terminated, amended, supplemented, waived or modified orally, but only by an
instrument in writing signed by the Party against which the enforcement of the
termination, amendment, supplement, waiver or modification is sought.
Section 14.08 Survival. Notwithstanding any provisions contained herein to the
contrary, the indemnity obligations set forth in Article IX, the limitations on
liabilities set forth in Article X, the dispute resolution provisions set forth
in Article XI and the confidentiality obligations set forth in Article XII shall
survive in full force the expiration or termination of this Agreement.
-39-
Section 14.09 No Waiver. It is understood and agreed that any delay, waiver or
omission by a Party to exercise any right or power arising from any breach or
default by the other Party with respect to any of the terms, provisions or
covenants of this Agreement shall not be construed to be a waiver by the non-
defaulting Party of any subsequent breach or default of the same or other terms,
provisions or covenants on the part of the defaulting Party.
Section 14.10 Notices. Any notice, demand, offer or other written instrument
required or permitted to be given pursuant to this Agreement shall be in writing
signed by the Party giving such notice and shall be hand delivered or sent by
overnight courier, registered mail or telefax to the other Party at the address
for such Party set forth below.
If delivered to POA:
Project Orange Associates, L.P.
c/o GPU International, Inc.
Xxx Xxxxx Xxxx Xxxx
Xxxxxxxxxx, XX 00000
Attention:
Vice President - Business Management
Telephone: (000) 000-0000
Telefacsimile: (000) 000-0000
with copies to:
Manager of Operations
(Address same as above)
and
Business Manager
(Address same as above)
If delivered to GE:
GE Energy Plant Operations, Inc.
0000 Xxxxx Xxxx Xxxx
Xxxxxxx, Xxxxxxx 00000
Attention: General Manager of Operations
Telephone: (000) 000-0000
Telefacsimile: (000) 000-0000
with a copy to:
Division Counsel
(Address same as above)
-40-
Each Party shall have the right to change the place to which notice shall be
sent or delivered by similar notice sent in like manner to the other Party.
Without limiting any other means by which a Party may be able to prove that a
notice has been received by the other Party, a notice shall be deemed to be duly
received:
(a) if sent by hand, the date when left with a responsible persons at the
address of the recipient;
(b) if sent by registered mail or overnight courier, the date of delivery
to the address specified herein; or
(c) if sent by facsimile, upon receipt by the sender of an acknowledgment
or transmission report generated by the machine from which the
facsimile was sent indicating that the facsimile was sent in its
entirety to the recipient's facsimile number specified herein.
Section 14.11 Representations and Warranties. Each Party represents and
warrants to the other Party that: (i) such Party has the full power and
authority to execute, deliver and perform its obligations under this Agreement
and to carry out the transactions contemplated hereby; (ii) the execution and
delivery of this Agreement by such Party and the carrying out by such Party of
the transactions contemplated hereby have been duly authorized by all requisite
corporate action or partnership action, as the case may be, and this Agreement
has been duly executed and delivered by such Party and constitutes the legal,
valid and binding obligation of such Party, enforceable against it in accordance
with its term, subject, to limitations imposed by bankruptcy, insolvency,
reorganization, moratorium or other similar laws relating to or affecting the
enforcement of creditors' rights generally and to general principles of equity;
(iii) no authorization, consent, approval or order of, notice to or
registration, qualification, declaration or filing with any governmental
authority is required for the execution, delivery and performance by such Party
of this Agreement or the carrying out by such Party of the transactions
contemplated hereby, other than regulatory and similar approvals needed with
respect to the operation of the Facility; and (iv) none of the execution,
delivery and performance by such Party of this Agreement, the compliance with
the terms and provisions, and the carrying out of the transactions contemplated
hereby, conflict with or result in a breach or violation of any of the terms,
conditions or provisions of any law in existence on the date or the charter
documents or partnership agreement, as amended, or by-laws, as amended, of such
Party in existence on the date, or any applicable order, writ, injunction,
judgment or decree of any court or administrative or regulatory agency or body
against such Party or by which it or any of its properties is bound, or any loan
agreement, indenture, mortgage, bond, note, resolution, contract or other
agreement or instrument to which such Party is a party or by which it or any of
its properties is bound or constitutes a default thereunder or will result in
the imposition of any lien, mortgage or other encumbrance upon any of its
properties.
Section 14.12 Counterparts. The Parties may execute this Agreement in two (2)
or more counterparts, all of which taken together shall constitute one and the
same instrument and each of which shall be deemed an original instrument as
against any Party who has signed it.
Section 14.13 Governing Law. This Agreement shall be governed by and enforced
in accordance with the laws of the State of New York, except the conflict of
laws principles thereof.
-41-
Section 14.14 Partial Invalidity. If any provision of this Agreement becomes or
is declared by a court of competent jurisdiction to be illegal, unenforceable or
void, this Agreement shall continue in full force and effect without said
provision; provided, however, that if such severability materially changes the
economic benefits of this Agreement to either Party, the Parties shall negotiate
in good faith an equitable adjustment in the provisions of this Agreement.
Section 14.15 Captions, Exhibits and the Table of Contents. Titles or captions
of Sections contained in this Agreement are inserted only as a matter of
convenience and for reference, and in no way define, limit, extend, describe or
otherwise affect the scope or meaning of this Agreement or the intent of any
provision. All Exhibits attached hereto shall be considered a part of this
Agreement as though fully set forth herein.
Section 14.16 Entire Agreement. This Agreement sets forth the full and complete
understanding of the Parties relating to the subject matter herein, and
supersedes any and all negotiations, agreements and representations made or
dated prior thereto.
Section 14.17 Conflicting Provisions. In the event of any conflict between this
document and any Exhibit hereto, the terms and provisions of this document, as
amended from time to time, shall control. In the event of any conflict among the
Exhibits, the Exhibit of latest date shall control.
Section 14.18 Successors and Assigns. The terms and provisions of this
Agreement and the respective rights and obligations hereunder of GE and POA
shall be binding upon, and inure to the benefit of, their respective successors
and permitted assigns.
Section 14.19 Opinion of Counsel. At the request and expense of POA, GE shall
provide to POA an opinion of GE's counsel in appropriate form as to the
representations and warranties made by GE in Section 14.11.
Section 14.20 Performance During Legal Proceedings. All performance required by
either Party under this Agreement shall continue during any legal proceedings.
Section 14.21 Joint Effort. Preparation of this Agreement has been a joint
effort of the Parties and the resulting document shall not be construed more
severely against one of the Parties than against the other.
SECTION 14.22 DISCLAIMER OF WARRANTIES. EXCEPT FOR WARRANTIES EXPRESSED HEREIN,
GE HEREBY DISCLAIMS ALL WARRANTIES OF ANY KIND, WHETHER STATUTORY, ORAL,
WRITTEN, EXPRESS OR IMPLIED, INCLUDING ALL IMPLIED WARRANTIES OF MERCHANTABILITY
AND FITNESS FOR A PARTICULAR PURPOSE, AND ALL WARRANTIES ARISING FROM COURSE OF
DEALING OR USAGE OF TRADE.
Section 14.23 Standard of Reasonableness. Except as expressly stated to be
within the sole discretion of any Party, all consents or approvals required of
either Party shall not be unreasonably withheld or delayed.
-42-
ARTICLE XV -MAINTENANCE OF INVENTORY OF
CONSUMABLES AND PARTS AND TOOLS
Section 15.01 Maintenance of Inventory of Consumables and Parts and Tools.
(a) On and after the date hereof, and continuing until the Commencement
Date, GE shall keep and maintain at the Facility site an inventory of
Consumables and Parts and Tools which is consistent with the inventory
of such Consumables and Parts and Tools which GE has maintained at the
Site while operating, maintaining and repairing the Facility pursuant
to the Prior Agreement. GE shall also keep all personal property
(other than the Spare Parts) at the Site which GE owns and has used
solely in connection with operating, maintaining and repairing the
Facility pursuant to the Prior Agreement.
(b) Title to all Consumables, Parts and Tools and all other personal
property located at the Site on the date hereof (other than the Spare
Parts) for use in connection with the operation, maintenance and
repair of the Facility under the Prior Agreement or this Agreement, to
the extent not previously transferred to POA, shall become vested in
POA as of the Commencement Date at no charge or cost to POA. GE shall
execute and deliver such bills of sale and other documentation
reasonably requested by POA to effect such transfer of title.
-43-
IN WITNESS WHEREOF, the Parties have executed this Cogeneration Facility
Operation and Maintenance Agreement through their duly authorized officers or
representatives as of the date first above written.
PROJECT ORANGE ASSOCIATES, L.P.
By: NCP Syracuse, Inc., Managing General Partner
By: NCP Energy, Inc., Attorney-in-Fact
By: /s/ Xxxx Xxxxxxxx
---------------------------------------
Name: Xxxx Xxxxxxxx
Title: Vice President
GE ENERGY PLANT OPERATIONS, INC.
By: /s/ Xxxxx Xxxxx
---------------------------------------
Name: Xxxxx Xxxxx
Title: General Manager of Operations
-44-
EXHIBIT A-I
MINIMUM REPAIR AND MAINTENANCE REQUIREMENTS
FOR THE EXISTING PLANT
Including but not limited to:
Hourly:
------
Walk through inspection of entire plant every hour and log readings every
three hours per Schedule I
Daily:
-----
Test makeup, condensate, and feedwater for chemical and other readings
required per Schedules 2 and 3 and adjust as needed. Test more often if
necessary.
Monthly:
-------
Inspect, add water, clean and charge switchgear storage batteries for
proper gravity level.
Check all chemical inventories.
Grease governor bearings on 1,000 K.W. turbine generator.
Quarterly:
---------
Have steam purity test performed by independent laboratory.
Yearly:
------
Inspect boilers according to New York State boiler code regulations and
standards and correct all deficiencies resulting from inspection.
Pack all valves, replace or repair any valves with problems.
Inspect, repair or replace all traps and strainers.
Clean, repair and grease all reducing valves. Replace if necessary.
Inspect and clean all safety valves, repair or replace as required.
Inspect 1,000 K.W. turbine generator, replace oil, clean and grease
couplings, bearings and replace any needed parts.
Inspect and clean all electrical breakers and switchgear.
Inspect two stacks, bricks, lighting rods and pointing, repair as
required.
-1-
EXHIBIT A- I, Continued
MINIMUM REPAIR AND MAINTENANCE REQUIREMENTS
FOR THE EXISTING PLANT
Inspect two main air compressors including dryers and filters and repair
as required. Air system shall be kept free of oil and water contamination.
Every Three Years:
-----------------
Have all switch relays tested and cleaned by manufacturer.
Every Five Years:
----------------
Perform internal structural inspection of two stacks and repair if
necessary.
Sonic test two oil tanks and three deareaters.
INSTRUMENTATION
---------------
Common Equipment. Both Plants:
-----------------------------
At least Yearly: Check all auxiliary transmitters, recorders and
integrators for calibration: house steam, treated water, condensate flow,
condensate temperature end feedwater temperature.
Xxxxx Plant:
-----------
Tests performed on 3 and 4 boilers, and their replacements, if any, in
late spring and summer.
Complete calibration check and repairs, parts replaced as needed on the
following:
(a) recorders and integrators
(b) pneumatic and electronic relays
(c) pneumatic and electronic selector stations
(d) draft and pressure gauges
(e) valve and control drive positioners
(f) pneumatic and electronic transmitters
(g) oxygen and combustible analyzers
Clean forced draft fans and inducted draft fans and make sure vanes and
associated linkage work freely.
-2-
EXHIBIT A- I, Continued
MINIMUM REPAIR AND MAINTENANCE REQUIREMENTS
FOR THE EXISTING PLANT
Loop check combustion, feedwater and boiler draft system. Check for
pneumatic leaks.
Run combustion tests on all boilers at least once a year.
Alto Plant:
----------
Tests performed on 6 and 7 boilers and their replacements, if any, in
winter and early spring.
Complete calibration check and repairs, parts replaced as needed on the
following:
(a) recorders and integrators
(b) pneumatic relays, pressure and combustion system
(c) pneumatic selector stations
(d) draft and pressure gauges
(e) valve and control drive positioners
(f) pneumatic and electronic transmitters, pressure, flow, and
temperature
(g) oxygen and combustion analyzer.
Clean forced draft and induced draft fans and make sure linkage is not
binding and moves freely.
Loop check combustion, feedwater and boiler draft system. Check for
pneumatic leaks.
Run combustion tests on all boilers at least once a year.
-3-
EXHIBIT A-2
MINIMUM OPERATING REQUIREMENTS FOR THE EXISTING PLANT
Modifications:
-------------
A 300 lb./hr. 100 psig steam coil will be installed in the mud drums of
each of the two Xxxxx boilers pursuant to the terms of the Construction
Contract. An attemperator will be provided, as required, to let down 300
psig steam to 100 psig.
Lay-Up Procedure - Alto Boilers:
-------------------------------
The following lay-up procedure is to be performed on each boiler one at a
time, and shall be followed for each boiler.
(a) All water walls are blown under pressure.
(b) Boiler is drained, opened, and inspected.
(c) System is purged and pressurized with dry nitrogen.
(d) Heat lamps are installed and operated to keep boiler walls warm and
refractories dry.
(e) System is monitored daily, checking for proper nitrogen pressure and
for proper operation of heat lamps.
(f) Annually, prior to the summer season, each Alto Boiler will be
operated in full temperature and pressure to ensure proper operation.
After successful testing steps (a) through (e) above will be
followed.
Standby Operation - Xxxxx Boilers
---------------------------------
(a) Approximately 300 lbs./hr of 100 psig steam will be circulated
continuously through the steam coils in the mud drum of each of the
Xxxxx boilers, maintaining 50 psig and 300 degrees F. in the drums.
(b) To prevent condensation and to drive off any moisture in the
refractory, pilots will be operated periodically as required to keep
the refractory dry.
(c) To avoid feeding cold water to the boiler, condensate from the steam
coils will be routed to the generators, maintaining the boiler feed
water above 150 degrees F.
(d) Once a day, the water chemistry will be checked and adjustments made
as necessary.
(e) To demonstrate the operability of the system, once a month each
boiler will be brought to operating temperature and pressure held for
three hours.
-4-
EXHIBIT B
MINIMUM PIPELINE MAINTENANCE REQUIREMENTS
Pipeline maintenance shall include, in addition to any other requirements
included in the Agreement, the following services:
. Labor, vehicle, and supervision to provide the daily monitoring and
maintenance activity over the entire route of the Pipeline.
. Services would be provided in accordance with New York State Public
Service Commission Rules And Regulations Part 255 GAS Utilities.
. Labor would be provided to perform the following:
(a) Conduct Pipeline patrolling.
(b) Maintain Right of Way 20 feet-wide (10 feet either side of the
Pipeline) as required.
(c) Monitor Pipeline pressure.
(d) Maintain/inspection of vegetative cover.
(e) Maintain marking as provided in Right of Way.
(f) Maintain access to valves.
(g) Update location of transmission valves.
(h) Contact and communication with local emergency, rescue, fire and
police within Pipeline jurisdiction.
(i) Report to Owner with respect to leaks and emergency service
performed.
(j) Assistance in event of emergency.
(k) Conduct and assist in electrical measurements and inspection of
cathodic protection system.
(l) Odorization of Pipeline - inspection and maintenance of daily
records of adequacy of odorization.
(m) Maintain daily log of activities performed.
(n) Provide assistance to others in locating Pipeline.
(0) Conduct gas detection survey of Pipeline with combustible gas
instruments.
(p) Right of Way brush removal.
-5-
EXHIBIT B, Continued
MINIMUM PIPELINE MAINTENANCE REQUIREMENTS
. Supervision would be provided by Operator for the following:
(a) Develop inspection plan.
(b) Update Owner of Right of Way maintenance.
(c) Provide record of emergency contacts.
(d) Supervise daily activities.
(e) Coordinate outside services.
(f) Direct contact with Owner.
(g) Annual leak Report summary.
. Operator will provide the following equipment as Operator deems
necessary as part of the above proposal:
(a) Four wheel drive vehicle (including fuel, maintenance and
insurance).
(b) Combustible gas instrument.
(c) Miscellaneous equipment (chain saw, shovels, xxxxx, toolbox,
gloves, hard hats, uniforms and small hand tools).
. Operator will provide the Mercaptan compound to be used as the
odorizer in the natural gas for purposes of leak detection.
. "Smart pigging" and cleaning of the pipeline shall be performed as
required, based on the operating history and prudent industry
practices.
