EXHIBIT 10.98
DESIGN/BUILD
CONSTRUCTION CONTRACT
AGREEMENT, made this 14th day of August, 1997, by and between McLeodUSA
Incorporated ("Owner"), located at McLeodUSA Technology Park, 0000 X Xxxxxx XX,
Xxxxx Xxxxxx, Xxxx 00000-0000 and Xxxxxx Xxxx, Inc., and its subsidiary, Xxxxxx
Xxxx L.C., Cedar Rapids with offices located at 000 00xx Xxxxxx Xxxxx XX, Xxxxx
Xxxxxx, XX 00000 ("Contractor").
1. Scope of Work. Owner is developing an office park on its property
-------------
located at 0000 X Xxxxxx XX, Xxxxx Xxxxxx, Xxxx ("Project"). The existing office
building on the Project Site is generally referred to as "Building 1." The
office building being constructed pursuant to this Contract is generally
referred to as "Building 2." Contractor shall furnish all of the labor,
materials, skill, supervision, equipment, tools, machinery, transportation, and
other facilities, services and administration necessary for the proper execution
and completion of the design and construction of a two-story, approximately
320,000 square foot office building located at 0000 X Xxxxxx, XX, Xxxxx Xxxxxx,
Xxxx ("Project Site") and related improvements in accordance with the plans,
outline specifications and any other materials described on Exhibit A, in
accordance with the Contract Documents, as authorized by appropriate Change
Orders, and the final plans and specifications prepared therefrom (hereinafter
referred to as the "Work"). The term "Work" in this Contract shall also include
the total architectural and engineering design of Building 2, and the
preparation of construction drawings and specifications. The design portion of
Work was authorized to commence on July 25, 1997 (Xxxxxx Xxxx Project Schedule
Data Date) ("Start Date").
Exhibit "A" shall reflect the scope of work to design and construct the shell,
structure, HVAC and all items to one hundred percent (100%) completion of the
first floor of Building 2, except approximately 31,840 square feet in the center
of the first floor reserved for the switch/data center (as reflected on the
design drawings) and the entire second floor (collectively referred to as
"Reserved Space"). The Reserved Space shall be finished to the extent of
life/safety items as determined by construction industry standards and the
applicable state, federal and local building codes, ordinances, and regulations.
The completed Building 2 baseline, except the Reserved Space, shall be
determined to be: (a) of equivalent or better design features, quality, labor
and materials (including quantity of materials) provided by the general
contractor of Building 1 and its subcontractors ("Baseline"), as evidenced by
the physical structure, final statement of work, specifications, and as-built
drawings, all relating to Building 1; (b) Any exceptions to the Baseline
including but not limited to those items to be performed by Owner or its
subcontractor, shall be specifically enumerated in Exhibit "A" to this Contract;
and (c) plus any exceptions or scope changes documented in a duly executed
Change Order to this Contract (collectively referred to as "Final Baseline"). If
there is a conflict among any of the aforementioned components comprising the
Final Baseline, the physical Building 1 structure shall be controlling.
The Work shall be undertaken with a standard of care, skill and workmanship
throughout, consistent with applicable industry standards in the area in which
the Project is located. Final plans and specifications will comply with all
applicable building codes, ordinances and regulations in effect and enforced as
applicable. Owner has furnished to Contractor any necessary program or design
information regarding Owner's needs or requirements for the Work for any work to
be performed by separate contractors working directly for the Owner. Contractor
shall be entitled to rely on the accuracy and completeness of such information
in the design and construction of the Work.
Owner's decision in matters relating to aesthetic affect will be final if
consistent with the intent of the Construction Documents and Contract Documents.
The Construction Documents pertinent to Contractor's work have been carefully
examined by the Contractor.
2. Schedule. Upon award of the Contract, Contractor shall prepare
--------
and submit for Owner's approval a firm schedule ("Work Schedule") as it relates
to the Project schedule ("Master Project Schedule"). The Work Schedule shall
indicate the critical dates to complete the Work including but not limited to
order dates, lead times, delivery dates and completion of various stages of the
Work. The Contractor shall be responsible for maintaining progress in accordance
with the Work Schedule.
Contractor shall achieve Substantial Completion of the Project no later than
July 1, 1998 ("Completion Date"). All claims for an extension of time shall be
made in writing to Owner within 15 days after the occurrence of the cause of
delay or shall be deemed waived, but in the case of a continuing cause of delay,
only one claim shall be necessary. Extensions of time include but are not
limited to extensions for each Work Day or Half Day which Contractor is not
responsible for the delay as described in paragraph 7 of this Agreement.
Substantial Completion shall be deemed to have been achieved when construction
is sufficiently complete so that Owner can utilize the Work for the purpose for
which it is intended and a certificate of occupancy (temporary or permanent) has
been issued for the Work. Time is of the essence in completion of this Project.
Owner and Contractor shall execute a Certificate of Substantial Completion
certifying the Date of Substantial Completion. As of the Date of Substantial
Completion, Owner shall assume full responsibility for all maintenance,
utilities, insurance, security and all other operational aspects of the Project.
3. Related Work. The Contractor acknowledges that Owner may award
------------
separate contracts for work related to the Project, and that Owner will
coordinate such separate work with the work of the Contractor, who shall
cooperate with such contractors.
4. Contract Price. The Owner agrees to pay the Contractor for the
--------------
full, faithful and prompt performance of this Agreement subject to all the
terms and conditions hereof, a sum of Twelve Million, One Hundred Forty-Three
Thousand, Seven Hundred and One Dollars ($12,143,701) ("Guaranteed Maximum Price
or "GMP"), comprised of the proposed Cost of Work.), subject to additions and
deductions by Change Order as provided in the Contract Documents, plus the
Contractor's Fixed Fee.
2
The Cost of Work is defined in subparagraph 7.1 of Exhibit "D". Costs which
would cause the Guaranteed Maximum Price to be exceeded shall be paid by the
Contractor without reimbursement by the Owner, and 100% of savings accrue to the
Owner. The pricing detail is reflected in Exhibit "A" to this Contract, which
includes allowances only for those items specified therein.
The Contractor's Fixed Fee is Three Hundred Twenty-Six Thousand, Three Hundred
Sixty-One Dollars ($326,361), determined as two point seventy-five percent
(2.75%) of the proposed Cost of Work, and is fixed as a lump sum amount ("Fixed
Fee"). No additional fee will be charged on changes to the GMP until the
aggregate total of Change Orders equals five percent (5%) of the GMP. Cost of
Work above this "buffer" will be subject to a fee of two point seventy-five
percent (2.75%) ("Additional Fee"). The GMP is predicated upon the Final
Baseline (as defined in paragraph 1 of this Contract), with no contingencies.
5. Subcontractors. Subcontractor pricing will be negotiated and a
--------------
mutually agreeable subcontract pricing process will be attached to and
incorporated into the Statement of Work. Contractor shall supply a list of all
subcontractors and vendors, and such list shall be timely updated.
6. Payment Terms. The Owner agrees to make payment to the Contractor in
-------------
accordance with the following terms:
Progress Payments: Contractor shall submit to Owner, on or about the first day
-----------------
of each month, an Application for Payment based on the value of the work
completed (including materials suitably stored on the site) and the Schedule of
Values set forth in Exhibit A. The Schedule of Values shall be the basis for the
allocation of the GMP to the activities shown on the Construction Schedule. If
no Schedule of Values is attached hereto, Contractor shall submit one to Owner
prior to Contractor's first Application for Payment. Upon receipt of each
Application for Payment, Owner shall have the right to inspect the Project to
confirm that Contractor's Application reflects the value of work actually
completed. If Owner discovers that the work actually completed differs from that
represented on the Application for Payment, or the work is defective or does not
comply with the requirements of the Contract, Owner may withhold such sums as it
reasonably deems necessary in light of the work actually completed until the
work is completed or the defect is remedied.
Within 15 days after receipt of each Application for Payment, Owner shall pay to
Contractor the entire amount thereof, subject to possible withholding as
provided above, except that until such time as Contractor certifies that the
Work is fifty percent (50%) complete, a retainage of ten percent (10%) of the
amount set forth in each Application for Payment shall be withheld. Subsequent
to Contractor's certification that the Work is fifty percent (50%) complete, no
additional retainage shall be withheld from such payments. No payment to
Contractor shall constitute an acceptance of any work not in accordance with the
requirements of this Contract.