-6-
EXHIBIT C
PROJECT ORANGE ORGANIZATION
---------------
Plant Manager
---------------
------------------------
Administrative Assistant
------------------------
-----------------------
Assistant Plant Manager
-----------------------
---------------------- ----------------
Maintenance Supervisor Pipeline Manager
---------------------- ----------------
---------------- ------------------- ----------------
I & E Technician I & E Technician Pipeline Manager
---------------- ------------------- ----------------
---------------- -------------------
Plant Mechanic Plant Mechanic
---------------- -------------------
---------------- -------------------
Plant Mechanic Mechanic Apprentice
---------------- -------------------
-------------------------------------------------------------------------
------------------ ------------------ ------------------ ------------------
Shift Supervisor Shift Supervisor Shift Supervisor Shift Supervisor
------------------ ------------------ ------------------ ------------------
---------------- ---------------- ---------------- ----------------
Plant Operator Plant Operator Plant Operator Plant Operator
---------------- ---------------- ---------------- ----------------
-7-
EXHIBIT D
BUDGET FOR FIRST OPERATING YEAR
----------------- -----------------------------------------------------------------------------
Nov-98 Dec-98 Jan-98 Feb-99 Mar-99 Apr-99 May-99 Jun-99 Jul-99 Aug-99
----------------- -----------------------------------------------------------------------------
Operations and Maintenance
------------------------------
GE Fees
-------
Operating Fee 29,167 29,167 29,167 29,167 29,167 29,167 29,167 29,167 29,167 29,167
Spare Parts Carrying Fee 4,167 4,167 4,167 4,167 4,167 4,167 4,167 4,167 4,167 4,167
Leased Engine Fee 25,000 25,000 25,000 25,000 25,000 25,000 25,000 25,000 25,000 25,000
Handling Fee 4,167 4,167 4,167 4,167 4,167 4,167 4,167 4,167 4,167 4,167
Gas Turbine Overhaul Fee 126,192 130,418 129,888 117,216 129,888 125,664 112,288 125,664 129,888 129,888
Directed Starts Fee 0 0 0 0 0 0 0 0 0 0
----------------- -----------------------------------------------------------------------------
Total GE Fees 185,692 192,916 192,388 179,716 192,388 188,164 174,788 188,164 192,388 192,388
Total Engine Hours On Line 1,434 1,482 1,476 1,332 1,476 1,428 1,276 1,428 1,476 1,476
x $88 per hour 88 88 88.0 88.0 88.0 88.0 88.0 88.0 88.0 88.0
----------------- -----------------------------------------------------------------------------
=Gas Turbine Overhaul Fee 126,192 130,416 129,888 117,216 129,888 125,664 112,288 125,664 129,888 129,888
Cumulative Directed Starts 14 14 16 18 20 22 26 28 30 32
Total Directed Starts * 56 @ $600 0 0 0 0 0 0 0 0 0 0
Total Directed Starts * 75 @ $1200 0 0 0 0 0 0 0 0 0 0
----------------- -----------------------------------------------------------------------------
Directed Starts Fee 0 0 0 0 0 0 0 0 0 0
Plant Personnel Compensation
----------------------------
Salaried Supervision 22,333 22,333 20,692 20,692 20,692 20,692 20,692 20,692 20,692 20,692
Hourly 66,642 66,642 58,350 58,350 58,350 58,350 58,350 58,350 58,350 58,350
Hourly Overtime 16,926 16,926 13,129 13,129 13,129 13,129 13,129 13,129 13,129 13,129
Fringe Benefits 42,045 42,045 35,840 35,840 35,840 35,840 35,840 35,840 35,840 35,840
Salaries G&A 10,105 10,105 12,544 12,544 12,544 12,544 12,544 12,544 12,544 12,544
----------------- -----------------------------------------------------------------------------
Total Plant Personnel Comp 158,051 158,051 140,555 140,555 140,555 140,555 140,555 140,555 140,555 140,555
Plant Operating Expense
-----------------------
Plant Upkeep 751 750 1,286 1,286 1,286 1,286 1,286 1,286 1,286 1,286
Emmission Testing 4,000 0 3,269 3,269 3,269 3,269 3,269 3,269 3,269 3,269
Water Treatment 23,540 24,040 21,053 21,053 21,053 21,053 21,053 21,053 21,053 21,053
Consumables/lub/filler 1,989 1,989 1,354 1,354 1,354 1,354 1,354 1,354 1,354 1,354
----------------- -----------------------------------------------------------------------------
Total Plant Operating Expense 30,280 26,779 26,962 26,962 26,962 26,962 26,962 26,962 26,962 26,962
Plant Administrative Expense
----------------------------
Vehicle Expense 292 292 542 542 542 542 542 542 542 542
Outside Service 8,459 8,459 2,417 2,417 2,417 2,417 2,417 2,417 2,417 2,417
Equipment Rental 833 833 1,788 1,788 1,788 1,788 1,788 1,788 1,788 1,788
Phone 0 0 1,792 1,792 1,792 1,792 1,792 1,792 1,792 1,792
Administrative 3,458 3,458 4,657 4,657 4,657 4,657 4,657 4,657 4,657 4,657
----------------- -----------------------------------------------------------------------------
Total Plant Administrative Exp 13,041 13,041 11,194 11,194 11,194 11,194 11,194 11,194 11,194 11,194
Plant Employee Services
-----------------------
Travel and Subsistance 420 420 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000
Safety Training 125 125 333 333 333 333 333 333 333 333
Equipment Training 1,292 292 1,167 1,167 1,167 1,167 1,167 1,167 1,167 1,167
----------------- -----------------------------------------------------------------------------
Total Plant Employee Services 1,837 837 2,500 2,500 2,500 2,500 2,500 2,500 2,500 2,500
Plant Maintenance Materials
---------------------------
Heat Recovery Boiler 1,600 1,600 3,037 3,037 3,037 3,037 3,037 3,037 3,037 3,037
Electrical Interconnect 667 667 2,958 2,958 2,958 2,958 2,958 2,958 2,958 2,958
Water Treatment, Demin. 750 750 1,250 1,250 1,250 1,250 1,250 1,250 1,250 1,250
Tools & Shop Equipment 333 333 1,183 1,183 1,183 1,183 1,183 1,183 1,183 1,183
Effluent Control 708 708 1,512 1,512 1,512 1,512 1,512 1,512 1,512 1,512
Emmission Controls 542 542 878 878 878 878 878 878 878 878
Plant Aux, & Misc. 2,333 2,333 7,350 7,350 7,350 7,350 7,350 7,350 7,350 7,350
----------------- -----------------------------------------------------------------------------
Total Maintenance Materials 6,933 6,933 18,168 18,168 18,168 18,168 18,168 18,168 18,168 18,168
Total O&M Expenses 398,834 398,557 391,767 379,095 391,767 387,543 374,167 387,543 391,767 391,767
------- ------- ------- ------- ------- ------- ------- ------- ------- -------
-------------------------------------------------
Sep 99 Oct-99 Nov-99 Dec-99 Total-99
-------------------------------------------------
Operations and Maintenance
------------------------------
GE Fees
-------
Operating Fee 29,167 29,167 29,167 29,167 350,000
Spare Parts Carrying Fee 4,167 4,167 4,167 4,167 50,000
Leased Engine Fee 25,000 25,000 25,000 25,000 300,000
Handling Fee 4,167 4,167 4,167 4,167 50,000
Gas Turbine Overhaul Fee 108,768 129,888 125,664 129,888 1,494,592
Directed Starts Fee 0 0 0 0 0
-------------------------------------------------
Total GE Fees 171,268 192,388 188,164 192,386 2,244,592
Total Engine Hours On Line 1,236 1,476 1,428 1,476 16,984
x $88 per hour 88.0 88.0 88.0 88.0 88.0
-------------------------------------------------
=Gas Turbine Overhaul Fee 108,768 129,888 125,664 129,888 1,494,592
Cumulative Directed Starts 36 38 40 42 42
Total Directed Starts > 56 @ $600 0 0 0 0 0
Total Directed Starts > 75 @ $1200 0 0 0 0 0
-------------------------------------------------
Directed Starts Fee 0 0 0 0 0
Plant Personnel Compensations
-----------------------------
Salaried Supervision 20,692 20,692 20,692 20,692 248,307
Hourly 58,350 58,350 58,350 58,350 700,203
Hourly Overtime 13,129 13,129 13,129 13,129 157,546
Fringe Benefits 35,840 35,840 35,840 35,840 430,080
Salaries G&A 12,544 12,544 12,544 12,544 150,528
-------------------------------------------------
Total Plant Personnel Comp 140,555 140,555 140,555 140,555 1,686,684
Plant Operating Expenses
------------------------
Plant Upkeep 1,286 1,286 1,286 1,286 15,431
Emmission Testing 3,269 3,269 3,269 3,269 39,223
Water Treatment 21,053 21,053 21,053 21,053 252,634
Consumables/lub/filler 1,354 1,354 1,354 1,354 16,250
-------------------------------------------------
Total Plant Operating Expense 26,962 26,962 26,962 26,962 323,538
Plant Administrative Expense
----------------------------
Vechicle Expense 542 542 542 542 6,500
Outside Services 2,417 2,417 2,417 2,417 29,000
Equipment Rental 1,788 1,788 1,788 1,788 21,450
Phone 1,792 1,792 1,792 1,792 21,500
Administrative 4,657 4,657 4,657 4,657 55,879
-------------------------------------------------
Total Plant Administrative Exp 11,194 11,194 11,194 11,194 134,329
Plant Employee Services
-----------------------
Travel and Subsistance 1,000 1,000 1,000 1,000 12,000
Safety Training 333 333 333 333 4,000
Equipment Training 1,167 1,167 1,167 1,167 14,000
-------------------------------------------------
Total Plant Employee Services 2,500 2,500 2,500 2,500 30,000
Plant Maintenance Materials
---------------------------
Heat Recovery Boiler 3,037 3,037 3,037 3,037 36,446
Electricial Interconnect 2,958 2,958 2,958 29,958 35,500
Water Treatment, Denmin. 1,250 1,250 1,250 1,250 15,000
Tools & Shop Equipment 1,183 1,183 1,183 1,183 14,200
Effluent Con???? 1,512 1,512 1,512 1,512 18,142
Emmission Controls 878 878 878 878 10,530
Plant Aux, & Misc. 7,350 7,350 7,350 7,350 88,200
-------------------------------------------------
Total Maintenance Materials 18,168 18,168 18,168 18,168 218,018
Total O & M Expenses 370,647 391,767 367,543 391,767 4,637,141
------- ------- ------- ------- ---------
* represents >
-8-
EXHIBIT E
INSURANCE
GE shall maintain and cause to be maintained by its subcontractors, at no
expense to POA, during the Term, for the protection of GE and such
subcontractors, Workers Compensation insurance, Employers Liability insurance in
an amount not less than $5,000,000 applicable to the Operation and Maintenance
of the Facility and the performance of this Agreement only, Disability Benefits
insurance and all other insurance GE or any such subcontractor is required by
law to provide covering loss resulting from injury, sickness, disability or
death of all persons employed by GE or its subcontractors or agents. GE and such
subcontractors shall also provide Automobile Liability insurance, including
uninsured/underinsured motorists protection, for all owned, non-owned and hired
autos in an amount not less than $5,000,000. GE shall require all subcontractors
coming onto the Facility site or the Right-of-Way to maintain Commercial General
Liability insurance coverage in an amount of not less than $l,000,000. Policy
forms ad insurers shall be reasonably acceptable to POA and Steam User. GE will
furnish certificates of insurance to POA and Steam User evidencing such
insurance and providing that such insurance shall not be canceled or reduced in
amount except upon thirty (30) days' prior written notice to POA and Steam User.
All policies of GE and subcontractors required by this Agreement, except Workers
Compensation and Employers Liability insurance, shall name POA and Steam User as
additional insureds. Coverage supplied by GE and subcontractors shall be primary
and waive the rights of subrogation against POA and Steam User. If requested by
POA, GE shall furnish to POA copies of the original policies of insurance
required to be carried by GE hereunder.
GE and its subcontractors shall be responsible for any loss of or damage to
their own property, including, without limitation, tools, equipment and
vehicles, but excluding materials to be included in the Facility, and shall
waive all rights of subrogation against POA and Steam User.
POA shall maintain, at its expense, during the Term, the following insurance:
(1) Workers Compensation providing coverage required by statute.
(2) Employer's Liability insurance in an amount not less than $5,000,000
applicable to the Facility
(3) Commercial General Liability insurance coverage with respect to the
Facility, with a deductible of not more than $100,000, or such higher
deductible as may be permitted by POA, in an amount not less than
$5,000,000 combined single-limit coverage, which shall insure the
activities of GE, including contractual coverage, products and completed
operations, broad form property damage and removal of the XCV exclusion.
(4) All Risk Property insurance, including Boiler and Machinery and Pressure
Vessel insurance coverage in the amount of the full replacement value of
the Facility and the Existing Plant for machinery breakdown including
all Equipment used in the operation and/or maintenance of the Facility
and/or the Existing Plant, including property damage, repair or
replacement.
-9-
EXHIBIT E, Continued
INSURANCE
(5) Such Business interruption and Extra Expense insurance as is required by
Steam User.
(6) Umbrella Liability insurance with policy coverage of not less than
twenty million dollars ($20,000,000).
Each such policy of insurance (other than worker's compensation and Employer's
Liability) shall name GE as an additional Named Insured, and all insurance
policies shall be endorsed to waive subrogation against GE and shall be primary
with respect to any other insurance, except that it shall be deemed to be excess
coverage hereunder. POA shall furnish to GE copies of the original policies of
insurance required to be carried by POA hereunder. Each such policy of insurance
shall provide that such insurance shall not be canceled or reduced in amount, or
have its terms and conditions modified, except upon thirty (30) days' prior
written notice to GE.
POA shall be responsible for payment of deductible amounts under the policies to
be provided by POA, except to the extent that the loss insured arises from the
gross negligence or willful misconduct of GE or its subcontractors or the
failure of GE to perform its obligations hereunder, in which event, the
deductibles with respect to losses which result therefrom shall be paid by GE.
All of the aforesaid insurance to be provided by GE and POA hereunder shall
provide the indicated coverage amounts on an annual aggregate basis applicable
to the Facility only.
-10-
EXHIBIT F
GAS TURBINE PACKAGE DIAGRAM
[DIAGRAM APPEARS HERE]
-11-
EXHIBIT G
LM5000 LEASE ENGINE PROGRAM
I. ENGINE SUPPORT PROGRAM
For as long as the Agreement is in effect, the Parties shall participate
in the LM5000 ENGINE SUPPORT PROGRAM (the "Leased Engine Program") under
which POA shall pay to GE an Annual Lease Engine Fee, and the fixed Weekly
Use Rate Fees identified in Article IIIB below of this Exhibit, and GE
shall lease LM5000 Gas Turbine equipment under the terms and conditions
described in this Exhibit. In addition, the Parties shall continue their
participation in the Leased Engine Program until the completion of the
last major overhaul of any Gas Turbine Package required to be performed by
GE under Section 2.04 after the expiration of the Term or termination of
this Agreement, provided however, that in the event such continued
-------- -------
participation is required due to GE's continuing obligation to Repair and
Overhaul only one Gas Turbine Package, or in the event that, during such
continued participation, GE's Repair and Overhaul obligation becomes
applicable to only one Gas Turbine Package, then the Annual Lease Engine
Fee shall be reduced by 50% pro rata for all periods thereafter until the
termination of such participation.
II. GE's OBLIGATIONS UNDER THIS AGREEMENT
A. GE guarantees, during the Parties' participation in the Leased Engine
Program, to provide one operable leased LM5000 Gas Turbine on board a
carrier, at the Site (hereby established as the Delivery Point) and
qualified technical direction for its installation and removal within
seventy-two (72) hours of oral or written confirmation by POA of
notification of need, provided such oral notice to the Regional
Manager, GE Atlanta, Georgia or his delegated representative shall be
effective when received.
1. In the event a leased unit becomes inoperative during the term of
its lease due to causes reasonably determined by GE to be within
its control, GE will either repair the unit on-site within
seventy-two (72) hours or deliver a replacement unit at the
Delivery Point at GE's expense. If GE determines that a
replacement unit is required, it will be provided within
seventy-two (72) hours.
B. The Leased Engine Program terms assume that scheduled hot section
refurbishment of POA's engine will be accomplished on-site without the
need for a leased engine and use of a leased engine during an off-site
scheduled hot section refurbishment is specifically excluded from the
Leased Engine Program. If the User desires a leased engine while his
engine is undergoing scheduled off-site hot section refurbishment, POA
agrees to pay the non-member non-exclusive lease engine rates in
effect at that time. The Leased Engine Program does apply to the
scheduled gas generator overhaul, anticipated to occur at
approximately 50,000 hours of operation.
-12-
EXHIBIT G, Continued
LM5000 LEASE ENGINE PROGRAM
C. Except to the extent caused by Force Majeure, should GE fail to
deliver a lease unit per Article IIA above, GE will be liable for late
delivery penalties of $850.00 per hour or $20,400.00 per day up to the
maximum liability which is equal to the total Annual Lease Engine Fee.
Penalties assessed against GE by virtue of such late delivery will be
in the form of a credit memorandum to be applied against the
subsequent Weekly Use Rate payments to be made to GE by POA. Any
unliquidated credit due User at the expiration or termination of the
Program shall be paid to POA within thirty (30) days.
III. USER'S OBLIGATIONS UNDER THIS AGREEMENT
A. Subject to Article I, above, User agrees to pay an Annual Lease Engine
Fee of $300,000 dual coverage for engines. Such Annual Lease Engine
Fee shall be effective for the first Operating Year and shall be
escalated for each Operating Year thereafter, based on the change in
the U.S. Department of Labor Consumer Price Index for December of the
preceding Operating Year, from such index for the next preceding
December.
B. POA further agrees to pay a Weekly Use Rate Fee for each week or, pro-
rata for any fraction thereof, for leased unit use which commences on
the date the lease unit arrives at the Site and ends when the lease
unit is ready to be removed from the Site. The Weekly Use Rate Fee is
as follows:
Weekly Use Rate Fee - Contiguous Weekly Charge
1-10 Weeks Over 10 Weeks
Gas Turbine $23,800 $37,900
Gas Generator $16,460 $26,740
Power Turbine $ 5,200 $ 8,490
Such Weekly Use Rate Fees shall be effective for the first Operating
Year and shall be escalated thereafter, based on the change in the
U.S. Department of Labor Consumer Price Index for December of the
Operating Year preceding the Operating Year in which the leased unit
is used, from such index for the next preceding December.
C. POA is responsible for notifying GE when a leased unit is required. At
the first opportunity, GE will orally identify to POA the (i) serial
number of the leased unit, (ii) carrier and estimated date and hour of
arrival at the Delivery Point and (iii) the Stated Value of the leased
equipment to be insured by POA. Within seventy-two (72) hours of POA
oral request for the leased unit, POA will confirm his request in
writing to GE and identify the existence of adequate insurance for the
Stated
-13-
EXHIBIT G, Continued
LM5000 LEASE ENGINE PROGRAM
Value of the leased unit by providing GE with a valid Certificate of
Insurance for the leased equipment. Notwithstanding the foregoing, POA
shall have no obligation to provide insurance coverage for losses
occurring during transportation. GE shall have all risk of loss during
transportation of the leased unit to and from the Delivery Point.
D. POA agrees to allow GE to utilize any hardware from POA's engines
(including engine-mounted kits) at no charge on the leased unit during
the period the leased unit is operated at the Site. Kits include, but
are not limited to, fuel nozzles, manifolds and piping, starters,
temperature and pressure sensing and indicating systems.
E. GE will be responsible for the costs of providing GE technical
direction for leased unit installation and removal and for all normal
wear and tear of the leased unit during its intended use at the POA's
installation. POA is responsible for damage to the lease unit due to
operation at POA's request above the T44 required to produce the power
provided by POA's unit prior to its removal (the "Site Rating").
F. Should POA call for a leased unit per Article IIIC and subsequently
determine that a leased unit is not required, POA will reimburse GE for
the actual transportation costs incurred by GE as a result of this
redetermination.
G. Should POA elect to defer the re-installation of its repaired Engine
(and continue operations with the GE leased engine) beyond one (1) week
after POA's engine has arrived at the Site and is available for re-
installation, POA shall pay GE at the Weekly Use Rate. These rates will
extend through each week or fraction of a week that the leased engine
remains unavailable to GE beyond the one-week period.
IV. AGREEMENT ADDENDUM
A. GE reserves the right to prospectively reprice the Leased Engine Fee
when POA's engine is operated, at POA's request, at a gas temperature
(T44) in excess of the Site Rating. The maximum price increase for this
cause is 10% of the Leased Engine Fee.
-14-
EXHIBIT H
MAINTENANCE SCHEDULE
1.1 SCOPE
The following maintenance instructions provide a guide to operator-level
maintenance of the LM5000 turbine generator set located at Project Orange
Associates Cogeneration Facility.
1.2 GENERAL MAINTENANCE CONCEPT
1.2.1 On-Condition Maintenance: The maintenance concept for the Xxxxxxx &
------------------------
Xxxxxxxxx turbine-powered package is generally referred to as "on-condition"
maintenance, which eliminates scheduled overhaul based on operating hours. Under
the on-condition concept, turbine-driven equipment and ancillary equipment are
inspected on a regular schedule and repaired as necessary to restore the unit to
operational serviceability. The extent of repairs under this concept is
determined by two basic factors:
1. Correction of the primary cause of failure and/or discrepancy and any
resultant secondary damage.
2. Replacement or repair of parts that do not meet the established
inspection criteria as defined in their respective product manuals,
1.2.2 On-Site Maintenance: On-site maintenance falls into two categories: (a)
-------------------
preventive (scheduled) maintenance and (b) corrective (unscheduled) maintenance.
(a) Preventive maintenance includes those scheduled maintenance actions which
are performed based on operating hours, calendar time, or a combination
of operating hours, calendar time, and condition monitoring.
(b) Corrective maintenance includes those maintenance actions performed for
cause, either as a result of failure or an impending failure detected by
inspection and/or condition monitoring.
1.2.3 During operation, the following items are monitored: gas generator speed,
power turbine speed, gas generator, and exhaust gas temperature, engine and
driven equipment vibration, oil pressure, oil temperature, and operating time.
1.2.4 Under the "on-condition" maintenance concept, scheduled maintenance
actions requiring shutdown can be accomplished concurrently at intervals of
4,000 hours (or 6 months) and 8,000 hours (or 12 months).
1.2.5 The most significant item of these scheduled inspections is a turbine
borescope check, which provides specific information on the condition of the
engine's compressor and hot gas path. The turbine, therefore, has a number of
ports specifically located to facilitate borescope inspections. It is standard
practice to monitor the condition of internal parts and schedule on-condition
maintenance intervals based on borescope inspections.
-15-
EXHIBIT H, Continued
MAINTENANCE SCHEDULE
1.2.6 For support of the turbine-powered, overall maintenance is divided into
three basic levels according to shop capability.
1.2.7 On-Site External - Level 1: On-site external maintenance encompasses the
--------------------------
following two categories of maintenance tasks:
(a) Preventive: Tasks which are scheduled on the basis of equipment run hours
or calendar time.
(b) Corrective: Tasks which are unscheduled and accomplished as a result of a
problem.
1.2.8 The work scopes for these tasks cover all work on the exterior of
installed equipment plus scheduled inspections, turbine gas generator cleaning
(water wash), gas generator/power turbine changeout (when necessary), and
changeout of components of driven equipment.
1.2.9 Off-Site or Off-Site Level 2 Repair: This level of maintenance includes
-----------------------------------
complete teardown and rebuild of a gas generator and/or power turbine by
subassemblies. Replacement of major subassemblies is within the capability of
this maintenance level.
1.2.10 Off-Site Xxxxx 0 xx Xxxxx 0 Xxxxxx: This scope of work provides for all
----------------------------------
levels of maintenance, plus complete repair of gas generator, power turbine, or
driven equipment parts. A test cell is required for a Level 3 or Level 4
facility.
1.2.11 Maintenance Schedule: Normal maintenance of each Xxxxxxx & Xxxxxxxxx
--------------------
LM5000 turbine generator set during the initial 3 years of operation (at 8,000
hours per unit per year) will require only a weekly Visual inspection of turbine
and driven equipment exteriors. None of these inspections will require equipment
removal or disassembly.
-16-
SCHEDULE 1
INITIAL INVENTORY OF SPARE PARTS
12-09-97 Syracuse University Inventory Catalog
Spare Part Description Supplier # Supp Part # Location QOH at Loc Total Cost ABC Flag
---------- ----------- ---------- ----------- -------- ---------- ---------- --------
010101003 BEARING XXXX (N.E.E.) S&S A03137751-01 SU--SEC 1.00 26540.27 C
010101004 BEARING XXXX (E.E) S&S B3128079-01 SU--SEC 1.00 23471.63 C
010102012 FUSE S&S E1327747-04 SU--SECC2 4.00 158.16 C
010102013 DIODE BRIDGE 30MI20 S&S 28278-818 SU--SECD2 2.00 83.82 C
010102014 FUSE S&S E3127032-00 SU--SECC2 23.00 1923.49 C
010105011 VOLTAGE MONITER CARD S&S 9602947 SU--MCCCABD 1.00 1968.34 C
010105012 POTENTIOMETER DRIVE UNIT S&S 266661014 SU--SECC2 1.00 1470.49 C
010105013 CONTROL CARD S&S 9611592/00 SU--MCCCABD 3.00 5640.66 C
010107001 IEFAN01 CABINET FAN ASSEMBLY, XXXXXX IEFAN01 SU--MCCCABA 1.00 465.50 C
120VAC
010107002 NIAI02 TERM MODULE, XXXXXX NIAI02 SU--MCCCABA 1.00 143.50 C
THERMOCOUPLE INPUT
010107003 INNIS01 INTERFACE SLAVE XXXXXX INNIS01 SU--MCCCABA 1.00 3461.50 C
010107006 NICS01 TERM MODULE, CONTROL XXXXXX NICS01 SU--MCCCABA 1.00 94.50 C
I/O
010107007 NIAI04 TERM MODULE ANALOG XXXXXX NIAI04 SU--MCCCABA 1.00 150.50 C
INPUT
010107008 NIDI01 TERMINATION MODULE XXXXXX NIDI01 SU--MCCCABA 1.00 70.00 C
010107010 IMCIS02 CONTROL I/O SLAVE XXXXXX IMCIS02 SU--MCCCABA 1.00 612.50 C
010107013 XXXX00-00 XXXXX XXXXXX XXXX00-00 XX--XXXXXXX 1.00 60.20 C
010107015 NICL01 TERMINATION MODULE, XXXXXX NICL01 SU--MCCCABA 1.00 213.50 C
COMM LINK
010107016 INDSI02 MODULE, DIGITAL INPUT XXXXXX INDSI02 SU--MCCCABA 1.00 518.00 C
SLAVE
010107017 IMASI02 ANALOG INPUT SLAVE XXXXXX IMASI02 SU--MCCCABA 1.00 630.00 C
010107018 1948564A1 POWER SUPPLY, XXXXXX 1948564A1 SU--MCCCABA 1.00 755.00 C
SWITCHING
010107019 IMDS004 MODULE, DIGITAL OUTPUT XXXXXX IMDS004 SU--MCCCABA 1.00 486.50 C
SLAVE
010107020 NTMU01 TERM. MTG, UNIT, REAR XXXXXX NTMU01 SU--MCCCABA 1.00 119.00 C
MOUNT
010108003 ELECTRIC HEATER S&S 25281-528 SU--SECC1 1.00 205.89 C
010108004 ELECTRIC CART. TYPE HEATER S&S 25281-714 SU--SECC2 1.00 146.02 C
010109012 GENERATOR L/O PUMP, COUPLING S&S 3142638101 SU--SECC5 1.00 3767.16 C
010109013 GENERATOR LUBE OIL TANK TEMP S&S 100TC5-4CC615 SU--MCCCABD 1.00 454.60 C
SWITCH
010109014 GENERATOR AUXILLARY LUB OIL S&S 300 5CCIG-CC SU--SECO4 1.00 521.97 C
PUMP
010109015 GENERATOR LUBE OIL SUPL TEMP S&S 78F25NOOA025T34 SU--MCCCABD 1.00 189.81 C
SENSOR
010109016 OIL SEAL RING (C/W) W/SPRING S&S 83135309-01 SU--SECD4 8.00 15892.24 C
3128497/01
010109017 GENERATOR L/O PUMP (MECH) S&S 314089901 SU--SEC03 1.00 4485.19 C
010109019 GASKET, X.X. XXXXXX, XXXX, XXXXX 000X00X-0 XX--XXXX0 4.00 24.00 C
OUTER SEAL, 6"
010109020 G-RING, L.O. COOLER, REVERSING XXXXX 080G0106 SU--SECA3 4.00 16.00 C
XXX, 0"
010109021 SWITCH, PRESSURE, L.O.HI/LO S&S 132p4s129-1 SU--MCCCABD 1.00 238.81 C
010201005 INSULATION TUBE S&S E3130399-17 SU--SECC1 39.00 687.18 C
010201006 INSULATION WASHER S&S E3116456-52 SU--SECC1 39.00 686.40 C
0?????001 DIODE BRIDGE FOR BRUSH S&S 3124865/00 SU--SECC1 3.00 305.22 C
Page 1
-17-
Spare Part Description Supplier # Supp Part # Location QOH at Loc Total Cost ABC Flag
---------- ----------------------------- ---------- --------------- ----------- ---------- ---------- --------
GENERATOR
010202002 LINK, FUSE TO DIODE S&S 3124863/01 SU--SECC1 6.00 339.84 C
010202003 EARTHING BRUSH HOLDER S&S E1174392-01 SU--SECC1 2.00 225.68 C
010202004 EARTHING BRUSH S&S E3116682-01 SU--SECC1 10.00 581.80 C
010202005 RECTIFIER 28239-078 S&S E3121182-01 SU--SECC1 12.00 6639.00 C
010202006 RECTIFIER 28239-079 S&S E3121182-02 SU--SECC1 12.00 6639.00 C
010203001 GASKET S&S D3135356-01 SU--SECC1 8.00 4391.92 C
010205002 XXXX.XX CONTROL CD HIW S&S 9602943/00 SU--MCCCABD 1.00 1796.21 C
010205003 EXCITATION LIMITER CARD S&S 9608470/00 SU--MCCCABD 1.00 1981.19 C
010205005 EXCITATION MONITOR CARD S&S 9608488/00 SU--MCCCABD 1.00 2012.60 C
010205006 AUTOMATIC POWER CARD S&S 9602933/00 SU--MCCCABD 1.00 1129.38 C
010205007 RELAY VP/2 S&S 25771-148 SU--SECD2 4.00 195.64 C
010205008 FUSE 500MA SIZE 0, 1/2 AMP S&S 25715-006 SU--SECD2 6.00 35.52 C
010205009 FUSE 2A SIZE 0 S&S 25715-010 SU--SECD2 4.00 20.96 C
010205010 FUSE 20ET S&S 25711-249 SU--SECD2 3.00 91.92 C
010205012 POTENTIOMETER FOR 500R + 500R S&S 26632-032 SU--SECD2 1.00 169.92 C
010205013 ELEC CONTROL BOARD S&S 9607087/00 SU--MCCCABD 1.00 2377.86 C
010205014 FUSE 4F21 S&S 25711-012 SU--SECD2 4.00 28.36 C
010205015 FUSE 250MA SIZE 0 S&S 25715-005 SU--SECD2 3.00 17.49 C
010205017 THYRISTOR NO 5400/122 S&S 28428-187 SU--SECD2 2.00 95.14 C
010205018 RELAY 125VDC 3P S&S 25771-167 SU--SECD2 2.00 142.32 C
010407001 SIEMENS TYPE AVB-O, 115KV WESTIN SEIMN-TP-AVB-O- SU--MEZ 2.00 950.00 C
PORCELAIN INSULATOR
010501084 ASSY. XXXXXXX XXXXXXX XXXXXX 00000-X0X XX--XXXXXXX 1.00 200.00 C
010501085 ARM ASM, RIGHT HAND XXXXXX 50925-G1P SU--MCCCABC 1.00 80.00 C
010501086 ARM ASM, XXXX XXXX XXXXXX 00000-X0X XX--XXXXXXX 1.00 80.00 C
010501087 MOTOR SW ASSY XXXXXX 00000-X0X XX--XXXXXXX 1.00 150.00 C
010501088 CT/ITI 300/5A XXXXXX 780-301 SU--MCCCABC 1.00 150.00 C
010501089 CT/ITI 3000/5A XXXXXX 780-302 SU--MCCCABC 1.00 150.00 C
010501090 ASM, COMM XXX XXXXX XXXXXX 00000-X0X XX--XXXXXXX 2.00 110.00 C
010501091 ANGLE, BARRIER SUPPORT XXXXXX 50607-P1 SU--MCCCABC 6.00 120.00 C
010501092 000XXX XXXXXXX XXXX XXXXXX 00000-X0X XX--XXXXXXX 1.00 230.00 C
010501093 000XXX XX XXXX XXXXXX 00000-X0X XX--XXXXXXX 1.00 230.00 C
010501094 SWBO PNL LAMP XXXXXX 011686708G3 SU--MCCCABC 1.00 25.00 C
010501095 CLF/CLE-2 15 KV/85KAIC XXXXXX 439D482G06 SU--SEC15 3.00 1530.00 C
010501096 PT/ITI 14.4KV/12OV XXXXXX PT5-110-143FF SU--SEC15 1.00 900.00 C
010501097 SET OF 3 CLE-2 5 + 15KV XXXXXX 9078A15G09 SU--SEC15 1.00 360.00 C
010501098 MICRO SWITCH XXXXXX XX-2RV2-A2 SU-MCCCABC 1.00 50.00 C
010502001 CS42 FUSE XXXXXX 25424-21120 SU-MCCCABC 10.00 1518.60 C
010502002 CS42 RECTIFIER XXXXXX 27907-34101 SU-MCCCABC 1.00 20.24 C
010502003 CS42 REACTOR XXXXXX 00000-000-00 SU-MCCCABC 1.00 35.15 C
010502004 CS42 FUSE XXXXXX 25416-10141 SU-MCCCABC 1.00 20.71 C
010502006 DS416HM TRIP RESET SPRING XXXXXX 795A077HOI(B) SU-MCCCABC 1.00 22.80 C
010502007 DS416HM TRIP RESET SPRING XXXXXX 795A077HOI(A) SU-MCCCABC 1.00 22.80 C
010502008 CS42 FUSE XXXXXX 25425-90500 SU-MCCCABC 1.00 31.88 C
010502009 COIL XXXXXX 00000-000-00 SU-MCCCABC 1.00 81.38 C
010502010 CS42 TRANSFORMR XXXXXX 00000-000-00 SU-MCCCABC 1.00 2123.51 C
010502011 CS42 COIL XXXXXX 9998-PD2C-110A SU-MCCCABC 11.00 318.78 C
010502013 DS416HM TRIP RETURN SPRING XXXXXX 4368621H05 SU-MCCCABC 1.00 26.60 C
010502014 CS42 RELAY XXXXXX 8501-PH40EV02 SU-MCCCABC 1.00 41.40 C
010502015 CS42 FUSE XXXXXX 25419-60160 SU-MCCCABC 1.00 22.61 C
010502016 SHUNT TRIP COIL XXXXXX 000X000X00 XX--XXXXXXX 1.00 106.40 C
010502017 SPRING RELEASE COIL XXXXXX 000X000X00 XX--XXXXXXX 1.00 106.40 C
010502018 DS416HM ARCHING SPRING XXXXXX 50380237H01 SU--MCCCABC 1.00 22.80 C
010502019 MOTOR KIT XXXXXX 000X000X00 XX--XXXXXXX 1.00 891.10 C
010502020 ANTI-PUMP RELAY XXXXXX 140D930H01 SU--MCCCABC 1.00 142.50 C
010504022 OSCILLATOR RESET XXXXXX 5038601H11 SU--MCCCABC 1.00 22.80 C
010504045 480120V XXXXXXXXXXX XXXXXX 000XX SU--MCCCABC 1.00 245.92 C
010504046 OVERLOAD XXXXXX 0XX00-00-0X XX--XXXXXXX 1.00 67.06 C
010504047 OVERLOAD BALDWI 3UA58-00-2V SU--MCCCABC 2.00 134.12 C
010504048 OVERLOAD XXXXXX 0XX00-00-0X XX--XXXXXXX 2.00 330.00 C
010504050 LIGHT SOCKET BALDWI 3SB14-00-2B SU--MCCCABC 4.00 89.44 C
010504051 480120V XXXXXXXXXXX XXXXXX 000XX SU--MCCCABC 1.00 149.79 C
010504052 OVERLOAD XXXXXX 0XX00-00-0X XX--XXXXXXX 2.00 178.88 C
010504053 480120V XXXXXXXXXXX XXXXXX 000XX SU--MCCCABC 1.00 167.67 C
010504054 OVERLOAD BALDWI 3UA52-00-1K SU--MCCCABC 2.00 76.00 C
010504055 OVERLOAD XXXXXX 0XX00-00-0X XX--XXXXXXX 2.00 76.00 C
010504056 OVERLOAD BALDWI 3UA59-00-1F SU--MCCCABC 2.00 169.90 C
010504057 OVERLOAD XXXXXX 0XX00-00-0X XX--XXXXXXX 2.00 169.90 C
010504059 OVERLOAD XXXXXX 0XX00-00-0X XX--XXXXXXX 2.00 134.12 C
010504060 OVERLOAD XXXXXX 0XX00-00-0X XX--XXXXXXX 2.00 134.12 C
010504061 OVERLOAD XXXXXX 0XX00-00-0X XX--XXXXXXX 2.00 138.12 C
010504062 OVERLOAD XXXXXX 0XX00-00-0X XX--XXXXXXX 2.00 91.86 C
010504065 BREAKER, MCC, 25 AMP BALDWI ED63A025 SU--MCCCABC 1.00 260.30 C
010516001 FUSE 400A 250 VAC SBM1 EXPERT 00-000000-00 SU--MCCCABC 3.00 199.59 C
010516002 XSTR 16BT MODULE 400A 600V EXPERT 00-000000-00 SU--MCCCABC 1.00 770.50 C
010516003 FUSE 400A 150 VAC SBM1 EXPERT 00-000000-00 SU--MCCCABC 1.00 53.33 C
010516004 XXX 000 XXX0 800V 200US EXPERT 00-000000-00 SU--MCCCABC 2.00 461.50 C
010516005 UPS FAN W/ALARM SOLIDS 00-000000-00 SU--MCCCABD 1.00 415.26 C
010517001 PILOT LIGHT NBON 125V AMBER EXPERT 00-000000-00 SU--MCCCABC 3.00 16.29 C
010517002 DIODE SENS 300228 SU--MCCCABA 9.00 135.00 C
010517003 SCR SENS 201757 SU--MCCCABA 3.00 225.00 C
010517004 FUSE 5A 250V 1/4 X 1-1/4 EXPERT 00-000000-00 SU--MCCCABC 1.00 1.41 C
010517005 MULTI ALARM SENS 203471 SU--MCCCABA 1.00 225.00 C
010517006 DISPLAY BOARD SENS 204491 SU--MCCCABA 3.00 225.00 C
010517007 RELAY TO 120VAC COIL 5 AMP @ EXPERT 00-000000-00 SU--MCCCABC 1.00 204.35 C
250VAC
010517008 PILOT LIGHT NEON 125V RED EXPERT 00-000000-00 SU--MCCCABC 3.00 16.29 C
010517009 PILOT LIGHT NEON 125V GREEN EXPERT 00-000000-00 SU--MCCCABC 3.00 30.96 C
010517010 RELAY 4PDT 3 AMP 120VAC EXPERT 00-000000-00 SU--MCCCABC 1.00 18.43 C
010517011 SHUNT SENS 204491 SU--MCCCABA 3.00 90.00 C
010517012 DIODE 100AMP 400V FRD EXPERT 00-000000-00 SU--MCCCABC 1.00 42.88 C
010517013 DC METER SENS 703221 SU--MCCCABA 1.00 45.00 C
010517014 CIRCUIT BREAKER SENS 702522 SU--MCCCABA 3.00 135.00 C
010517015 AMP-METER SENS 703234 SU--MCCCABA 1.00 45.00 C
010517016 RIBBON CABLE ASSY SENS 808953 SU--MCCCABA 3.00 30.00 C
010517017 FUSE 5A 250V 1/4 X 1-1/4 EXPERT 00-000000-00 SU--MCCCABC 1.00 2.61 C
010517018 SCR 235AMP 500V 80VS EXPERT 00-000000-00 SU--MCCCABC 2.00 278.06 C
010701034 POWER MODULE AC INPUT SYSTEM XXXXXX IEPAS01 SU--MCCCABA 1.00 1351.00 C
POWER IEPASO1
010701051 1948002A4 85 MB HARD DISK XXXXXX 1948002A4 SU--MCCCABA 1.00 851.00 C
DRIVE (OPTIONAL)
SCHEDULE 1, Continued
12-09-97 Syracruse University Inventory Catalog
Spare Part Description Supplier # Supp Part # Location QDH at Loc Total Cost ABC Flag
---------- ----------- ---------- ----------- -------- ---------- ---------- --------
010701054 IMMFP01 XXXXXX IMMFP01 SU--MCCCABA 1.00 7315.00 C
010701055 IEMMOUI MODULE MOUNTING UNIT XXXXXX IEMMUOI SU--MCCCABA 1.00 364.00 C
010702001 ANNUCIATOR DISPLAY PANEL (ADP) XXXXXX IIADP02 SU--MCCCABA 1.00 2225.00 C
010705001 ISOLATOR, 4-20/4-20MA ACI SC 2302-1 SU--MCCCABA 3.00 716.79 C
010705002 SWITCH, H.O.A. CITYEL SWP-126 SU--MCCCABD 1.00 53.23 C
010705003 SELECTOR, SWITCH, HOA CITYEL 0205871-2 SU--MCCCABD 1.00 26.68 C
020401001 SHAFT SLEEVE GOULDS 73705X-2229 SU--SECP3 2.00 279.80 C
020403002 PACKING SET, STD SQUARE, XXXXXX 24244.516 SU--SECN5 1.00 59.29 C
PEGGING STM
020403003 GUIDE, BRONZE, PACKING, 1.12 XXXXXX 1107.433 SU--SECN5 2.00 209.92 C
STM
020403004 SPACER, PACKING, 1.12 STEM XXXXXX 2499-150 SU--SECN5 1.00 173.60 C
PEGGING STEM
020404002 3196 CASING GASKET ESTABR 00000-00-0000 SU--SECP4 1.00 8.36 C
020404003 3196 O.B. OIL SEAL ESTABR 8690-1120 SU--SECP3 1.00 4.12 C
020404004 3196 I.B. OIL SEAL ESTABR 8690-17645 SU--SECP4 1.00 8.52 C
020404005 3196 BRG HSG O-RING ESTABR CO2495A245-5302 SU--MEZZP3 1.00 5.55 C
020404006 3196 ADAPTER GASKET ESTABR 73078-5130-0001 SU--SECP4 2.00 6.70 C
020404007 3196 TFE IMPELLER X-XXXX XXXXXX XX0000X00-0000 XX--XXXX0 1.00 8.36 C
020406002 4" SAFETY RELIEF VALVE DELTAK 0100743309 SU--MEZG3 1.00 2243.08 C
020407002 55" GAUGE GLASS DELTAK 0100743317 SU--SECL5 1.00 2224.00 C
020408001 STEM GUIDE DELTAK 0100743361SG SU--SECR1 1.00 103.40 C
020408002 GASKET DELTAK 0100743361GT SU--SECR1 1.00 44.00 C
020408003 SPRING DELTAK 0100743361SP SU--SECR1 1.00 88.00 C
020408004 STEM DELTAK 0100743361SM SU--SECR1 1.00 88.00 C
020408005 DISC DELTAK 0100743361DC SU--SECR1 1.00 55.00 C
020501005 #5 CARBON INSERT W/ SEALIN Y5FQ1625AAF SU--SECQ3 7.00 434.00 C
MVSR2125333 & MVSR2875333
VITON O-RINGS (141964)
020501006 TUNG CARBIDE 00-0 XXXX XXXX XXXXXX XX0X0000000 XX--XXXX0 3.00 1134.00 C
(141964)
020501007 MECHANICAL SEAL (PTO 1.626") SEALIN 3310H-144726 SU--SECQ2 3.00 3825.00 C
020501009 O-RING, BALANCE BUSHING GOULDS 244328 SU--SECP5 1.00 37.40 C
020501010 O-RING, PRESS RED SLEEVE GOULDS 241958 SU--SECP2 1.00 8.80 C
020501011 O-RING, CASING GOULDS 083112 SU--SECP2 5.00 88.00 C
020501012 DIFFUSER RING GOULDS 209184 SU--SECP5 4.00 1216.60 C
020501013 SHAFT SLEEVE, THRUST GOULDS 282636 SU--SECP5 2.00 2523.00 C
020501014 SHAFT SLEEVE, COUPLING GOULDS 282635 SU--SECP5 1.00 1261.50 C
020501016 DISK, COUNTER BALANCE GOULDS 034428 SU--SECP2 1.00 1645.80 C
020501017 BALANCE DISK GOULDS 034452 SU--SECP5 1.00 930.60 C
020501018 WEAR RING GOULDS 035306 SU--SECP2 5.00 1677.50 C
020501019 HP BFW PUMP COUPLING ESTABR XXXX 1060T31 SU--SECL2 1.00 714.00 C
020501020 BFP O.B. SPACER GOULDS 257375 SU--SECP4 5.00 2203.00 C
ESTABR H257375
020501021 BFP O.B. SPACER SNAP RING GOULDS 044782 SU--SECP4 13.00 39.00 C
020522062 BEARING LOCKNUT, CPLG. SIDE GOULDS 136A-075966 SU--SECP5 4.00 116.20 C
020522064 OIL SEAL, SMALL SEALIN 332-274684 SU--SECP5 3.00 17.19 C
020522070 BEARING LOCKWASHER GOULDS 382A-008096 SU--SECP5 10.00 32.35 C
020522072 PUMP COUPLINGS IP/LP BFW GOULDS XXXX 1050T31 SU--SECL2 1.00 603.00 C
020522073 BEARING FRAME GOULDS 2286 SU--SECP4 1.00 2561.00 C
020522074 GLASS WINDOW, FLOW INDICATOR ACI 00-000000-00 SU--SECI2 2.00 10.00 C
020502075 IMPELLERS, FLOW INDICATOR ACI 410549-02 SU--SECI2 2.00 6.00 C
020502076 GASKET KIT, FLOW INDICATOR ACI 00-000000-00 SU--SECI2 2.00 12.00 C
020502077 COOLING WATER SIGHT FLOW BURNSB 1/2SF SU--SECI2 1.00 45.00 C
INDICATOR
BURNSC 1/2SF
020502080 COVER, BLR FD PMP STUFFING BOX ESTABR H289288 SU--SECP4 1.00 2503.25 C
020503003 REPAIR KIT XXXXXX RPACKX00112 SU--SECH5 1.00 78.75 C
020503008 REPAIR KIT XXXXXX R667X000502 SU--SECH5 1.00 5.04 C
020503009 SEAL BUSHING XXXXXX 1E845714012 SU--SECH5 1.00 28.35 C
020503010 DIAPHRAGM XXXXXX 2E859602202 SU--SECH5 1.00 59.85 C
020503013 REPAIR KIT XXXXXX R83LX000012 SU--SECH5 1.00 14.18 C
020503017 REPAIR KIT XXXXXX R67AFRX0012 SU--SECH5 1.00 12.92 C
020503021 3" BPR 1500LBM 130 GPM AGI 3"BPR 1500LB 13 SU--SECL4 1.00 790.00 C
020503023 ROTARY HEAD ASSY AGI SSV10-3"/300#-1 SU--SECL1 2.00 4280.00 C
020503024 SPRING AGI SSV10-3"/95.1-3 SU--SECL1 2.00 280.00 C
020503025 SEAL SET AGI SSV10-3"/300#-7 SU--SECL1 1.00 110.00 C
020503028 ROTARY HEAD ASSY AGI SSV10-3"/900#-1 SU--SECL1 1.00 2438.00 C
020503029 PLUG CVSALE 21423.150 SU--SECN3 1.00 1266.53 C
020503030 BONNET GASKET CVSALE 1224.868 SU--SECN3 1.00 31.96 C
020503031 SEAT GASKET CVSALE 1228.868 SU--SECN3 2.00 71.38 C
020503036 SEAT GASKET CVSALE 1027.868 SU--SECN3 2.00 71.38 C
020503037 PKNG SET CVSALE 24242.929 SU--SECN4 2.00 83.06 C
020503038 PKNG SET CVSALE 24246.929 SU--SECN4 1.00 40.54 C
020503039 BONNET GASKET, HP REG VLV CVSALE 1240.868 SU--SECN3 2.00 140.84 C
XXXXXX 1240.868
020503040 PKNG SET CVSALE 24238.929 SU--SECN4 2.00 65.24 C
020503041 CHECK VALVE CVSALE 19231.402 SU--SECN4 1.00 34.95 C
020503043 PILOT VALVE CVSALE 17396.999 SU--SECN4 1.00 54.67 C
020503044 SWITCHING VALVE CVSALE 4873.999 SU--SECN3 1.00 312.51 C
020503045 POSITIONER CVSALE 62910.999 SU--SECN3 1.00 873.08 C
020503046 SEAT RING CVSALE 8246.150 SU--SECN4 1.00 1042.16 C
020503047 O-RING YOKE AND PISTON CVSALE 1313.650 SU--SECN3 3.00 45.81 C
020503049 SEAT RING CVSALE 1383.150 SU--SECN5 1.00 131.58 C
020503050 PILOT VALVE CVSALE 2744.999 SU--SECN5 1.00 39.89 C
020503051 ADJ SCRW GASKET CVSALE 1631.655 SU--SECN5 3.00 3.69 C
020503054 BYPASS ASSEMBLY, XXX00-000# XXX XXXXXX ASSY-SSV SU--SECL1 2.00 3120.00 C
020503055 THROTTLE, SSV1--3"-300# AGI THROTTLE-3"-300 SU--SECL1 2.00 996.00 C
020503056 GASKET, VELAN, X.X. XXXXX XXX XXXXX 0" XXXXX SOFTIR SU--SECN4 5.00 248.30 C
OUTLET
020503057 GASKET SET, XXXXXX VALVE, HP NORCON 1287100X032 SU--SECN4 1.00 56.60 C
BFW.