Upon receipt of each payment from Owner, Contractor shall deliver to Owner its
lien waiver in the amount of such payment. If requested by Owner, prior to
receipt of the second and each
3
succeeding payment, Contractor shall deliver to Owner lien waivers from its
subcontractors and suppliers covered by the previous payment received from
Owner. Contractor's lien shall be supported by lien waivers for amounts
exceeding $5,000 from subcontractors, vendors and sub-subcontractors.
Contractor guarantees that title to all work, materials, and equipment covered
by an Application for Payment, whether incorporated into the Project or not,
will pass to Owner free and clear of all liens, claims, security interests and
encumbrances upon the receipt of such payment by Contractor.
Punch List Work. Upon Substantial Completion of the Work by Contractor,
---------------
Contractor and Owner shall jointly inspect the Work, including but not limited
to all Owner or subcontractor installed equipment which constitutes part of the
Project. If there remain "punch list" items to be completed, Contractor and
Owner shall list items and Contractor shall complete such items within 30 days
thereof, unless Contractor is unable to complete such items due to weather
conditions, unavailability of materials or other causes beyond the Contractor's
or its subcontractor's reasonable control, in which case such items shall be
completed as soon as reasonably possible.
Owner may withhold a sum equal to 150% of the estimated cost of completing any
punch list items (unfinished work). Thereafter, Owner shall pay to Contractor,
on a monthly basis, the amount withheld for unfinished items as each item is
completed. However, if such items are not completed within 120 days of
Substantial Completion, Owner may waive completion of such items in writing and
retain a sum equal to 150% of the estimated cost of completing such unfinished
work, unless Contractor is unable to complete such items due to weather
conditions, unavailability of materials, or other causes beyond the Contractor's
or its subcontractor's reasonable control, in which case such items shall be
completed as soon as possible.
Final payment. The unpaid balance of the GMP, including all sums retained
-------------
pursuant to this Contract, shall be due and payable within 15 days after
resolution of all outstanding issues. Final payment shall be made simultaneously
with the furnishing of a lien waiver from the Contractor and lien waivers from
Contractor's subcontractors and suppliers for all sums paid to Contractor.
7. Performance Incentive/Liquidated Damages. Owner will incur expenses
----------------------------------------
for housing employees in leased office facilities until the Completion Date. If
Contractor achieves Substantial Completion prior to July 1, 1998, Owner shall
pay Contractor the amount of Five Thousand Dollars ($5,000) for each Work Day,
and Two Thousand, Five Hundred Dollars ($2,500) for each Half Day (two Half Days
equal a Work Day), which Substantial Completion precedes July 1, 1998
("Performance Incentive"), subject to a maximum Performance Incentive payment
totaling One Hundred, Fifty Thousand Dollars ($150,000). The stated calendar
date of July 1, 1998, shall not be modified concurrent with any change of the
Completion Date; however, the stated calendar date by which the Performance
Incentive is measured shall be equitably adjusted and reflected in any Change
Order to this Agreement.
If the Contractor fails to complete the Work by the Completion Date, including
failure of any Work to be in compliance with the Contract Documents, Owner may
deduct Seven Thousand, Five Hundred Dollars ($7,500) from any amounts due to
Contractor from Owner, whether under
4
this Agreement or any other agreement, for each Work Day, and Owner may deduct
Three Thousand, Seventy-Five Dollars ($3,750) for each Half Day, beyond
the Completion Date until the Substantial Completion has been achieved.
The Completion Date shall be extended day for day for each Work Day or Half Day,
during the performance of this Agreement, Contractor is precluded from working
because of delays beyond Contractor's reasonable control, including but not
limited to delay of preceding work, work contracted by McLeodUSA which precludes
issuance of a Certificate of Occupancy or Contractor's attainment of Substantial
Completion, weather, Acts of God, fire, explosion, action by civil, governmental
or military authority, riots, and wars. However, no exceptions shall be made
for delayed or slow delivery of materials ordered by Contractor. Contractor
shall use reasonable efforts under the circumstances to avoid or remove such
causes of non-performance or delay and shall proceed to perform with reasonable
dispatch whenever such causes are removed or ceased. For the purposes of this
subparagraph, the term "Contractor" shall also include the subcontractors hired
by Contractor.