020503058 PACKING KIT, HP XXXXXX XXX XXXXXX XXXXXX00000 SU--SECN4 1.00 38.40 C
020503059 I/P CONVERTER REPAIR KIT, NORCON R582X000012 SU--SECN4 1.00 10.80 C
XXXXXX CONT VLVS
020503060 1/4 PRESSURE REG REPAIR KIT NORCON R67AFRX0012 SU--SECN4 1.00 18.80 C
020504001 D/P GAUGE, BFP ACI 120-AC-12-00 SU--MCCCABC 1.00 135.00 C
020601004 O-RING & SEAL KIT ROTORK 11A/3 SU--SEC03 1.00 245.00 C
020604001 BONNET GASKET CVSALE 2615.868 SU--SECN2 1.00 122.33 C
020604003 PKG. SET CVSALE 24250.370 SU--SECN5 1.00 91.61 C
020604004 SEAT GASKET CVSALE 2616.868 SU--SECN2 1.00 110.00 C
020604005 SEAT GASKET CVSALE 2382.868 SU--SECN2 1.00 84.74 C
SCHEDULE 1, Continued
12-09-97 Syracuse University Inventory Catalog
Spare Part Description Supplier # Supp Part # Location QOH at Loc Total Cost ABC Flag
---------- ----------------------------- ---------- ----------- ---------- ---------- ---------- --------
020604006 BACKUP RINGS CVSALE 54509.791 SU--SECN2 2.00 920.00 C
020604007 BACKUP RINGS CVSALE 74257.791 SU--SECN2 2.00 353.64 C
020604008 SLEEVE GASKET CVSALE 21362.868 SU--SECN2 1.00 82.21 C
020604009 SLEEVE GASKET CVSALE 2381.868 SU--SECN2 2.00 220.00 C
020604010 SEAT GASKET CVSALE 1231.868 SU--SECN5 1.00 40.07 C
020604041 HANDWHEEL SPINNER KIT LIMITO L120-10-186 SU-- 2.00 2.00 C
020608001 3/4" DRAIN UNION ASSEMBLY GARYHO DUA 3/4" NPT SU--SECN4 2.00 236.00 C
(.031) ORIFICE / 100#
SYSTEM DRAIN
020608002 3/4" DRAIN UNION ASSEMBLY GARYHO 3/4" DUA NPT SU--SECN3 2.00 236.00 C
(.025) ORIFICE / 275# SYSTEM
020608004 ORIFICE STM TRAP GASKET SET GARYHO 6184200 SU--SECN4 4.00 90.56 C
020608005 STEAM TRAP, HIGH PRESS ORIFICE RLSTON MOD-3/4-421-5/1 SU--SECN3 1.00 521.00 C
020703001 GUIDE LINERS CVSALE 5388.927 SU--SECN5 4.00 65.32 C
020703004 BONNET GASKET CVSALE 2716.925 SU--SECN5 1.00 31.61 C
020703005 POSITIONER CVSALE 63931.999 SU--SECN3 1.00 873.80 C
030103001 REPLACE AGGLO MESH PADS DELTAK 0100743395RA SU--SECR1 22.00 836.80 C
TOP/CYCLONES
030105001 DIAPHRAGM, XXXXXX, DESUP VLV NORCON 2E800002202 SU--SECM5 1.00 41.60 C
030106001 STUD - 1 NC X 11 LG DELTAK 12030392 SU--SECR1 2.00 16.20 C
030106002 NUT - 1 NC HEX DELTAK 24010111 SU--SECS1 5.00 3.30 C
030106003 BOLT - 3/4 NC X 6 LG SQ HD DELTAK 12030369 SU--SECS1 7.00 35.00 C
030106004 NUT - 3/4 NC HEAVY HEX DELTAK 24010020 SU--SECS1 7.00 1.68 C
030106005 4" XXXXXX CONTROL VALVE NORTH RPACKX00112 SU--SECN3 1.00 1.00 C
REPAIR KIT
030106007 4" XXXXXX CONTROL VALVE NORTH R83LX000012 SU--SECN3 1.00 1.00 C
REPAIR KIT
030106009 3/4" FLAT WASHER, HARDENED DELTAK 33010050 SU--SECS1 12.00 2.88 C
030106011 L.P. & DEA VALVE, GAGE XXXXX XXXXXX 32120005 SU--SECS1 2.00 880.00 C
403-RS (250 PSI)
030106098 GASKET DELTAK 2642-050 SU--SECQ1 4.00 41.28 C
030106101 PACKING SET DELTAK 2592-001 SU--SECQ1 2.00 68.00 C
030106112 H.P. VALVE, GAGE GLASS SG-854 CLARKR 32120006* SU--SECS2 2.00 763.82 C
NOREAS 32120006*
030106113 I.P. VALVE, GAGE GLASS 404-RS XXXXXX 404-RS (450 PSI SU--SECR1 2.00 880.00 C
(450 PSI)
030106115 ELECTRO-PNEUMATIC I/P NORTH TYPE 546 SU--MCCABD 1.00 600.60 C
TRANSDUCER TYPE 546
030106116 LP DRUM TUBE SNUBBER BEND DELTAK 30040020 SU--XXXXX 1.00 95.00 C
JOINT
030107001 PACKING SEAL COPESV 187058 SU--SECM4 1.00 2.76 C
030107002 AIR FILTER REGULATOR COPESV 271777 SU--SECM4 1.00 80.34 C
030107003 STEM GUIDE BUSHING COPESV 184686H SU--SECM4 1.00 45.15 C
030107004 DIAPHRAGM COPESV 185989 SU--SECM4 1.00 90.53 C
030107005 GROMMET COPESV 264362 SU--SECM4 1.00 3.70 C
030107006 BODY/GAGE GASKET COPESV 262600 SU--SECM4 1.00 1.89 C
030107007 ACTUATOR GASKET COPESV 187031 SU--SECM4 1.00 11.23 C
030107008 SEAL BUSHING COPESV 187018 SU--SECM4 1.00 91.73 C
030107009 STEM CONNECTING ASSEMBLY COPESV 186996 SU--SECM4 1.00 169.74 C
030107010 GAUGE, O-100 COPESV 130599 SU--SECM4 1.00 14.70 C
030107011 ACTUATOR STEM COPESV 186007 SU--SECM4 1.00 289.00 C
030107013 PACKING COPESV 186201 SU--SECM4 1.00 59.41 C
030107014 CONNECTING LINK ASSEMBLY COPESV 333333 SU--SECM4 1.00 77.31 C
030107015 POSITIONER COPESV 333301H SU--SECN5 1.00 1052.48 C
030109001 1.5" SAFETY RELIEF VALVE DELTAK 0100743305 SU--MEZG3 1.00 2218.46 C
030109003 2" SAFETY RELIEF VALVE DELTAK 0000000000 SU--MEZG3 1.00 906.15 C
030109005 2.5" PRESSURE SAFETY RELIEF DELTAK 0100743302 SU--MEZG3 1.00 5775.38 C
VALVE 900#A
030109006 1.5" SAFETY RELIEF VALVE DELTAK 0100743304 SU--MEZG3 1.00 2218.46 C
030109008 2.5" SAFETY RELIEF VALVE DELTAK 0100743308 SU--MEZG3 1.00 1126.15 C
030109009 VALVE, BOTTOM BLOW, H.P. FWWEBB FIG-B6771 SU--SECO5 1.00 1786.00 C
STRAIGHT
030109010 VALVE, BOTTOM BLOW, H.P. FWWEBB FIG-B6761 SU--MEZ 1.00 1786.00 C
ANGLE
030110001 PACKING KIT DELTAK 0100743357PK SU--SECR1 1.00 99.22 C
030110002 STEM/DISK ASSEMBLY DELTAK 0000000000SD SU--SECR1 1.00 1058.40 C
030110003 BONNET GASKET DELTAK 0100743359BG SU--SECR1 3.00 79.38 C
030110004 YOKE BUSHING DELTAK 0100743357YB SU--SECR1 1.00 91.80 C
030110005 BONNET GASKET DELTAK 0100743363BG SU--SECR1 3.00 74.64 C
030110006 BONNET GASKET DELTAK 0100743357BG SU--SECR1 3.00 151.20 C
030110007 STEM/DISK ASSEMBLY DELTAK 0100743362SD SU--SECR1 1.00 549.98 C
030110008 YOKE BUSHING DELTAK 0100743362YB SU--SECR1 1.00 64.44 C
030110009 PACKING KIT DELTAK 0100743358PK SU--SECR1 1.00 99.22 C
030110010 PACKING KIT DELTAK 0100743359PK SU--SECR1 1.00 99.22 C
030110011 PACKING KIT DELTAK 0100743363PK SU--SECR1 1.00 88.84 C
030110012 STEM/DISK ASSEMBLY DELTAK 0100743357SD SU--SECR1 1.00 1058.40 C
030110013 YOKE BUSHING DELTAK 0000000000YB SU--SECR1 1.00 91.80 C
030110014 BONNET GASKET DELTAK 0100743362BG SU--SECR1 2.00 49.76 C
030110015 PACKING KIT DELTAK 0000000000PK SU--SECR1 1.00 99.22 C
030110016 BONNET GASKET DELTAK 0100743358BG SU--SECR1 1.00 26.40 C
030110017 BONNET GASKET DELTAK 0000000000BG SU--SECR1 3.00 151.20 C
030110018 PACKING KIT DELTAK 0100743362PK SU--SECR1 1.00 88.84 C
030115001 GASKET,GAS SIDE ACCESS DOOR DELTAK 0100743395GS SU--SECS1 4.00 81.36 C
030117012 LAMP SOCKET, EYE-HI COLOR CLARKR GI-40-23 SU--MCCCABB 16.00 241.92 C
CHANGE
NOREAS GI-40-23
030117013 REPAIR KIT DELTAK 0000000000 SU--SECQ1 2.00 179.08 C
030117014 GAGE PRESSURE TRANSMITTER ROSEMT 115GP7E12B1 SU--MCCCABB 1.00 693.00 C
030117016 PRESSURE TRANSMITTER ROSEMT 115OP4522M1B3 SU--MCCCABB 1.00 991.20 C
030117017 TEMP TRANS TYPE K
THERMOCOUPLE INPUT ROSEMT 0444TJ1U1A2NA SU--MCCCABB 1.00 437.75 C
030117018 TEMP TRANS TYPE K
THERMOCOUPLE INPUT ROSEMT 0444TK2U1A2NA SU--MCCCABB 1.00 437.75 C
030117019 PRESSURE TRANSMITTER ROSEMT 1151GP8S22M1B3 SU--MCCCABB 1.00 903.00 C
030117020 PRESSURE TRANSMITTER ROSEMT 1151GP6522M1B3 SU--MCCCABB 1.00 903.00 C
030117021 T PROBE DELTAK 0100743313 SU--SECQ1 2.00 254.60 C
030117022 V PROBE DELTAK 0100743311 SU--SECQ1 3.00 546.00 C
030117023 REPLACEMENT MODULES (SET OF 7) DELTAK 0000000000 SU--SECQ1 7.00 1359.40 C
030117024 TEMPERATURE TRANSMITTER ROSEMT 3044CA1B4M5E5 SU--MCCCABB 1.00 783.00 C
030117025 PRESSURE TRANSMITTER ROSEMT 1151GP9S22M1B3 SU--MCCCABB 1.00 978.60 C
030117026 REPLACEMENT MODULES (SET DELTAK 0100743316 SU--SECQ1 10.00 2040.00 C
OF 10)
SCHEDULE 1, Continued
12-09-97
Syracuse University Inventory Catalog
Spare Part Description Supplier # Supp Part # Location QOH at Loc Total Cost ABC Flag
-------------- ------------------------------ ------------- ---------------- ------------- ----------- ----------- --------
030117029 REPAIR KIT DELTAK 0100743379 SU--SECQI 2.00 636.48 c
030117030 T PROBE DELTAK 0100743312 SU--SECQI 3.00 381.90 c
030117033 REFLECTOR LAMP (SET OF 6) DELTAK 0100743318 SU--SECR1 2.00 129.36 c
030117034 GAGE PRESSURE TRANSMITTER ROSEMT 1151GP8E1281 SU--MCCCABB 1.00 693.00 c
030117035 DIFFERENTIAL PRESSURE ROSEMT 1151DP3E1281 SU--MCCCABB 1.00 831.60 c
TRANSMITTER
030117036 DEAERATOR THERMOCOUPLE ACI J49G-260H-100-L SU--SECS4 2.00 221.00 c
030117037 1/2" SYPHON ACI 71342 SU--SECH3 2.00 65.14 c
030117038 LIQUID 0-600 XXX XXXXX 0" XXX 000000 XX--XXXXXXX 2.00 436.12 c
030117041 MULITANGLE BI-NET THERMOCOUPLE ACI BA5118E180 SU--SECL2 2.00 152.00 c
030117042 THERMOWELL ACI 304ss-1"260HL-U SU--SECS4 2.00 40.18 c
030117043 THERMOWELL ACI 304ss-1"260HL-U SU--SECS4 2.00 75.88 c
030117044 THERMOWELL ACI 304ss-1"260HL-U SU--SECS4 2.00 36.26 c
030117045 LIQUID 0-160 XXX XXXXX 0" XXX 000000 XX--XXXXXXX 2.00 436.12 c
030117046 STEAM OUTLET THERMOCOUPLE ACI K49G-260s-100-L SU--SECS4 1.00 134.25 c
030117047 THERMOWELL ACI 1"-260HL-013 SU--SECS4 2.00 130.00 c
030117048 H.P. STEAM OUTLET THERMOCOUPLE ACI K49G-260H-100LO SU--SECS4 2.00 243.00 c
030117049 LIQUID 0-1500 XXX XXXXX 0" XXX 000000 XX--XXXXXXX 2.00 454.32 c
030117053 1/2" GAUGE COCK ACI PG6-T-SS-F4M4 SU--SECK2 2.00 192.00 c
030117054 LEVEL SWITCH JOBELL CB-300-4-ZD3W SU--SECS3 1.00 341.10 c
030117055 VORTEX FLOW METER NICE VBAR-FV-02-2-40 SU--SECH1 1.00 2795.00 c
030117056 VORTEX FLOW METER NICE VBAR-FV-06-2-40 SU--SECH1 1.00 2795.00 c
030117057 VORTEX FLOW METER NICE VBAR-FV-03-2-40 SU--SECH1 1.00 2795.00 c
030117093 SIMPLIPORT MODULES CLARKR PW-24B SU--SECS1 5.00 629.00 c
NOREAS PW-24B
030117094 SIMPLIPORT NUT ASSEMBLY CLARKR PW-27R SU--SECS1 5.00 418.10 c
NOREAS PW-27R
030123001 EYE-HI PROBES CLARKR V-020 SU--SECS1 13.00 1636.51 c
NOREAS V-020RK
030123002 3/4"00 X6"L X0/0"XXX XXXXXX XX0-0 XX--XXXX0 4.00 69.12 c
SIGHTGLASS ADAP.
030123003 IP/LP SIGHTGLASS PACKING XXXXXX SG454-10 SU--SECS1 10.00 22.20 c
WASHER
NOREAS SG454-10
030123004 EYE-HI PROBE GASKETS NOREAS E10-10 SU--SECS1 29.00 234.13 c
030123005 RELAY, EYE-HI PROBES XXXXXX 0X000 XX--XXXXXXX 2.00 27.06 c
030123006 RELAY, TRIP PROBES XXXXXX 0X0XX XX--XXXXXXX 3.00 262.65 c
030204003 INSULATOR, ELECTRODE IGNITION XXXX 0000-000-00 SU--MCCABC 1.00 45.00 c
WIRE
030204004 5/32" WIRE, ELECTRODE TO SPARK XXXX 0000-000-00 SU--MCCABC 2.00 22.00 c
PLUG X 11"
030204005 CABLE HIGH TEMP SPARK PLUG TO XXXX 0000-000-00 SU--MCCABC 2.00 60.00 c
XFMER
030204006 GROMHET, SPARK PLUG CABLE XXXX 0000-000-00 SU--MCCABC 2.00 30.00 c
030204007 SPARK PLUG, S1 - 140 XXXX 0000-000-00 SU--MCCABC 3.00 196.50 c
030204009 COUPLING, SPARK PLUG CABLE XXXX 0000-000-00 SU--MCCABC 3.00 33.00 c
030204010 CONNECTOR, WIRE TO SPARK PLUG XXXX 0000-000-00 SU--MCCABC 1.00 47.00 c
030204011 ELECTRODE ASSEMBLY IGNITION XXXX 0000-000-00 SU--MCCABC 1.00 100.00 c
030204012 HEAD ASSEMBLY, PILOT SET XXXX 0000-000-00 SU--MCCABC 1.00 449.00 c
030204013 IGNITION TRANSFOMER XXXX 0000-000-00 SU--MCCABC 2.00 208.00 c
030204014 PILOT GAS FLEX HOSE, 3/8"NPT X XXXX 0000-000-00 SU--MCCABC 2.00 130.00 c
16"
030204015 PILOT GAS CHECK VALVE FWWEBB #583-3/8-D63 SU--MCCCABC 5.00 512.15 c
030205001 DC POWER SUPPLY NIAGRA 61-3356 SU--MCCABC 1.00 108.12 c
030205002 FLAME SCANNER NIAGRA UV-1A6 SU--MCCABC 4.00 382.88 c
030205003 UV AMPLIFIER NIAGRA 61-3359 SU--MCCABC 3.00 871.02 c
030205006 NIPPLE, 1/2 X 1-1/2", 580 PART XXXX 0000-000-00 SU--MCCABC 6.00 24.00 c
OF LENS MOD. KIT #0000-000-00
030205007 UNION, #60-1290, PART OF LENS XXXX 0000-000-00 SU--MCCABC 2.00 448.96 c
MOD. KIT #0000-000-00
NIAGAR 60-1290
030205008 4" MAXON VALVE MAXON 15-43325 SU--SECE4 1.00 3048.30 c
030205009 LENS, FIRE-EYE, MAGNIFYING, NIAGAR 46-58 SU--MCCCABC 4.00 223.00 c
DUCT BURNER
030208004 700-F400-A1 CONTROL RELAY XXXXXX 000-X000-X0 XX--XXXXXXX 1.00 34.62 c
030208005 700-F310-A1 CONTROL RELAY XXXXXX 000-X000-X0 XX--XXXXXXX 1.00 34.62 c
030208037 SWITCH, HIGH TEG TEMP 800-1800 XXXX 2430-143-01 SU--MCCABC 2.00 886.00 c
DEGREES F
030208038 FLAME SIGNAL METER XXXX 0000-000-00 SU--MCCABC 1.00 152.00 c
030208039 SWITCH, LOW GAS CPICON B432VXFM 06-30 SU--MCCCABC 1.00 168.00 c
030208040 SWITCH, LOW INSTRUMENT AIR CPICON B432VXFM 100 PS SU--MCCCABC 1.00 270.00 c
030208041 VALVE, LOW FIRE, PROGRAMMING XXXX 0000-000-00 SU--MCCABC 1.00 122.00 c
030208042 WATCHDOG TIMER XXXX 0000-000-00 SU--MCCCABC 1.00 325.00 c
030208043 SWITCH, LOW SCANNER AIR CPICON B424VXFM 60-XX XX--MCCCABC 1.00 249.00 c
030208044 REPAIR KIT XXXXXX RPACKX00022 SU--SECM5 1.00 18.27 c
030208045 GASKET SET XXXXXX RGASKETX362 SU--SECL5 1.00 21.42 c
030208046 SEAT RING XXXXXX 1U222946172 SU--SECM5 1.00 129.15 c
030208047 I/P TRANSDUCER XXXXXX 35821-3FMI SU--SECM5 1.00 847.30 c
NORCON 35821-3FMI
030208048 CAGE, EQ% XXXXXX 2U236333272 SU--SECL5 1.00 522.90 c
030208049 RING, PISTON XXXXXX 1U239105092 SU--SECM5 1.00 15.44 c
030208050 PLUG/STEM BALANCED XXXXXX 1V6581X0042 SU--SECM5 1.00 217.35 c
030208093 SLC 500 MEMORY MODULE BALDWI 0000-X0 XX--XXXXXXX 1.00 189.53 c
030208094 SLC500 POWER SUPPLY XXXXXX 0000-X0 XX--XXXXXXX 1.00 236.08 c
030208095 SLC500 PROCESSOR UNIT BALDWI 1747-L514 SU--MCCCABA 1.00 319.20 c
030308096 SLC500 INPUT MODULE XXXXXX 0000-XX00 XX--XXXXXXX 1.00 169.58 c
030208097 SLC500 OUTPUT MODULE BALDWI 1746-OW16 SU--MCCCABA 1.00 172.90 c
030208098 SLC500 OUTPUT MODULE BALDWI 1746-OA16 SU--MCCCABA 1.00 247.12 c
030209002 BUSHING, 1.125" TUTHIL 23532-6 SU--SEC04 1.00 7.00 c
030209004 BLOWER REBUILD KIT TUTHIL 27305 SU--SEC04 4.00 900.00 c
ELECLAB 27305
030209005 BUSHING, 1.375 TUTHIL 23128-6 SU--SEC04 1.00 8.00 c
030209006 DRIVE V-BELT TUTHIL 28210-16 SU--SEC04 4.00 32.00 c
030209007 GASKET, PORT, #39 TUTHIL 7932 SU--SEC04 7.00 14.00 c
ELECLAB 7932
030314005 RELAY KIT, XXXX 71 DAHLCO 0000-00-0000 SU--XXXXX 2.00 170.00 c
030601006 4" XXXXXX CONTROL VALVE REPAIR CVSALE R4190X00C12 SU--SECN3 1.00 1.00 c
KIT
040202001 XXXXXX XXX PUMP EFR 111-15 XXXXXX EFR-111-15 SU-- 1.00 1853.00 c
040202002 REBUILD KIT FOR XXXX XXX PUMP XXXXXX 000-0000-000 SU--SECM2 1.00 271.00 c
040401029 GASKET, RND, 2-1/4, X 1/32 TIDE A-5375 SU--SECQ5 1.00 3.18 c
0????1030 GASKET, SOR, 5-7/8 X 5-7/8 TIDE B-0421 SU--SECQ5 1.00 3.03 c
SCHEDULE 1, Continued
12-09-97 Syracuse University Inventory Catalog
Spare Part Description Supplier # Supp Part # Location QOH at Loc Total Cost ABC Flag
---------- ----------- ---------- ----------- -------- ---------- ---------- --------
X1/32
040401031 O-RING, VT, 6.645 O.D.X.210 TIDE A-0724 SU--SECQ5 4.00 62.72 C
040401032 PACKING KIT, PRIMING PUMP TIDE B-0425-K SU--SECQ5 1.00 6.28 C
040401033 DISCHARGE VALVE ASSEMBLY HOERBI B-1376-L SU--SECR4 8.00 3005.64 C
TIDE B-1376-L
040401034 UNL, PISTON RING, 5-1/4 O.D. TIDE A-0475 SU--SECR4 2.00 82.90 C
040401035 GASKET,RET,23-1/2X20-5/16X1/32 TIDE B-0844 SU--SECR3 2.00 56.66 C
040401036 O-RING,VT,2.012 O.D.X.139 TIDE A-3507 SU--SECQ5 2.00 7.04 C
040401037 O-RING,VT,2.762 O.D.X.139 TIDE A-3508 SU--SECQ5 1.00 4.54 C
040401038 STL, GASKET, 3.855 X 3.537 X30 TIDE A-2084 SU--SECR4 10.00 35.10 C
040401039 GASKET, RET TIDE B-1032 SU--SECQ5 2.00 13.66 C
10-13/16X6-3/4X1/32
040401040 O-RING, VT, 1.318 O.D.X.103 TIDE A-3512 SU--SECQ5 6.00 7.20 C
040401041 LUBE OIL PUMP JGW:R:J/4, HEK/2 TIDE D-0292 SU--SECS2 1.00 847.98 C
040401042 SUCTION VALVE ASSEMBLY HOERBI B-1418-L SU--SECR4 8.00 3005.64 C
TIDE B-1418-L
040401043 XXXX,XXX,XXXXX, XXXXX, #00-00X TIDE A-0523 SU--SECR3 1.00 17.95 C
040401044 COMPRESSION SPRING, UNIVERSAL TIDE A-0629 SU--SECR3 2.00 14.72 C
040401045 STAT-O-SEAL, 1/2 DIA. TIDE FW0550GA SU--SECQ5 2.00 1.06 C
040401046 DUST SEAL, TEFLON, JGH:EIK TIDE A-0245-8 SU--SECR3 1.00 169.72 C
040401047 GASKET, NST, 17-3/4 TIDE B-0835 SU--SECR3 2.00 30.36 C
X15-7/8X1/64
040401048 O-RING, VT, 2.756 O.D.X.103 TIDE A-0745 SU--SECQ5 1.00 2.22 C
040401049 ROLLER CHAIN, 40-1X114, JGH:EIK TIDE A-3884 SU--SECR3 1.00 20.17 C
040401050 O-RING,VT, 2.625 O.D.X.139 TIDE A-0010 SU--SECQ5 1.00 2.55 C
040401051 XXXX, XXXXX, 00X*-00X-0X XXXX X-0000 XX--XXXX0 1.00 313.68 C
040401052 O-RING, VT, 3.887 O.D.X. 139 TIDE A-1812 SU--SECQ5 4.00 31.76 C
040401053 SPKT, RLR, CHAIN, X.X. PUMP, TIDE A-3874 SU--SECR3 1.00 101.86 C
28T
040401054 GASKET, RND, 22-1/2 X 1/64 TIDE B-1042 SU--SECR4 2.00 53.12 C
040401055 STL, GASKET, 7.375 X 7.750 X60 TIDE A-2087 SU--SECQ5 2.00 10.94 C
040401056 STAT-O-SEAL, 3/4 DIA., BLACK TIDE FW05501A SU--SECQ5 9.00 8.55 C
040401057 VALVE PACKING UNIVERSAL TIDE A-0639 SU--SECR3 2.00 46.46 C
040401059 GASKET,RND,12-13/16, X 1/32 TIDE A-3875 SU--SECQ5 1.00 15.18 C
040401060 GASKET,RND, 2-1/4, X 18 TIDE A-5376 SU--SECQ5 1.00 3.54 C
040401062 GASKET, SO, TIDE B-0779 SU--SECQ5 1.00 5.06 C
5-15/16X5-15/16X1/32
040401063 GASKET, RET, TIDE B-0832 SU--SECQ5 2.00 30.36 C
15-5/16X10-13/16X32
040401064 O-RING,VT, 3.887 O.D.X.139 TIDE A-1812 SU--SECQ5 8.00 63.52 C
040401065 SIGHT GLASS, 2" LENS TIDE A-5374 SU--SECQ5 1.00 2.52 C
040401066 FGC RM VENT FAN MOTOR AUBURN USEM 5HP, 1800R SU-- 1.00 169.71 C
040402002 FILTER ELEMENT TIDE GC80360E03B SU--MEZ12 1.00 198.00 C
040402003 FUEL FILTER ELEMENTS (FG-366) PERRY 11724 SU--MEZ12 20.00 410.33 C
040402004 O-RING, CLOSURE GASKETS PERRY 14973 SU--SECQ2 2.00 47.76 C
040402005 O-RING TIDE ORC12B SU--SECQ5 2.00 43.30 C
040402006 FILTER ELEMENT PLENTY 10273K99 SU--MEZ12 3.00 594.00 C
040402007 FILTER O-RING PLENTY 001-161 SU--MEZ12 2.00 48.00 C
040403028 X.X. XXXXX, XXXXX, XXXX XXXX X-0000 XX--XXXX0 3.00 58.74 C
040403029 NO FLOW SWITCH TIDE A-0505 SU--SECR3 1.00 453.74 C
?????3032 CONTROLLER ASSEMBLY - FGC NIBSCO 487369 SU--SECR3 1.00 1725.00 C
Page 10
SCHEDULE 1, Continued
12-09-97 Syracuse University Inventory Catalog
Spare Part Description Supplier # Supp Part # Location QOH at Loc Total Cost ABC Flag
---------- ----------- ---------- ----------- -------- ---------- ---------- --------
RECYCLE VALVE
040405001 HEAT XXXXXXXXX XXX XXXXXXX XXXX XXX00000 SU--SECR3 2.00 792.00 C
040405002 GASKET 5" X 3-9/16" X 1/32" XXXXXX XX-080-G2 SU--SECR4 1.00 5.00 C
040405003 GASKET 5" X 3-9/16" X 1" XXXXXX XX-080-N SU--SECR4 1.00 5.00 C
NEOPRN
040405004 XXXXX XXXX X-XXXX 0" X 0/0" XXXXXX XX-223-T SU--SECR4 1.00 114.00 C
040407001 REPAIR KIT FOR VALVE/ACT TIDE 18014 SU--SECR5 1.00 849.75 C
040407002 BOOT-PEAKING VALVE CJNOLT 000-00000-000 SU--SECS3 1.00 420.75 C
040407003 ACTUATOR REPAIR KIT-RECYCLE NIBSCO 433214 ACTUATOR SU--SECS3 2.00 130.00 C
VALVE
040407004 ACTUATOR SPRING-RECYCLE VALVE NIBSCO 415295 ACTUATOR SU--SECS3 2.00 174.00 C
040407005 RECYCLE VALVE/ NUT-HEXLOCK NIBSCO 485543 SU--SECS3 1.00 6.60 C
3/8-24
040407006 RECYCLE VALVE/ NIBSCO 485544 SU--SECS3 1.00 29.30 C
LEVER-POSITIONER
040407007 RECYCLE VALVE/ PIN STROKE NIBSCO 485545 SU--SECS3 2.00 64.00 C
ADJUSTING
040407008 RECYCLE VALVE/ NUT HEXLOCK NIBSCO 485546 SU--SECS3 2.00 18.00 C
1/4-28
040407009 RECYCLE VALVE/ BRACKET-MOTION NIBSCO 425872 SU--SECS3 2.00 39.00 C
FRONT
040407010 RECYCLE VALVE, ACTUATOR STEM NIBSCO 411978 - XXXXXX XX--SECS3 1.00 110.00 C
LOWER
040408001 SHAFT OIL SEAL TIDE A-3911 SU--SECQ5 1.00 3.31 C
????08002 SWITCH, LUBE OIL NO FLOW TIDE 815-S SU--SECR3 1.00 160.00 C
????08003 XXXXX. PRESSURE SWITCH TIDE 9012-GCW-1 SU--MCCCABC 1.00 140.61 C
040408004 TERMINAL CHECK VALVE TIDE A-0281 SU--SECQ5 2.00 46.32 C
040408005 XXXXX. TEMPERATURE SWITCH TIDE 9025-GKW5-A12 SU--MCCCABC 1.00 142.76 C
040408006 OIL TEMPERATURE SWITCH TIDE 9025-GKW3-A12 SU--MCCCABC 1.00 130.00 C
040408007 F.F. LUBE SLOT COVER GASKET TIDE A-5255 SU--SECQ5 2.00 36.54 C
040408008 BLOW-OUT ASSY, SPECIFY DISC TIDE A-0080 SU--SECQ5 1.00 8.04 C
040408009 F.F. LUBRICATOR PUMP 0/0 XXXXXX XXXX X-0000 XX--XXXX0 1.00 172.21 C
040408010 BLOW-OUT DISC, 3250 PSIG, TIDE A-0124 SU--SECQ5 7.00 8.05 C
PURPLE
040408011 VIBRATION SWITCH TIDE VS-2 SU--MCCCABC 1.00 86.00 C
040408014 SPKT, RLR, CHAIN, F.F.LUBR, 28T TIDE A-3873 SU--SECR3 1.00 134.11 C
040408015 OIL PRESSURE SWITCH TIDE 9012-XXX-2 SU--MCCCABC 1.00 71.38 C
040408020 DIRECT CURRENT ALARM RITEC DCA/2X4-20HA/DH SU--MCCCABD 1.00 405.00 C
040408021 END CAP, L.O. COOLER - FGC GLAUBE 41831 SU--SECR3 1.00 59.00 C
040501001 SUPPLY GAS REG - ESDV-1 NORTH 1301F-2 SU--SECL5 1.00 97.20 C
040501003 CONTROL VALVE FOR ESDV-1 PHENIX VAP-3301-316-33 SU--SECL5 1.00 519.20 C
040501004 CONTOL-SOLONOID VALVE, ESDV-1 PHENIX VGA-3422-316-35 SU--SECL5 1.00 702.30 C
040501005 CONTROL VALVE, 320PSI SET, CJNOLT 00-0000-0000 32 SU--SECL5 1.00 329.00 C
ESDV-1
040501006 RELIEF VALVE, ESDV-1 CJNOLT B8CPA-2-125 125 SU--SECL5 1.00 47.00 C
040501007 MICRO-KLEAN FILTER CARTRIDGE, NORTH 1F966406992 SU--SECL5 1.00 11.52 C
ESDV-1
040501009 XX XXXX XXXXXXX, XXX XXXX, 0", XXXXXX 300-B5-ORANGE SU--SECL5 10.00 249.50 C
SINGLE
040503001 PLUG CVSALE 3840.150 SU--SECN3 1.00 504.75 C
????03002 PKG SET CVSALE 55865.925 SU--SECN5 1.00 24.65 C
Page 11
SCHEDULE 1, Continued
12-09-97 Syracuse University Inventory Catalog
Spare Part Description Supplier # Supp Part # Location QOH at Loc Total Cost ABC Flag
------------ ------------------ ---------- --------------- ------------ ---------- ---------- --------
040503003 GASKET, NONMETALIC CVSALE 1886.925 SU--SECN5 1.00 6.38 C
040503004 GDE LINERS CVSALE 5386.927 SU--SECN5 2.00 18.42 C
040503005 PISTON BACKUP RING CVSALE 64273.925 SU--SECN5 2.00 123.36 C
040503006 O-RING, UPR SLEEVE CVSALE 5412.651 SU--SECN5 2.00 127.44 C
040503007 SOFT SEAL CVSALE 71885.976 SU--SECN5 1.00 74.12 C
040503008 SOLENOID 24VDC CVSALE 78001.999 SU--SECN4 2.00 438.96 C
040503009 O-RING, YOKE BUSHING CVSALE 1181.650 SU--SECN5 2.00 2.28 C
040503010 CAP LINER CVSALE 1885.676 SU--SECN4 1.00 52.86 C
040503011 O-RING, YOKE BSHG CVSALE 1337.650 SU--SECN5 2.00 2.80 C
040503012 SEAT GASKET CVSALE 1794.925 SU--SECN5 2.00 21.16 C
040503013 GASKET METAL CVSALE 1824.606 SU--SECN5 5.00 6.15 C
040503014 SEAT RING CVSALE 1210.150 SU--SECN4 1.00 204.57 C
040503015 SEAT GASKET CVSALE 1944.925 SU--SECN5 1.00 27.86 C
040503016 GASKET NON-METALLIC CVSALE 49671.813 SU--SECN5 1.00 20.78 C
040503017 POSITIONER CVSALE 63934.999 SU--SECN3 1.00 465.68 C
040503018 O-RING, ADAPTOR CVSALE 43102.651 SU--SECN5 1.00 5.23 C
040503019 SLDG SEAL ASSY CVSALE 62471.990 SU--SECN5 1.00 108.97 C
040503020 SEAT RING CVSALE 4682.150 SU--SECN4 1.00 204.57 C
040503021 GUIDE LINER CVSALE 6340.927 SU--SECN4 2.00 114.38 C
040503022 O-RING, YOKE CVSALE 1182.650 SU--SECN5 2.00 19.40 C
040503023 O-RING, STEM CVSALE 1183.650 SU--SECN4 2.00 1.40 C
040503024 BONNET GASKET CVSALE 1943.925 SU--SECN4 1.00 30.76 C
040503025 O-RING, YOKE BUSHING CVSALE 1113.650 SU--SECN4 2.00 1.68 C
040503026 SEAT RING CVSALE 3468.150 SU--SECN4 1.00 172.70 C
040503027 O-RING, YOKE HANDWHEEL CVSALE 5494.650 SU--SECN4 1.00 1.23 C
040503028 SEAT GASKET CVSALE 1704.925 SU--SECN4 1.00 8.14 C
040503029 PLUG CVSALE 1664.150 SU--SECN3 1.00 628.11 C
040503030 BONNET GASKET CVSALE 1705.925 SU--SECN4 1.00 11.38 C
040503031 O-RING, YOKE BUSHING CVSALE 1718.650 SU--SECN4 3.00 4.62 C
040503032 PLUG CVSALE 1510.150 SU--SECN3 1.00 628.11 C
040503033 PKG SET CVSALE 20746.925 SU--SECN4 1.00 10.20 C
040503034 PKNG SET CVSALE 20758.925 SU--SECN4 1.00 25.36 C
040503035 SEAT GASKET CVSALE 2717.925 SU--SECN4 2.00 46.22 C
040503036 O-RING, SLEEVE CVSALE 5442.651 SU--SECN4 1.00 46.00 C
040503037 ADJ SCREW GASKET CVSALE 1435.655 SU--SECN4 1.00 1.05 C
040503038 ADJ SCREW GASKET CVSALE 1501.655 SU--SECN4 1.00 .67 C
040503039 SEAT RING CVSALE 2027.150 SU--SECN4 1.00 886.14 C
040503040 AIR FILTER CVSALE 78245.999 SU--SECN4 2.00 136.02 C
040503041 VALVE, 3-WAY CVSALE 34747.402 SU--SECN4 1.00 106.67 C
040503042 PISTON BACK UP RING CVSALE 55220.925 SU--SECN4 1.00 15.39 C
040503043 O-RING, YOKE AND PISTON CVSALE 1114.650 SU--SECN4 8.00 47.84 C
040503044 O-RING, ACT STEM CVSALE 1312.650 SU--SECN4 3.00 2.88 C
040503045 PLUG CVSALE 30224.150 SU--SECN3 1.00 1586.20 C
040503046 SEAT RING CVSALE 54812.419 SU--SECN5 2.00 187.10 C
040504005 Y-STRAINER - OOORANT STREAM T600SS-0050, 80 SU--SECL5 1.00 49.20 C
040506001 PRESSURE SWITCH (1000 psi) CPICON PPS-N7-G-S-07-X SU--MCCCABC 1.00 396.50 C
050101001 CEM PANEL COOLING FAN NEWARK 026165 SU--MCCCABA 1.00 88.83 C
050101002 MUFFLER, PUREGAS HEATLESS MOBILE P-400-399 SU--MCCCABA 1.00 16.50 C
DRYER
050102001 GRAPHITE FERRULES (PACK OF 10) ENVIRO 335-00757 SU--MCCCABA 10.00 420.00 C
050102002 PROBE RETAINER SPRING ENVIRO 335-00028 SU--MCCCABA 1.00 10.54 C
Page 12
SCHEDULE 1, Continued
12-09-97 Syracuse University Inventory Catalog
Spare Part Description Supplier # Supp Part # Location QOH at Loc Total Cost ABC Flag
--------- ---------------------------- ---------- ------------ ---------- ------------ ---------- ---------
050102003 QUARTZ WOOL (LOT) ENVIRO 510-00021 SU--MCCCABA 1.00 9.00 C
XXXXXX 400P-0009
050102004 ANTI-SEIZE COMPOUND (SILVER) ENVIRO 220-00509 SU--MCCCABA 1.00 225.58 C
050102006 PROBE FILTER SCREEN ENVIRO 355-00029 SU--MCCCABA 1.00 21.48 C
050102007 ORIFICE, 150ml ENVIRO 340-00769 SU--MCCCABA 2.00 982.00 C
XXXXXX 400-0036-150ML
050104003 PRECISION REGULATOR ENVIRO 410-00385 SU--MCCCABA 1.00 242.00 C
050104004 3-WAY PURGE SOLENICO ENVIRO 430-00057 SU--MCCCABA 1.00 141.85 C
050104005 COIL 53, VOC ENVIRO 405-03468 SU--MCCCABA 1.00 184.51 C
050104006 PRESSURE REGULATOR ENVIRO 410-00037 SU--MCCCABA 1.00 63.84 C
050104008 0.5m FILTER (M16-02-FMO) ENVIRO 395-00387(M16-0 SU--MCCCABA 1.00 74.98 C
050104009 O.5m FILTER (M10-02-FOO) ENVIRO 395-00387(M10-0 SU--MCCCABA 1.00 74.98 C
050104010 2-WAY CAL SOLENOID ENVIRO 430-02351 SU--MCCCABA 4.00 230.50 C
POWERQ 5220165NGB 120/
050104017 0.5m IN-LINE FILTER (47mm ENVIRO 210-00233 SU--MCCCABA 9.00 10.95 C
GLASS)
050104018 0.5m IN-LINE FILTER (47mm XXXXXX 400P-0011 SU--MCCCABA 5.00 450.00 C
TEFLON)
050104019 FILTER, XXXXXXXXX, XXX XXXXXX 0XX00 XX--XXXXXXX 6.00 34.44 C
050106002 O-RING (PKG OF 10) ENVIRO 115-01510 SU--MCCCABA 1.00 14.21 C
050106003 THREE WAY SOLENOID VALVE ENVIRO 115-03234 SU--MCCCABA 1.00 417.28 C
050106004 CAPILLARY (0.08ml OZONE) ENVIRO 055-01272 SU--MCCCABA 1.00 47.91 C
050106007 SAMPLE PUMP ENVIRO 048-03296 SU--MCCCABA 1.00 1365.00 C
050106008 OZONATOR ASSEMBLY ENVIRO 048-03416 SU--MCCCABA 1.00 644.42 C
050106009 3-WAY SAMPLE SELECT SOLENOID ENVIRO 430-00055 SU--MCCCABA 1.00 639.56 C
050107001 CAPILLARY, 18 mil ENVIRO 015-01154 SU--MCCCABA 1.00 48.92 C
050107002 SAMPLE PUMP ENVIRO 360-00524 SU--MCCCABA 2.00 969.58 C
050107003 FUSE, 2 amp S/B (PKG/5) ENVIRO 140-00066 SU--MCCCABA 5.00 20.50 C
050107004 FUSE ENVIRO 025-01970 SU--MCCCABA 5.00 25.00 C
050107005 KNF INTERNAL PUMP ENVIRO 015-01237 SU--MCCCABA 1.00 280.00 C
THERMO KNF-8550
050107006 SOURCE, IR ENVIRO 015-01245 SU--MCCCABA 2.00 66.00 C
THERMO 7361
050107007 RESISTOR ENVIRO 015-01234 SU--MCCCABA 1.00 633.86 C
050107008 P.C. BOARD, INPUT ENVIRO 015-01226 SU--MCCCABA 1.00 1264.41 C
050107009 P.C. BOARD, D/A ENVIRO 015-01224 SU--MCCCABA 1.00 570.46 C
050109001 OMRON SWITCHING RELAY RLSTON 0MRON MK3P5-S 1 SU--MCCCABA 2.00 29.50 C
050109002 11 PIN OCTAL BASE FOR OMRON RLSTON 11 PIN OCTAL BA SU--MCCCABA 1.00 10.00 C
MK3P5-S
060103022 RO 2.125" SEAL SEALIN 341OM-127727 SU--SECQ2 2.00 946.00 C
060103025 RETAINING RING GOULDS 58102-118 SU--SECP4 1.00 1.75 C
060103026 BALL BEARING I.B. ESTABR 8050-20760 SU--SECP4 1.00 12.81 C
060103027 SLEEVE NUT GOULDS RBO1015A-1203 SU--SECP3 2.00 379.40 C
060103028 SHAFT SLEEVE GOULDS COO457A-1203 SU--SECP3 2.00 635.60 C
060103029 WEAR RING GOULDS CO1293A06-1000 SU--SECP3 2.00 228.00 C
060103032 GLAND GASKET GOULDS A01437A08-5162 SU--SECP3 2.00 24.22 C
060103033 BALL BEARING O.B. GOULDS 8049-30600 SU--SECP3 2.00 103.60 C
060103034 CITY WATER PUMP COUPLING GOULDS REXNORD E30 SU--SECL3 1.00 352.00 C
060103035 OILER, #5, 8 OX. CAP GOULDS 072531-14-8683 SU--SECP3 1.00 76.88 C
060104001 PKG SET CVSALE 56138.925 SU--SECN5 1.00 12.11 C
060104002 POSITIONER CVSALE 63939.999 SU--SECN3 1.00 873.80 C
Page 13
Suracuse University Inventory Catalog
Spare part Description Supplier # Supp Part # Location QOH at Loc Total Cost ABC Flag
---------- ----------- ---------- ----------- -------- ---------- ---------- --------
060104003 SEAT GASKET CVSALE 64345.925 SU--SECN5 1.00 25.39 C
060104004 O-RING, ADAPTOR CVSALE 32395.925 SU--SECN4 1.00 3.08 C
060104005 SOFT SEAT INSERT CVSALE 50956.925 SU--SECN5 1.00 58.63 C
060111001 TURBIDITY CELL ROSEMT 2120 SU--MCCCABB 1.00 301.00 C
060206002 XXXXXXX XXXXXX MIXER (PILOTED BURHAN 1.938E SU--SEC03 2.00 420.00 C
BEARING)
060207001 DA-M/UP PUMP COUPLING GOULDS REXNORD ES10 SU--SECL2 1.00 181.00 C
060208024 1" SPIDER COMPRESSOR AQUATE A484IC SU--SECQ2 1.00 14.00 C
060208025 SPIDER TO STEM PIN RMNEWE 2497 SU--SECQ3 2.00 18.00 C
060208026 TUBE NUT KEY, 6" VLV XXXXXX 0000 SU--SECQ3 3.00 21.00 C
060208027 NUT, TUBE NUT, 6" VLV XXXXXX 0000 SU--SECQ3 3.00 36.00 C
060208028 2" SPIDER COMPRESSOR XXXXXX 0000 SU--SECQ2 1.00 25.00 C
060208030 6" SPIDER COMPRESSOR XXXXXX 0000 SU--SECQ2 4.00 488.00 C
060208031 #12 ACTUATOR DIAPHRAM XXXXXX 00000 SU--SECQ2 1.00 20.00 C
060208032 BONNET GASKET CVSALE 1233,868 SU--SECN5 1.00 44.72 C
060208034 3/4" VITON DIAPHRAM REPAIR KIT XXXXXX 00000 SU--SECQ2 1.00 38.00 C
060208035 O-RING, YOKE CVSALE 1184,650 SU--SECN5 2.00 14.34 C
060208037 4" EPDM DIAPHRAM REPAIR KIT RMNEWE 1464 SU--SECQ3 2.00 138.00 C
060208038 6" EPDM DIAPHRAM REPAIR KIT RMNEWE 1649 SU--SECQ3 1.00 198.00 C
060208040 #101 ACTUATOR DIAPHRAM XXXXXX 0000 SU--SECQ3 1.00 147.00 C
060208041 4" VITON DIAPHRAM REPAIR KIT RMNEWE 1448 SU--SECQ3 1.00 365.00 C
060208043 6" BUTTERFLY VLV XXXXXX XX000XXX SU--SECP1 1.00 137.50 C
060208044 3" VITON DIAPHRAM REPAIR KIT RMNEWE 1259 SU--SECQ3 4.00 1040.00 C
060208045 2" VITON DIAPHRAM REPAIR KIT RMNEWE 890 SU--SECQ2 1.00 140.00 C
060208047 1" VITON DIAPHRAM REPAIR KIT RMNEWE 5971 SU--SECQ2 1.00 63.00 C
AQUATE A1795IC
060208049 1.5" VITON DIAPHRAM REPAIR KIT RMNEWE 669 SU--SECQ2 1.00 61.00 C
060208052 #75 ACTUATOR DIAPHRAM XXXXXX 0000 SU--SECQ3 1.00 101.00 C
060208056 #50 ACTUATOR DIAPHRAM XXXXXX 0000 SU--SECQ3 1.00 79.00 C
060208058 2" TEMP REG VALVE RITEC XXXX 802 SU--SECS4 1.00 2033.50 C
060208062 BUTTERFLY VALVE 2" JTLYNN S30/114-2" SU--SECQ4 1.00 90.60 C
060208063 BUTTERFLY VALUE 3" JTLYNN S30/114-3" SU--SECQ4 2.00 224.00 C
060208064 PNEUMATIC ACTUATOR 4" JTLYNN 91-1004-21310-5 SU--SECQ4 1.00 697.00 C
060208065 BUTTERFLY VALVE 4" JTLYNN S30/114-4" SU--SECQ4 2.00 278.00 C
060208066 PNEUMATIC ACTUATOR 3" JTLYNN 91-0805-21310-5 SU--SECQ4 1.00 560.00 C
060208067 PNEUMATIC ACTUATOR 2" JTLYNN 91-0605-21310-5 SU--SECQ4 1.00 438.00 C
060208068 4", 3", & 6" SIGHT GLASS, ITT RMNEWE 2145 SU--SECQ3 3.00 9.00 C
VALVES
060208069 1 1/2" SIGHT GLASS, ITT VALVES RMNEWE 2144 SU--SECQ3 6.00 18.00 X
000000000 0", 0", & 0" XXXX, XXX VALVES RMNEWE 2027 SU--SECQ3 5.00 80.00 C
060208071 1 1/2" CAGE, ITT VALVE RMNEWE 2026 SU--SECQ3 6.00 84.00 C
060208076 SEAT, VALVE, 2" BUTTERFLY AQUATE A200292801461IC SU--SECQ4 1.00 55.00 C
060209001 XXXXXXX XXXXX XXX/XXX XXXXX XXXXXX 000-X XX--XXXXXXX 4.00 360.00 C
CARD
060209002 ACID DRIVE ACC/DEC DRIVE CARD EXTRON 182-T SU--MCCCABA 2.00 192.00 C
060209003 ACID/CAUSTIC INPUT/OUTPUT CARD EXTRON 1817-0410 SU--MCCCABA 2.00 256.00 C
060209004 X-00# X/X XXXXXX XXX 0000-X-00-XX XX--XXXXXXX 2.00 775.00 C
060209037 ISOLATED INPUT MODULE BALDWI 1771-ID SU--MCCCABC 1.00 137.97 C
060209039 000 XXX XX XXXX XXXXXX 0000-XXX XX--XXXXXXX 1.00 236.52 C
060209040 SERIES B REMOTE I/O ADAPTER BALDWI 1771-ASB SU--MCCCABC 1.00 689.85 C
060209041 PH XMITTER ROSEMT SCL-P014-M2 SU--MCCCABB 1.00 710.00 C
060209042 DELTA P IND SWITCH ACI 140-SA-00-FA SU--MCCCABC 1.00 452.50 C
060209043 COMMUNICATIONS I/F MODULE BALDWI 1785-KE SU--MCCCABC 1.00 1780.47 C
060209044 ANALOG OUTPUT MODULE BALDWI 1771-0FE SU--MCCCABC 1.00 916.52 C
060209045 ISOLATED OUTPUT MODULE BALDWI 1771-DD SU--MCCCABC 1.00 197.10 C
060209046 O-RING & SEAL KIT ROTORK 118/3 SU--SECO3 1.00 317.00 C
060209047 ANALOG INPUT MODULE BALDWI 1771-IFE SU--MCCCABC 1.00 916.52 C
060209048 000 XXX XX XXXX XXXXXX 0000-XXX XX--XXXXXXX 1.00 328.50 C
060209049 XXXXXXXX XXXXX XXXXXXXX XXXXXX 0000-X0 XX--XXXXXXX 1.00 597.87 C
060209050 CONDUCTIVITY METER ROSEMT SCL-C001-M2 SU--MCCCABB 1.00 675.00 C
060209051 TEMP IND SWITCH ACI 802-6BS-S101-M3 SU--MCCCABB 1.00 426.55 C
060209053 VSPH ELECTRODE ROSEMT VSPH SU--MCCCABB 2.00 520.00 C
060209054 CONCENTRATION PROBE ROSEML CEL-470 SU--MCCCABB 1.00 455.00 C
060209055 CAUSTIC LEVEL TRANSMITTER ROSEMT 1151LT-5EA//QA1 SU--MCCCABB 1.00 1071.00 C
060209056 ACID LEVEL TRANSMITTER ROSEMT 1151LT-5EC//QA1 SU--MCCCABB 1.00 1092.25 C
060209082 CONDUCTIVITY CELL (IN-LINE) ROSEMT 05010784263 SU--MCCCABB 2.00 590.00 C
STEAMP 05010784263
060209086 0-10% CONCENTRATION PROSE ROSEMT CEL-470 SU--MCCCABB 2.00 910.00 C
060209087 LINK, FOXBORO CONTROLLER FOXBOR X0101BE SU--MCCCABA 1.00 29.00 C
060212002 O-RING, BEARING HOUSING XXXXXX 131-SBR SU--SECP1 1.00 8.00 C
ADAPTER
060212003 MECH SEAL DURAMET MOO P-50, SEALIN 149699 SU--SECP1 1.00 718.00 C
B/H 149699, 1 7/8"
060212004 BEARING X.X. XXXXXX 121-STEEL SU--SECP1 1.00 117.00 C
060212005 REAR COVER GASKET XXXXXX 107-NAH SU--SECP1 1.00 13.00 C
060212006 OIL SEAL X.X. XXXXXX 129-TFSR SU--SECP1 1.00 19.00 C
060212007 OIL SEAL X.X. XXXXXX 118-TFSR SU--SECP1 1.00 15.50 C
060212008 BEARING X.X. XXXXXX 120-STEEL SU--SECP1 1.00 50.00 C
060212009 IMPELLER GASKET XXXXXX 104-TFR SU--SECP1 1.00 18.00 C
060212010 O-RING, BRG XXXX XXXXXX 2018-NITRILE SU--SECP1 2.00 8.00 C
060214002 PULSEFEEDER FOR 7660 SIEWER KPGBCBTAEEE SU--SECM3 2.00 3310.00 C
060214004 TEFLON XXXXXXXXX-0000 XXXXXX X000000-XXX XX--XXXX0 1.00 240.40 C
060214005 TEFLON O-RINGS 0000\0000 XXXXXX X000000-XXX XX--XXXX0 21.00 366.93 C
060214006 AUTO BLEEDER VLV (NUT & SIEWER W203594-000 SU--SECM3 1.00 3.10 C
FERRULE)
060215002 KOPKIT FOR 0000 XXXXXX XXXXXXXXXXX XX--XXXX0 2.00 1643.00 C
060215004 TEFLON DIAPHRAGM 0000 XXXXXX XX00000-XXX XX--XXXX0 1.00 222.10 C
060215005 7660 RELIEF VALVE CASINGS SIEWER W203376-000 SU--SECM3 2.00 2.00 C
060216001 TUBE BUNDLE AND GASKETS (HEAT XXXXXX 00000 SU--MEZ 1.00 2050.00 C
EXCHANGER)
060217002 CENTERLINE CHECK VALVE SPRINGS L&S 125-31674/38307 SU--SECM2 3.00 66.00 C
060217003 CENTERLINE CHECK VALVE WASHERS L&S 000-00000-00 SU--SECM2 11.00 13.75 C
060217004 PLATES, CHECK VLV, 316SS L&S 000-00000-00 SU--SECM2 2.00 480.00 C
SET(2)
060217008 GASKET, IMPELLER XXXXXX 2Z104 SU--SECM2 1.00 16.00 C
060217009 GASKET, XXXX XXXXX, 0" XXXXXX XX000 XX--XXXX0 1.00 16.00 C
060217011 SEAL, OIL, X.X. XXXXXX 2Z129 SU--SECM2 1.00 17.00 C
060217012 O-RING, BEARING CAP XXXXXX 2K201B SU--SECM2 2.00 8.00 C
060306002 DIAPHRAGMS, FIRE SPRINKLER DAVISU 06675A SU--SEC13 4.00 560.00 C
060801001 DISC, BRONZE,(2 HALVES) PIPING 6-71-DISC-BRON SU--SECM2 1.00 130.65 C
060801002 SHAFT, 316SS, CHECK VALVE PIPING 6-71-SHAFT-316S SU--SECM2 3.00 33.15 C
060805001 O-RING, ADAPTOR CVSALE 32396.925 SU--SECN4 1.00 3.58 C
SCHEDULE 1, Continued
12-09-97 Syracuse University Inventory Catalog
Spare Part Description Supplier # Supp Part # Location OOH at Loc Total Cost ABC Flag
---------- ------------------------------- ---------- ---------------- ------------ ---------- ---------- --------
060805002 SOFT SEAT INSERT CVSALE 53753.925 SU--SECN5 1.00 124.96 C
060805003 O-RING, ADAPTOR CVSALE 43102.925 SU--SECN4 1.00 4.83 C
060805004 PKG. SET CVSALE 56142.925 SU--SECN4 1.00 21.34 C
060805005 SEAT GASKET CVSALE 64335.925 SU--SECN5 1.00 97.82 C
060805006 SEAT GASKET CVSALE 64414.925 SU--SECN5 1.00 39.51 C
060805007 SOFT SEAT INSERT CVSALE 53865.925 SU--SECN5 1.00 150.09 C
060805008 SLDG SEAL ASSY CVSALE 55586.999 SU--SECN5 1.00 121.30 C
060805010 BACKUP RING CVSALE 64006.925 SU--SECN5 2.00 85.46 C
060805011 BONNET GASKET CVSALE 1793.925 SU--SECN5 2.00 43.18 C
061001001 TEFLON DIAPHRAGM 000 XXXXXX X000000-XXX XX--XXXX0 2.00 186.80 C
061001002 TEFLON O-RINGS 000 XXXXXX X000000-XXX XX--XXXX0 6.00 28.80 C
061001003 000 XXXXXX XXX XXXX XXXXXX X000000-000 XX--XXXX0 3.00 27.00 C
061001005 880 STROKE ADJ X-XXXX XXXXXX X000000-XXX XX--XXXX0 3.00 1.20 C
061001006 STROKE ADJ BARRELS FOR 000 XXXXXX X00000-000 XX--XXXX0 3.00 3.00 C
061001007 STROKE ADJ SCREWS FOR 000 XXXXXX X000000-000 XX--XXXX0 3.00 3.00 C
061003001 CHEMICAL MIXER, IMPELLER NEPTUN 000514 SU--SECN3 1.00 25.00 C
061003002 CHEMICAL MIXER, COUPLING NEPTUN SU--SECN3 1.00 1.00 C
061003003 CHEMICAL MIXER IMPELLER, 5/8" NEPTUN 000539 SU--SECN3 1.00 81.70 C
061004001 PULSEFEEDER FOR 880 SIEWER KPDRABFACCC SU--SECN3 2.00 927.67 C
061101001 PH ELECTRODE FOR XXXXXXX XXXXX CYCLOP 2772527 SU--MCCCABA 4.00 357.14 C
SAMPLE PANEL
061101013 L&N D.O. SENSOR AFTA CAT#7931-30 SU--SECI4 1.00 696.00 C
061101014 L&N PH SENSOR XXXXXX 0000-00 XX--XXXXXXX 1.00 1009.38 C
061101015 L&N PH SENSOR(PROBE) AFTA 117486 SU--MCCCABA 1.00 149.00 C
CYCLOP 2772527
061101016 L&N PROBE MOUNT (D.O. SENSOR) AFTA 063336 SU--SECI3 1.00 40.00 C
061102003 CONDUCTIVITY SENSOR JOHMAR 1648-24 SU--SECI3 2.00 680.60 C
061102004 SAMPLE COOLER GASKETS MODEL JOHMAR 1648-11 SU--SECJ3 1.00 3.25 C
25040
061102005 ROTANETER 20-300 CC/MIN ACI 2-RMA-34-SSV SU--SECJ3 7.00 149.80 C
061102006 SS-4C-50 NUPRO RELIEF VALUE JOHMAR 1648-5 SU--SECJ3 1.00 62.40 C
061102007 NUPRO FILTERS JOHMAR 1648-6 SU--SECJ3 1.00 9.90 C
061102011 ASCO REPAIR KIT JOHMAR 1648-15 SU--SECJ3 1.00 38.20 C
061102013 SAMPLE COOLER GASKETS MODEL JOHMAR 1648-10 SU--SECJ3 1.00 3.55 C
37540
061102016 CONDUCTIVITY SENSOR JOHMAR 1648-25 SU--SECI3 3.00 1016.40 C
061102017 ASCO HIGH TEMP SWITCH JOHMAR 1648-16 SU--SECR2 1.00 249.15 C
061102021 CONDUCTIVITY SENSOR JOHMAR 1648-23 SU--SECI3 2.00 676.10 C
061102029 SAMPLE CELL LIGHT SHIELD HACH 45994-00 SU--DEMIN 3.00 25.50 C
061102030 SAMPLE CELLCOVER ASSEMBLY HACH 45427-50 SU--DEMIN 3.00 111.38 C
061103002 RELIEF VALUE XXXXXX H202-35 SU--SECL5 1.00 54.00 C
061103003 PRESSURE, REGULATOR XXXXXX 67AFR-226 SU--SECL5 1.00 61.20 C
061103004 PRESSURE, REGULATOR XXXXXX 95L-4 SU--SECL5 1.00 219.60 C
061103005 PRESSURE, REGULATOR XXXXXX 1301F-1 SU--SECL5 1.00 90.00 C
061103007 2 WAY DIAPHRAM SOLENOID VLV, HACH 44948-00 SU--MCCCABA 1.00 62.97 C
SILICA ANALYZER
061202001 O-RING, PUMP COVER GOULDS C02495A358-5308 SU--SECP4 1.00 39.90 C
061202002 IMP O-RING GOULDS C02495A28-5308 SU--SECP4 1.00 10.92 C
061202004 BEARING LOCKNUT GOULDS 8601-0006 SU--SECP4 1.00 4.06 C
061202005 U CUP GOULDS 402108811 SU--SECP3 1.00 16.10 C
061202006 COLUMN ASSEMBLY BEARINGS GOULDS 0802056A03-6470 SU--SECP3 4.00 1162.80 C
061202007 O-RING, BRG MSG GOULDS C02495A236-5302 SU--SECP3 1.00 1.82 C
061202008 CHEM SUMP MOTOR HUB MIDWAY 6JX1HUB SU--SECL1 1.00 9.58 C
061202009 CHEM SUMP MOTOR HUB MIDWAY 6JX1 1/BHUB SU--SECL1 1.00 9.58 C
061202010 CHEM SUMP COUPLING INSERT MIDWAY 6JE INSERT SU--SECL1 1.00 10.00 C
061202011 VALUE, ANGLE TEMP RELIEF, FWWEBB WATTS40XL-3/4-T SU--SECI4 2.00 109.32 C
SAMPLE COOLER
061204003 CONVERTOR, PULSE/ANALOG TRANS ACT 13080 SU--MCCCABB 1.00 265.00 C
SEWER FLOW COGEN
070204001 BEARING, BALL 3196 PMP ESTABR 8049-30600 SU--SECM3 1.00 .00 C
070204003 DIAPHRAGN, M-15 WILDEN PUMP GLAUBE 00-0000-00 SU--SECM1 2.00 70.00 C
070204004 BALLS, VALVE GLAUBE 00-0000-00 SU--SECM1 4.00 44.00 C
070204005 SEAT, VALVE, M15 GLAUBE 00-0000-00 SU--SECM1 4.00 25.20 C
070204006 SHAFT, PUMP GLAUBE 00-0000-00 SU--SECM1 1.00 38.00 C
070204007 O-RING, SHAFT GLAUBE 00-0000-00 SU--SECM2 14.00 7.00 C
070206002 SHAFT STUD GLAUBE T61F SU--SECM2 5.00 5.00 C
GLAUBE T61F
070206003 MUFFLER GLAUBE 70A SU--SECM2 1.00 20.50 C
GLAUBE 70A
070206005 BALL GLAUBE BN71 SU--SECM2 4.00 27.20 C
GLAUBE BN71
070206008 AIR VALVE GASKET GLAUBE P608 SU--SECM2 1.00 1.00 C
GLAUBE P608
071001001 O-RING, FILTER SEPARATOR TRIL 0663716800 SU--SECR5 4.00 150.72 C
071001002 SEPARATOR ELEMENT FILTER TRIL 1202741900 SU--SECR5 1.00 287.28 C
071001005 MOISTURE SEPARATOR O-RING TRIL 0000-0000-00 SU--SECR5 2.00 10.90 C
071001007 FITTING, NIPPLE TRIL 0000-0000-00 SU--SECR5 2.00 6.44 C
071001008 HOSE ASSEMBLY TRIL 0000-0000-00 SU--SECR5 1.00 27.84 C
071001012 TRANSDUCER, PRESSURE, PLANT TRIL 0000-0000-00 SU--SECR5 1.00 230.10 C
AIR COMPRESSOR
071001013 FUSE, 100 AMP RIL/ALCO AIR CITYEL TRS-100R SU--MCCCABC 5.00 88.00 C
COMPRESSOR
071004001 DEW POINT SENSOR COSA SHI9049 SU--MCCCABA 1.00 1200.00 C
071004002 KIT, O-RING, OIL SYSTEM TRIL 0000-0000-00 SU--SECR5 1.00 47.06 C
071004003 GASKET, OIL DRAIN PLUG TRIL 0000-0000-00 SU--SECR5 3.00 6.06 C
071004998 O-RING (WATER SEPERATOR) TRIL 0663714700 SU--SECR5 4.00 21.80 C
071005001 AFTERFILTER, PARTICULATE TRIL 511E SU--SECR2 2.00 258.50 C
071005002 OIL STOP VALVE SERVICE KIT TRIL 2901006400 SU--SECR2 1.00 15.13 C
071005003 MINIMUM PRESSURE VALVE SERVICE TRIL 2901006500 SU--SECR2 1.00 39.18 C
KIT
071005005 OIL FILTER TRIL 1613610500 SU--SECR2 10.00 244.44 C
071005006 INTAKE FILTER ELEMENT TRIL 1619279800 SU--SECR5 4.00 394.62 C
071005008 SOLENOID VALVE TRIL 1089050507 SU--SECR2 1.00 178.06 C
071005009 UNLOADING VALVE SERVICE KIT TRIL 2901007600 SU--SECR2 1.00 91.97 C
071005010 BUSHING XXXXXX 1E398535132 SU--SECM5 1.00 6.62 C
071005011 95M REPAIR KIT XXXXXX R95HX000042 SU--SECM5 1.00 130.00 C
071005012 REPAIR KIT XXXXXX R95LX000012 SU--SECM5 1.00 24.57 C
071005013 AIR TEK TP7715 EXHAUST VLV KIT TRIL IP7715 SU--SECN3 1.00 26.48 C
071005015 JOY AIR COMP OIL FILTER TRIL 01228337-001 SU--SECR4 9.00 130.34 C
071005019 JOY COMPRESSOR VALVE COVER TRIL 25BC505 SU--SECR4 8.00 28.80 C
GASKET
HOERBI 05937B05562X0
SCHEDULE 1, Continued
12-09-97 Syracuse University Inventory Catalog
Spare Part Description Supplier # Supp Part # Location QOH at Loc Total Cost ABC Flag
------------- ---------------------------- ---------- ----------- ----------- ---------- ---------- --------
071005023 GASKET, VALVE SEAT, XXX XXXX 25BC544 SU--SECR4 8.00 21.68 C
COMPRESSOR
HOERBI 25BC544
071005025 HEAD GASKET, XXXXX COMPRESSOR TRIL 211JGY715 SU--SECR5 2.00 110.67 C
HOERBI 211JGY715
071005026 HEAD GASKET, ALCO AIR TRIL 211JGY715 SU--SECR5 2.00 168.66 C
COMPRESSOR
071005028 PLATE, REACTION, JOY VALVE TRIL 01605076-002 SU--SECR4 8.00 30.72 C
HOERBI 01605076-002
071005029 PLATE, REACTION, JOY VALVE TRIL 01605076-001 SU--SECR4 8.00 20.40 C
HOERBI 01605076-001
071005030 GASKET, CAP NUT TRIL 25BC479 SU--SECR2 8.00 6.80 C
HOERBI 25BC479
071005031 SPRING, OUTER TRIL 01604843-0042 SU--SECR2 12.00 83.64 C
HOERBI 010604843-042
071005032 SPRING, MIDDLE TRIL 010604843-0041 SU--SECR2 12.00 55.08 C
HOERBI 010604843-0041
071005033 SPRING, INTER TRIL 01604843-0039 SU--SECR2 16.00 34.56 C
HOERBI 01604843-0039
071005034 DIAPHRAGM, SUCTION TRIL 01249294 SU--SECR2 4.00 34.00 C
HOERBI 01249294
080000002 XXXXXX 0XX XXXXX XXX XXXXXXXXX X&X 0000X00X00 XX--XXXX0 5.00 1.30 C
080000004 XXXXXX 0XX XXXXX XXX XXXXXXXXX X&X 0000X00X00 XX--XXXX0 5.00 1.30 C
PLUG
080000005 EXCITER, IGNITION S&S X00000X00 SU--SECB2 1.00 5441.80 C
080000006 PLUG, LPC BORESCOPE S&S 9697M19P01 SU--SECA2 2.00 70.50 C
080000007 PLUG BORESCOPE (COMBUSTOR) S&S 9135M62P01 SU--SECB2 3.00 134.60 C
080000008 PLUG 0XX XXXXX XXX X&X 0000X00X00 XX--XXXX0 1.00 373.00 C
080000009 PLUG, XXX, XXX XXXXXXXXX X&X 0000X00X00 XX--XXXX0 3.00 204.75 C
080000010 GASKET LPC/HPC BOLESCOPE PLUG S&S MS9373-021 SU--SECA2 2.00 4.04 C
080000011 PLUG, 2ND STAGE HPT S&S 9680M73G03 SU--SECA3 1.00 439.16 C
080000012 WASHER COMBUSTOR BORESCOPE S&S 9609M43P03 SU--SECB2 5.00 1.30 C
080000013 CABLE, POWER S&S L24932P01 SU--MCCCABD 2.00 3150.00 C
080000014 PLUG IGNITER S&S 9101M37P72 SU--MCCCABD 1.00 423.57 C
080101003 XXX XXXXX 0 XXXXXXX X&X 0000X00X00 XX--XXXX0 115.00 293.25 C
080101004 XXX XXXXX 0 XXXXXXX X&X 0000X00X00 XX--XXXX0 115.00 311.65 C
080103003 SENSOR, CIT (VG CONTROL) S&S L25061P01 SU--SECA2 1.00 12346.56 C
080103005 O-RING, RTD S&S J221P904-(A) SU--SECA3 4.00 1.60 C
080103006 O-RING, VSV FITTINGS S&S J221P908 SU--SECA3 24.00 11.52 C
080103007 VARIABLE GEOMETRY CONTROL S&S L24913P15 SU--SECA4 1.00 67797.19 C
080103009 O-RING, VSV FITTINGS S&S J221P906 SU--SECA2 24.00 9.36 C
080103010 GASKET, VG CONTROL S&S L28004P01 SU--SECA3 1.00 357.97 C
080103011 CONDITIONER, SIGNAL S&S 9040M58P02 SU--SEC B2 1.00 2960.15 C
080103013 VSV ACTUATOR BOLT S&S 9628M16P02 SU--SECA2 4.00 15.56 C
080103014 VSV ACTUATOR BRACKET NUT S&S 635E901P01 SU--SECA2 3.00 24.99 C
080103015 CONDITIONER, SIGNAL, VSV/VBV S&S 9040M58P02 SU--MCCCABD 1.00 1469.70 C
080104001 ACTUATOR VARIABLE BLEED VALVE S&S 9042M12P06 SU--SECB2 1.00 1958.04 C
080104002 VSV, BLACKET,/GROMMET, RUBBER S&S 9054M35P01 SU--SECA3 2.00 8.62 C
080104004 VSV DOOR NUTS GE 9629M48P06 SU--A4 14.00 80.50 C
080104006 TRANSMITTER, VSV ISOLATOR, S&S SCT/O-5VDC/4-20 SU--MCCCABD 1.00 355.20 C
XDCR-5842
080104007 CABLE, FEEDBACK, VBV S&S L24986P01 SU--SECA3 1.00 1263.05 C
080104008 CABLE, FEEDBACK, VSV S&S L24979P01 SU--SECA3 1.00 1674.32 C
080201001 SEAL, FUEL NOZZLE SEALIN 9016M30P02 SU--SECA3 67.00 2861.57 C
S&S
080201002 FUEL NOZZLE S&S L31736G09 SU--SECB2 4.00 17240.36 C
080201003 TMF SPLIT-LINE BOLTS GE J648P28A SU--SECA4 4.00 63.00 C
080202002 FILTER, WTR WASH S&S U20A10S SU--SECB3 2.00 12.66 C
080402005 COMBUSTION LINER S&S 9016M26G49 SU--SECB3 1.00 122694.00 C
080403002 RTD, FUEL GAS TEMP S&S 78R25C60A025T34 SU--MCCCABD 2.00 505.98 C
080403004 NUT, SHLDR BOLT S&S 9629M48P04 SU--SECB2 6.00 7.98 C
080403006 BOLT, SHLDR, ROD END BEARING S&S J864P019A SU--SECB2 5.00 .00 C
080403007 TUBE,J, FUEL NOZZLE S&S L35220G01 SU--SECA2 20.00 7772.80 C
080403008 BOLT, FUEL NOZZLE S&S J644P08O SU--SECA3 2.00 13.50 C
080403009 BOLT, FUEL NOZZLE S&S J644P060 SU--SECB2 7.00 47.25 C
080403010 PACKING, STIG (FUEL GAS) S&S J221P129 SU--SECA2 20.00 23.20 C
080403011 FUEL GAS MANIFOLD TURNBUCKLE S&S L24983GO5 SU--SECB2 8.00 1618.24 C
(BEARING ROD END
(R))L24983G05)
080403012 FUEL GAS MANIFOLD TURNBUCKLE S&S L24983GO6 SU--SECB2 7.00 1415.96 C
(BEARING ROD END(L))
L24983G06)
080403013 FUEL GAS MANIFOLD TURNBUCKLE S&S J864P018A ROD E SU--SECB2 14.00 355.46 C
(BOLT SHOULDER) J864P018A ROD
END
080403014 RTD, FUEL GAS TEMP, ROSEMT S&S 7SR25N00A020T34 SU--SECB2 2.00 404.92 C
080403016 BOLT, GAS/NOZZLE S&S MS9492-24 SU--SECB2 6.00 .00 C
080403017 WASHER, GAS/NOZZLE BOLT S&S AN96OC616 SU--SECB2 6.00 .00 C
080403018 XXXXXXX, XXX XXX, XXX X&X X00000X00 XX--XXXX0 3.00 .00 C
080403019 BRACKET, GAS MANIFOLD S&S L24972P03 SU--SECA3 2.00 .00 C
080403020 BRACKET, GAS MANIFOLD S&S L24972P04 SU--SECA3 4.00 .00 C
080403021 TUBE, J, NOZZLE STEAM S&S L35238GO1 SU--SECA2 6.00 4351.20 C
080501001 299987 S&S KIT (EXHAUST S&S 299987 S&S KIT SU--SECA4 1.00 4197.73 C
COLLECTOR ROPE SEAL)
080501003 TUBE, RIGHT, AIR, 7TH STAGE S&S X00000X00 SU--SECA4 4.00 9116.00 C
080601003 O-RING, RTD S&S J221P904 SU--SECA2 23.00 9.66 C
080603019 X-100 1.875" SEAL SEALIN 3196MT-109961 SU--SECQ2 2.00 2138.00 C
080603020 PUMP REPAIR KIT ESTABR R196MTPRKO SU--SECM2 1.00 191.67 C
080603021 GLYCOL PUMP COUPLING GOULDS REXNORD ES-4 SU--SECL2 1.00 104.00 C
080604001 PKG SET CVSALE 24244.516 SU--SECN4 1.00 45.92 C
080604002 RING, PISTON XXXXXX 1U23420512 SU--SECM5 1.00 25.20 C
080604003 BELLOWS, ASSEMBLY XXXXXX 16A6953XO12 SU--SECM5 1.00 30.87 C
080604004 SEAT RING XXXXXX 1U222846172 SU--SECM5 1.00 97.65 C
080604005 CAGE, WHISPER XXXXXX 2V502733272 SU--SECL5 1.00 1392.30 C
080604006 GASKET SET XXXXXX RGASKETX202 SU--SECM5 1.00 36.54 C
080604008 GAUGE, PRESSURE XXXXXX 1188577X012 SU--SECM5 1.00 9.80 C
080604009 PLUG/STEM XXXXXX 1V6579X0092 SU--SECM5 1.00 233.10 C
080604010 IND. CONTROLLER XXXXXX R4190X00C12 SU--SECM5 1.00 8.19 C
080604011 FLAPPER ASSEMBLY XXXXXX 29A9518X012 SU--SECM5 1.00 27.72 C
080701032 HYDRAULIC STARTER S&S 272127 SU--SECE5 1.00 1846.12 C
080701036 O-RING, HYD STARTER HOSE S&S MS9388-219 SU--SECA2 1.00 2.89 C
080701037 CHARGE PUMP VACUUM SWITCH S&S 180P4-4C6 SU--MCCCABD 1.00 258.24 C
SCHEDULE 1, Continued
12-09-97 Syracuse University Inventory Catalog
Spare Part Description Supplier # Supp Part # Location QOH at Loc Total Cost ABC Flag
---------- ----------- ---------- ----------- -------- ---------- ---------- --------
080701038 HYDRAULIC PUMP CTRL PRESS S&S 100P4-4C6R SU--MCCCABO 1.00 221.61 C
SWITCH
080701039 GASKET HYD STARTER S&S MS9139-01 SU--SECB2 1.00 1.90 C
080701040 O-RING, PACKING HYD STARTER S&S J221P222 SU--SEC82 50.00 69.00 C
080701041 CASE HIGH TEMPERATURE SWITCH S&S 100TC5-4C6 SU--MCCCABD 1.00 398.44 C
080701042 HYDRAULIC PUMP S&S AA4V125ELIR3C20 SU--SECC5 1.00 4658.30 C
080701043 FLUID FILTER ASSEMBLY (HMK05) S&S P165973 SU--SECD3 1.00 63.88 C
080701045 D/P VISUAL INDICATOR S&S P16-2696 SU--SECD2 1.00 10.40 C
080701046 CLUTCH, STARTER S&S 6601-01-019-C SU--SECC4 1.00 2378.66 C
HILLIA
080702003 LUBE OIL SUCTION STRAINER S&S RD35234 SU--SECB2 1.00 513.24 C
080702006 LUBE OIL MAGNETIC PLUG S&S MS9015-05 SU--SECA2 2.00 1060.50 C
080702009 L.O.COOLER ZINC ANODES, GTG XXXXX 5W02X 3/4 SU--SECA3 4.00 116.00 C
COOLER
080702010 GASKETS, COOLER HEAD, INTER XXXXX 030G10A-8 SU--SECA3 1.00 7.00 C
SEAL, 8"
080702011 GASKETS, XX XXXXXX, XXXXX XXXX, XXXXX 000X00X-0 XX--XXXX0 2.00 16.00 C
8"
080702012 O-RING, L.O. COOLER, REVERSING XXXXX 080G01D-8 SU--SECA3 2.00 10.00 C
XXX, 0"
080702014 VALVE, DRAGON, 3-WAY DRAGON 1053V3 SU--SECA2 23.00 1334.00 C
080702028 TURBINE LUBE OIL (HYD) FILTER S&S HC9600FUN82 SU--SECC5 3.00 227.25 C
ELEMENTS
080702041 RTD 100 OHM (DUAL ELEMENT) S&S L35166P01 SU--MCCCABD 1.00 699.38 C
080702042 TURBINE LUBE OIL TANK TEMP S&S 100TC5-4CC6 SU--MCCCABD 1.00 465.69 C
SWITCH
080702044 TURBINE LUBE OIL SCAV PRES S&S 132P4-1C68 SU--MCCCABD 1.00 167.98 C
SWITCH
080702045 O-RING, P.T. FINGER FILTERS S&S J221P924 SU--SECA3 10.00 18.29 C
080702046 TURBINE LUBE OIL DIF PRES S&S 160P4-S36 SU--MCCCABD 1.00 306.55 C
SWITCH
080702047 TURBINE LUBE OIL TRANSMITTER S&S 1151GP7E2282D3 SU--MCCCABD 1.00 886.61 C
080702048 O-RING, FINGER FILTER SCREENS S&S M83248-1-910 SU--SECA3 14.00 3.49 C
080702049 O-RING, FINGER FILTER SCREENS S&S M83248-/1-121 SU--SECA2 43.00 101.66 C
080702050 PUMP, LUBE OIL AND SCAVENGE S&S C21289P01 SU--SECA3 1.00 17058.92 C
080702051 O-RING FINGER FILTER SCREENS S&S M83248-1-912 SU--SECA3 19.00 25.08 C
080702052 O-RING FINGER FILTER SCREEN S&S M83248/1-905 SU--SECA2 21.00 12.71 C
080702053 GASKET S&S 9013H28P02 SU--SECA3 1.00 35.13 C
080702055 TURBINE LUBE OIL TANK LEVEL S&S KC-F-307BEP SU--SECE4 1.00 397.99 C
SWITCH
080702056 TURBINE LUBE OIL SUPL PRES S&S 132P4-8C68 SU--MCCCABD 2.00 352.04 C
SWITCH
080702057 O-RING, P.T. FINGER FILTERS S&S J221P905 SU--SECA2 3.00 1.20 C
080702058 TURBINE LUBE OIL DIF PRES S&S 160P4-S43 SU--MCCCABD 1.00 302.57 C
SWITCH
080702060 O-RING S&S J221P240 SU--SECA2 3.00 11.97 C
080702061 OIL/AIR SEPARATOR FILTER S&S 95-115 SU--SECA4 2.00 2886.30 C
(95-115)
080702062 OIL/AIR SEPARATOR FILTER S&S 95-116 SU--SECE1 2.00 874.80 C
(95-116)
080702064 OIL/AIR SEPARATOR HOLD DOWN S&S 1330745 SU--SECE2 1.00 259.20 C
SCHEDULE 1, Continued
12-09-97 Syracuse University Inventory Catalog
Spare Part Description Supplier # Supp Part # Location QOH at Loc Total Cost ABC Fl:
---------- ------------------------------------ ---------- ----------- ----------- ---------- ---------- -------
KIT
080702068 PT OIL PUMP DISCHARGE TUBE S&S X00000X00 SU--SECA3 1.00 1136.20 C
GE X00000X00
080702070 GASKET, OIL TUBE SUPPLY S&S 9057M32P01 SU--SECA3 22.00 60.72 C
080702071 OIL TUBE, "C" SUMP SUPPLY S&S L24748G01 SU--SECA2 1.00 530.35 C
080702072 THERMOSTATIC CONTROL VALVE S&S 1125P120-F SU--SECA2 1.00 200.57 C
TEMPERATURE ELEMENT SET 2
120F.
080702073 THERMOSTATIC CONTROL VALVE S&S 917OX011 SU--SECA2 2.00 43.36 C
VITON O-RING KIT
080702074 INTEGRAL CABLE, C-SUMP RTD OIL INTEGR ICI51DQ/17 SU--MCCCABD 1.00 835.00 C
080702075 INTEGRAL CABLE PT OIL TEMP RTD INTEGR ICI51DQ/10 SU--MCCCABD 1.00 800.00 C
080702076 BOSS FOR INTEGRAL CABLES INTEGR ICI-51QB SU--MCCCABD 1.00 25.00 C
080704026 REGULATOR BODY FUEL GAS S&S 310-SP SU--SECF5 1.00 7396.45 C
080704027 GASKET, SEAL (FUEL MANIFOLD) S&S L35246P02 SU--SECA3 1.00 472.80 C
080704028 FLOW TRANSDUCER 2" FUEL GAS S&S YF105-NNNA2A-S3 SU--SECD5 1.00 1484.63 C
080704029 FUEL VALVE, NATURAL GAS S&S 8915-123 SU--SECE5 1.00 20315.61 C
080704030 TURBINE FUEL GAS PRESSURE S&S 132P4-4C6B SU--MCCCABD 1.00 176.53 C
SWITCH
080704031 Y-STRAINER SCREEN, (316ss 150 S&S 764-SS-100M SU--SECD2 1.00 90.87 C
MESH)
080704032 YF011 SIGNAL CABLE S&S YF011-1-0030F*E SU--SECD5 5.00 555.00 C
080704033 VORTEX FLOW CONVERTER S&S YFA11-AUPA-08*E SU--MCCCABD 1.00 743.70 C
080705006 GASKET S&S 9608M12P02 SU--SECA2 3.00 2.91 C
080705022 HYDRAULIC SUPPLY PUMP S&S 8580-017 SU--MCCCABD 1.00 2551.95 C
080705023 GASKET, HYD PUMP S&S L21803P01 SU--SECA2 1.00 4.87 C
080707001 CDP CHECK VALVE, 3INCH S&S 3"G60CPFN34 SU--SECD3 1.00 1091.13 C
080707002 CDP STM XXXXXXX XXX 0" X&X 0000-000 XX--XXX 1.00 21834.75 C
080707007 PROXIMITY LIMIT SWITCH, CDP S&S 21-11524-A3 SU--MCCCABD 1.00 207.29 C
PREHEAT
080707011 CLAMP 0.250" S&S J1153G04 SU--SECA2 3.00 4.32 C
080707012 GASKET METAL O-RING S&S MS9373-029 SU--SECA2 1.00 4.19 C
(AIR-TUBING)
080707013 GASKET, METAL O-RING (AIR S&S NS9373-051 SU--SECA2 3.00 9.74 C
TUBING)
080707014 CLAMP 0.375" S&S J1153G06 SU--SECB2 5.00 16.65 C
080707015 HP RECOUP BLOCK GE X00000X00 SU--SECA2 2.00 300.00 C
080707016 HP RECOUP ORIFICE PLUG GE AN933S0 SU--SECA2 4.00 40.00 C
080707017 HP RECOUP RETAINER SEAL GE L216118P04 SU--SECA2 4.00 40.00 C
080707018 HP RECOUP GASKET, MTL GE MS9373-051 SU--SECA2 1.00 22.50 C
080708011 MICRO 550 CONTROLLER S&S 000-000-000 SU--MCCCABD 1.00 590.52 C
080708012 INPUT MODULE S&S IM SU--MCCCABD 1.00 579.42 C
080708013 525 RELEASE MODULE S&S 00X000000 SU--MCCCABD 2.00 1076.70 C
080708014 FAULT MODULE S&S FM SU--MCCCABD 1.00 294.15 C
080708015 ALARM MODULE S&S AM SU--MCCCABD 2.00 1061.16 C
080708016 GAS SENSOR TRANSMITTER S&S 000-000-00 SU--MCCCABD 3.00 1325.34 C
080708018 FUSE SOMA S&S 1335 SU--MCCCABC 5.00 16.10 C
080708019 FUSE 2A S&S 1328 SU--MCCCABC 5.00 17.20 C
080708020 FUSE 0.1A S&S 1310 SU--MCCCABC 5.00 16.10 C
080708021 FUSE 4A S&S 1269 SU--MCCCABC 10.00 49.40 C
080708022 FUSE 31MA S&S 1308 SU--MCCCABC 5.00 36.10 C
Page 21
Spare Part Description Supplier # Supp Part # Location QOH at Loc Total Cost ABC Flag
------------- -------------------------------- ---------- ---------------- ------------ ---------- ---------- --------
080708025 PRINTED CIRCUIT BOARD STROBE S&S 700-K-24 SU--SECB2 1.00 276.39 C
080708026 FLASHTUBE FOR STROBE LIGHT S&S 3001 SU--SECB2 1.00 47.73 C
080708027 COMBUSIBLE SENSOR S&S 000-000-00 SU--MCCCABD 2.00 1047.84 C
080708028 PRINTED CIRCUIT BOARD HORN S&S 1002-24-PCB-S5 SU--SECB2 1.00 213.12 C
080708030 GAS SENSOR PROTECTIVE COVER DELPHI 000-000-00 SU--SECB2 4.00 48.00 C
080709003 TEMP SENSOR ASSY ENCL TEMP'S S&S 78F25N00N120 SU--MCCCABD 1.00 144.85 C
PLAT RTD
080709004 FLOW SWITCH MONITOR XXXXX-X X&X XX00-0-0 0/0" XX--XXXXXXX 1.00 1304.50 C
080710001 STEAM PIPE TEMPERATURE SENSOR S&S 2511A SU--MCCCABD 1.00 155.22 C
080710003 STEAM PRESSURE TRANSMITTER S&S 1151GP8E22B2D3 SU--MCCCABD 2.00 1539.57 C
080710004 GASKET, COP STEAM S&S X00000X00 SU--SECB2 1.00 465.60 C
080710005 GASKET, STEAM (NOZZEL) S&S X00000X00 SU--SECB2 2.00 167.08 C
080710006 FLOW TRANSDUCER #4" CDP STEAM S&S YF110-NNNA3A-S3 SU--SECC5 1.00 3360.53 C
080710008 MANIFOLD STEAM TEMP SENSOR S&S 305-01BH-D-6-C- SU--MCCCABD 2.00 484.00 C
080710012 NOZZLE STEAM GIMBLE (RIGHTHAND S&S 43360 SU--SECA1 1.00 10560.54 C
#1 GTG)
080710013 LEFT-HANDED HIGH PRESSURE S&S SU--SECA2 1.00 10000.00 C
EXPANSION JOINT
080712076 7200 SRS SGL PLANE VIB MON W/ S&S 72200-XX-XX-XX- SU--MCCCABD 2.00 2727.94 C
MOO 154646-01
080712125 ACCELEROMETER, CRF VIBROM 303-032 ACCELER SU--MCCCABD 1.00 2156.00 C
080712127 XXX XXXXX XXX X&X 0000X00X00 XX--XXXX0 2.00 1998.00 C
080712128 DC REMOTE POWER SUPPLY S&S 45606-01 SU--MCCCABD 1.00 919.08 C
080712129 POWER SUPPLY CONDITIONING UNIT S&S 45607-01 SU--MCCCABD 1.00 807.19 C
080712131 DUAL TRACKING FILTER PWA S&S 41590-XX SU--MCCCABD 2.00 2470.42 C
080712132 INTEGRAL VIBRATION CABLE, 25 INTEGR 1U-1655-34/25 SU--MCCCABD 1.00 1322.00 C
FT.
080712133 RELAY MODULE, ALARM S&S 72130-02 SU--MCCCABD 1.00 255.74 C
080712134 ACCELEROMETER INTERFACE MODULE S&S 77772-01-00-00 SU--MCCCABD 5.00 2770.55 C
080712135 PROXIMITY EXTENSION CABLE S&S 00000-000-00 SU--MCCCABD 1.00 126.65 C
080712137 7200 PROXIMITOR S&S CA18745-03 SU--MCCCABD 1.00 336.55 C
080712138 7200 PROXIMITOR S&S CA18745-04 SU--MCCCABD 1.00 360.53 C
080712139 RELATIVE PROBE HOUSING S&S CA21000-05-05-0 SU--MCCCABD 2.00 564.76 C
ASSEMBLY
080712140 ACCELEROMETER EXTENSION CABLE S&S 45358-09 SU--MCCCABD 1.00 1088.91 C
080712143 SEQUENCER CARD 8 CHANNEL RTD S&S 0000-000 XX--XXXXXXX 1.00 2756.13 C
080712144 PROXIMETER PROBE S&S CA21508-02-12-0 SU--MCCCABD 1.00 126.98 C
080712158 SPEED SENSOR, GG S&S L21131P02 SU--SECA3 2.00 1117.84 C
080712159 ACCELEROMETER S&S L34246P03 SU--MCCCABD 1.00 2593.79 C
080712160 ACTUATOR, XXXXXXXX XXXXXX XXXX X&X 0000X00X00 XX--XXXX0 1.00 1948.47 C
080712163 O-RING, VSV ACTUATOR S&S J221P904 SU--SECA3 20.00 7.00 C
080712172 SECONDARY POWER SUPPLY FUEL S&S 5462-750 SU--MCCCABD 1.00 2200.57 C
CONTROL
080712178 POWER SUPPLY, LOW VOLTAGE S&S 5461-975 SU--MCCCABD 1.00 4018.75 C
080712180 POWER AUXILIARY MODULE (FUEL S&S 5463-034 SU--MCCCABD 1.00 1049.78 C
CONTROL SYSTEM)
080712181 DPDT RELAY, XXXXXXX XXXXXX S&S 01200024 SU--MCCCABD 2.00 148.08 C
080712182 SIO VER 4.4, FUEL CONTROL S&S 0000-000 XX--XXXXXXX 1.00 3196.24 C
080712200 DISCRETE OUTPUT, FUEL CONTROL S&S 0000-000 XX--XXXXXXX 1.00 1829.24 C
080712201 DPS 3/DT, FUEL CONTROL S&S 0000-000 XX--XXXXXXX 1.00 3196.24 C
080712202 DUAL TRACKING FILTER W/ MOO S&S 41590-XX-(A) SU--MCCCABD 2.00 2470.42 C
154647-01
080712203 AUX MEMORY MODULE, SEQ S&S 0000-000 XX--XXXXXXX 2.00 1875.90 C
080712204 DSC MASTER CO-CPU, FULE CONT. S&S 0000-000 XX--XXXXXXX 2.00 5284.69 C
080712205 TRANSCEIVER, SEQ. S&S 0000-000 XX--XXXXXXX 1.00 1002.88 C
080712206 GASKET, HP SPEED PICK-UP S&S J219PO4A SU--SECA3 2.00 14.24 C
080712207 HARNESS, T44 TOP RIGHT S&S L35167P01 SU--SECA3 2.00 14201.88 C
080712208 4-20 CURRENT OUTPUT FUEL S&S 5463-482 SU--MCCCABD 1.00 2471.70 C
CONTROL
080712209 CABLE ACCELEROMETER S&S L28255PO1 SU--MCCCABD 1.00 5418.00 C
080712210 CABLE ACCELEROMETER S&S L28255PO2 SU--MCCCABD 1.00 5418.00 C
080712211 GASKET, CIT SENSOR S&S L28124PO1 SU-SECA2 1.00 8.30 C
080712212 SIGHT GUAGE, FLAME VIEW POC. S&S L3600OG02 SU--MCCCABD 3.00 2902.19 C
080712213 MASTER CPU (SEQ), SEQ S&S 0000-000 XX--XXXXXXX 1.00 4108.94 C
080712214 PROXIMITY EXTENSION CABLE 4.5 S&S 21747-045-01 SU--MCCCABD 1.00 73.70 C
METERS
080712216 SPEED SENSOR, L.P. ROTOR S&S 9303M65P01 SU--SECA2 1.00 3760.24 C
080712217 HIGH TEMPERATURE ACCEL EXT S&S 83387-100 SU--MCCCABD 1.00 2564.10 C
CABLE
080712219 LABEL-MODULE IDENT A-O THRU S&S 3081-275 SU--MCCCABD 1.00 4.50 C
A-16
080712220 7200 SERIES DUAL PLANE VIB MON S&S 72850-01-04-01- SU--MCCCABD 1.00 1065.82 C
080712221 7200 SERIES SINGLE PLANE VIB S&S 72200-XX-XX-XX- SU--MCCCABD 2.00 2355.70 C
MON WITH L.P.C
080712222 B CHANNEL INPUT, SEQ. S&S 0000-000 XX--XXXXXXX 1.00 3344.94 C
080712223 TRANSDUCER VSV & VBV (LVDT) S&S 9153M75P02 SU--SECB2 1.00 3791.23 C
080712224 DISCRETE INPUT, FUEL CONTROL S&S 0000-000 XX--XXXXXXX 1.00 1598.12 C
080712226 SENSOR, FLAME S&S L28490P02 SU--SECA2 1.00 5749.64 C
000000000 4 CHANNEL FINAL DRIVER FUEL S&S 5463-305 SU--MCCCABD 1.00 2420.63 C
CONTROL
080712228 HIGH TEMPERATURE ACCEL EXT. S&S 83387-065 SU--MCCCABD 1.00 .00 C
CABLE
080712229 8 CHANNEL T/L, FUEL CONTROL S&S 0000-000 XX--XXXXXXX 1.00 4172.07 C
080712230 SPEED SENSOR, FUEL CONTROL S&S 0000-000 XX--XXXXXXX 1.00 4172.07 C
080712231 GASKET T44 HARNESS S&S 1030M59P01 SU--SECA3 4.00 116.40 C
080712232 TRANSDUCER, SPEED P/U S&S L31225P03 SU--SECB2 1.00 9705.48 C
080712233 HARNESS, X00 XXXXXX XXXX X&X X00000X00 XX--XXXX0 1.00 6391.20 C
080712234 DSC MASTER CPU, FUEL CONTROL S&S 0000-000 XX--XXXXXXX 2.00 8268.21 C
080712235 GASKET, CIT SENSOR'S S&S 9053M62P02 SU--SECA3 1.00 1.65 C
080712236 XXXXXX-MODULE IDENT 1-17 THU S&S 3060-18 SU--MCCCABD 1.00 5.00 C
A32
080712237 HARNESS, T44 BOTTOM RIGHT S&S L35169P01 SU--SECA3 2.00 12782.40 C
080712238 7200 SRS SGL PLANE VIB MON S&S 72200-XX-XX-XX- SU--MCCCABD 2.00 2490.89 C
W/MOD 154378-01
080712240 SHIM LP SPEED SENSOR S&S 9107H55P01 SU--SECA2 2.00 21.72 C
080712241 FUSE 00X XXXXXX XX00 XX--XXXXXXX 10.00 5.50 C
080712242 FUSE 1-8/10 A BALDWI TRM1-8/10 SU--MCCCABD 2.00 3.38 C
080712243 FUSE 00X XXXXXX XX00 XX--XXXXXXX 10.00 9.00 C
080712244 FUSE 0X XXXXXX XXX0 XX--XXXXXXX 2.00 8.24 C
080712245 FUSE 00X XXXXXX XXXX00 XX--XXXXXXX 8.00 32.88 C
080712246 FUSE S&S KTK-10 SU--MCCCABD 3.00 14.04 C
080712247 FUSE 1A BALDWI ATH1 SU--MCCCABD 2.00 3.38 C
SCHEDULE 1, Continued
12-09-97 Syracuse University Inventory Catalog
Spare Part Description Supplier # Supp Part # Location QOH at Loc Total Cost ABC Flag
---------- ----------- ---------- ----------- -------- ---------- ---------- --------
080712248 FUSE 5-6/10 A BALDWI TRM5-6/10 SU--MCCCABC 9.00 15.21 C
080712251 FUSE 3-2/10 A BALDWI TRM3-2/10 SU--MCCCABC 10.00 16.90 C
080712252 FUSE S&S KTK-8 SU--MCCCABC 10.00 46.80 C
080712253 FUSE 0X XXXXXX XXX0X XX--XXXXXXX 10.00 42.50 C
080712254 FUSE 0X XXXXXX XXX-0 XX--XXXXXXX 9.00 15.75 C
080712255 FUSE 1-6/10 A BALDWI ATQ1-6/10 SU--MCCCABC 10.00 45.70 C
080712256 FUSE 0X XXXXXX XXXX-0 XX--XXXXXXX 8.00 43.20 C
080712257 FUSE 00X XXXXXX XXX00 XX--XXXXXXX 10.00 37.00 C
080712258 FUSE 00X XXXXXX XX00 XX--XXXXXXX 3.00 1.65 C
080712259 FUSE S&S KTK-20 SU--MCCCABC 9.00 43.65 C
080712260 FUSE 00X XXXXXX XXX00 XX--XXXXXXX 20.00 31.60 C
080712261 FUSE 00X XXXXXX XXX00 XX--XXXXXXX 10.00 37.00 C
080712262 FUSE 00X XXXXXX XXX00 XX--XXXXXXX 10.00 37.00 C
080712263 FUSE 0-0/0X XXXXXX XXXX-0-0/0 XX--XXXXXXX 10.00 54.00 C
080712264 FUSE 0/0X XXXXXX 0XX0/0X000 XX--XXXXXXX 7.00 8.75 C
080712265 FUSE 0X XXXXXX XXXX-0 XX--XXXXXXX 5.00 29.00 C
080712266 FUSE .5A BALDWI TRM.5 SU--MCCCABC 4.00 6.76 C
080712267 FUSE 00X XXXXXX XXX00 XX--XXXXXXX 9.00 14.22 C
080712268 FUSE S&S KTK-2 SU--MCCCABC 6.00 28.08 C
080712269 FUSE 0X XXXXXX XXXX-0 XX--XXXXXXX 10.00 54.00 C
080712270 FUSE 2-1/4 A BALDWI TRM2-1/4 SU--MCCCABC 10.00 16.90 C
080712271 FUSE 3-1/2 A BALDWI TRM3-1/2 SU--MCCCABC 6.00 10.14 C
080712272 FUSE 0X XXXXXX XXX0 XX--XXXXXXX 10.00 16.90 C
080712273 FUSE S&S KTK-5 SU--MCCCABC 4.00 18.72 C
080712274 FUSE 0X XXXXXX XXX0 XX--XXXXXXX 10.00 15.80 C
080712275 FUSE 8A BALDWI ATM8 SU--MCCCABC 10.00 37.00 C
080712276 FUSE 0X XXXXXX XXX0 XX--XXXXXXX 9.00 15.21 C
080712277 FUSE 2.5A BALDWI TRM2.5 SU--MCCCABC 10.00 16.90 C
080712278 FUSE 3A BALDWI OT3 SU--MCCCABC 8.00 4.64 C
080712279 T 2.5 OFF-ENGINE CABLE, TC S&S X00000X00 SU--MCCCABD 1.00 3149.38 C
(20FT)
GE X00000X00
080712280 GASKET, FLAME SENSOR S&S 9609M43P05 SU--SECB2 4.00 1.28 C
SIGHTGLASS
080712281 GASKET, T3 SENSOR S&S MS9372-029 SU--MCCCABD 5.00 14.45 C
080712282 XXXXXXXX BUFFER BOARD 5500-558 S&S 0000-000 XX--XXXXXXX 1.00 333.00 C
080712283 GASKET, FLAME SENSOR S&S L43073P01 SU--SECA2 3.00 43.71 C
080714002 CARTRIDGE FILTER S&S LM0105-3/4 SU--SECL3 3.00 31.98 C
080714003 REPAIR KITS, XXXXXX S&S R1066SRX752 SU--SECD1 5.00 155.48 C
080714005 OFF LINE WTR WASH TANK S&S 951101MA SU--SECL3 1.00 344.10 C
PRESSURE RELIEF VALVE
080717001 XXXXXX XXXXX XXXX X00000X00 S&S RADIAL DRIVE BO SU--SECA4 1.00 795.20 C
080717002 ACC GRBX HAND XXXX COVER S&S J221P134 SU--SECA4 4.00 5.32 C
GASKET
080717006 O-RING (FUEL GAS MANIFOLD) S&S J221P019 SU--SECA2 29.00 11.75 C
080717016 SHAFT SEAL ASSEMBLY, TGB S&S L21431G01 SU--SECB2 1.00 229.36 C
090107001 VORTEX FLOW METER NICE VBAR-FV-08-1-40 SU--SECH1 1.00 2195.00 C
090107002 VORTEX FLOW METER NICE VBAR-FV-08-1-40 SU--SECH1 1.00 2195.00 C
090107003 VORTEX FLOW METER NICE VBAR-FV-06-2-40 SU--SECH1 1.00 2895.00 C
090107004 VORTEX FLOW METER NICE VBAR-FV-06-1-40 SU--SECH1 1.00 2195.00 C
090107004 XXXXX #2005 MAGNEHELIC ACI XXXXX #2005 SU--MCCCABB 1.00 44.90 C
SCHEDULE 1, Continued
12-09-97 Syracuse University Inventory Catalog
Spare Part Description Supplier # Supp Part # Location QOH at Loc Total Cost ABC Flag
---------- ----------- ---------- ----------- -------- ---------- ---------- --------
GUAGE/RANGE 0-5" WC
090202006 1/2" X.X. SPEC. #150026 XXX 0-0/0" XXX 0000 XX--XXXXXXX 2.00 178.20 C
090202007 1/2" X.X. SPEC. #150027 XXX 0-0/0" XXX 0000 XX--XXXXXXX 1.00 83.24 C
090202021 1/2" X.X. SPEC. #150009 XXX 0-0/0" XXX 0000 XX--XXXXXXX 3.00 150.15 C
090202022 1/2" X.X. SPEC. #150034 XXX 0-0/0" XXX 0000 XX--XXXXXXX 2.00 193.70 C
090202023 1/2" X.X. SPEC. #150029 XXX 0-0/0" XXX 0000 XX--XXXXXXX 2.00 166.48 C
090202026 BELLOFRAM TYPE 50 ACI #241-960-069-00 SU--MCCCABB 2.00 77.20 C
REGULATOR/DRIPWELL 0-120 PSI
090202031 BELLOFRAM TYPE 50 ACI #241-960-067-00 SU--SECK3 1.00 38.60 C
REGULATOR/DRIPWELL 0-30 PSI
090202032 1/4" X.X. SPEC. #47104 XXX 0-0/0" XXX X000 XX--XXXXXXX 2.00 19.46 C
090202033 BELLOFRAM TYPE 50 ACI #241-960-068-00 SU--SECK3 2.00 77.20 C
REGULATOR/DRIPWELL 0-60 PSI
090202039 1/2" X.X. SPEC. #150024 XXX 0-0/0" XXX 0000 XX--XXXXXXX 2.00 166.48 C
090202044 1/4" STAINLESS BONNET VALVE ACI 4Z-V6LR-G-SS SU--SECH3 1.00 92.00 C
090202054 1/2" STAINLESS VALVE ACI 8Z-B8LJ-SSP-OZ SU--SECH3 1.00 135.99 C
090202055 1/2 STAINLESS NEEDLE VALVE ACI 8ZV8L NSS SU--SECH3 2.00 120.96 C
090202056 1/2" STAINLESS VALVE ACI 8Z8LJSSPKY SU--SECH3 1.00 120.88 C
090405003 LAMP ASSEMBLY, SILICA ANALYZER HACH 4011.33 SU--MCCCABA 1.00 14.66 C
090503044 2.5" GUAGE, 0-2000 PSI, PHOS ACI 147197 SU--XXXXX 6.00 161.46 C
PHP
954683.70
Page 24
SCHEDULE 2
PROPRIETARY DOCUMENTS
1. Maintenance Software "Gpmate"
2. Training Software "Tris"
3. Performance Tracking Software "PPIMS"
4. Vibration Analysis Software "Entek Monitor"
5. Chemistry Trending Software "Vantage"
6. LM 5000 Training Program "TSI Energy"
7. GE Safety and Regulatory Compliance Manual
8. GE Predictive Maintenance Manual
9. GE Training Manual
10. GE Administrative Manual
11. GE Transportation Directory
12. GE Employee Handbook
-18-
SCHEDULE 3
APPROVED CONTRACTORS
Gas Generator
-------------
1. Air New Zealand
2. IHI
3. General Electric Company
4. MTU Motoren-und Turbinen-Union
Power Turbine
--------------
1. European Gas Turbines Ltd. Industrial Products
2. S&S Energy Products
3. General Electric Company
-19-
SCHEDULE 4
TERMINATION FEE
------------------------------------------------------
NPV of POA
Date of Termination O&M CONTRACT
------------------------------------------------------
6/30/98 $6,972,537
------------------------------------------------------
6/30/99 $6,366,003
------------------------------------------------------
6/30/00 $5,741,181
------------------------------------------------------
6/30/01 $5,097,428
------------------------------------------------------
6/30/02 $4,434,070
------------------------------------------------------
6/30/03 $3,750,401
------------------------------------------------------
6/30/04 $3,045,678
------------------------------------------------------
6/30/05 $2,319,120
------------------------------------------------------
6/30/06 $1,569,906
------------------------------------------------------
6/30/07 $ 797,170
------------------------------------------------------
4/1/08 $ 0
------------------------------------------------------
-20-