For the purpose of day for day extensions of the Completion Date and determining
any Performance Incentive or Liquidated Damages, a "Work Day" means any calendar
day, excluding Saturdays, Sundays, holidays or days when weather or other
conditions beyond the reasonable control of the Contractor which preclude
performance of the Work, and Contractor is unable to work for more than six (6)
hours during any day which would otherwise be a Work Day. However, if Contractor
is able to work at least four (4) hours, but less than six (6) hours, such day
shall be deemed a Half Day. For the purposes of this subparagraph, the term
"Contractor" shall also include the subcontractors hired by Contractor.
Contractor shall notify the Project Manager in writing of each such delay in
writing as specified in paragraph 2 of this Agreement, and the Project Manager
shall indicate the applicable extension of the Completion Date on the Master
Project Schedule. All such extensions shall be incorporated into the Contract by
Change Order upon the request of the Contractor. Such Change Orders shall
aggregate extensions granted up to and through the date of the Change Order, and
Contractor shall not request such Change Orders more frequently than twice per
month.
Although the GMP and the Completion Date are predicated upon eight (8) hour work
days, five (5) days a week, Owner may authorize, by a duly executed Change
Order, including but not limited to shift-work and overtime premiums to expedite
the Completion Date ("Expedited Completion Date"). However, unless an Expedited
Completion Date is authorized, Contractor shall remain responsible for timely
completion of the Work, and shall implement shift work and pay all shift work
and overtime premiums if required to achieve the Completion Date. Work shall be
permitted on a 24 hour day basis and on Saturdays, Sundays and holidays.
Contractor is expected to xxxxxxxx the necessary forces to achieve the
Completion Date, including but not limited to, extra crews, contractors, extra
work hours, or other acceptable methods to insure completion of the Work by the
Completion Date and in compliance with the terms of this Agreement.
5
Whenever the Project Manager anticipates that Contractor may be subject to
Liquidated Damages, the Manager shall furnish the Contractor written notice of
such possibility at lease two (2) days prior to the accrual of Liquidated
Damages. Subsequently, Project Manager shall provide Contractor a weekly
statement indicating the number of Working Days subject to Liquidated Damages.
Should Contractor believe the statement to be inaccurate, the Contractor should
submit to the Project Manager, in writing, an objection and reasons within
ten (10) calendar days after receipt of the statement. If the Contractor fails
to submit its objection within that time, the original statement may be
considered as accurate and final.
If the amount of Liquidated Damages exceeds any amount due from Owner to
Contractor, Owner may proceed against the Contractor's performance bond, or any
other legal remedy available to Owner.
8. Supervision and Construction. Contractor shall supervise and direct
----------------------------
the Work and shall be solely responsible for all construction means, methods,
techniques, sequences and procedures for the Work, and for coordinating and
assuring the safety of personnel, property and operations of all portions of the
Work to be performed by Contractor and its subcontractors under this Contract.
9. Orderly Progress of Work. Contractor agrees to proceed with the
------------------------
Work in an orderly and reasonable sequence.
10. Waiver of Liens. Contractor agrees to pay for all materials,
---------------
skills, labor and equipment used in or in connection with the performance of
this Agreement, when and as bills or claims therefore become due, and to save,
protect and hold harmless the Project, and the Owner from all claims and
mechanics' liens on account award of this Agreement and/or performance by
Contractor of this Agreement. If any such liens are filed, Contractor shall,
within 14 days after such filing, either satisfy such lien or post a bond in an
amount equal to 150% of the amount of such lien. This provision shall not be
construed as a waiver of the right of the Contractor to file and enforce a lien
claim against the Owner in the event of the Owner's failure to pay the
Contractor.
11. Schedule Delays. No extension of time of performance of this
---------------
Agreement shall be recognized by the Owner without the written consent of the
Owner.
12. Work Standards. Contractor agrees to be bound by the terms of the
--------------
exhibits attached to this Contract which are incorporated by this reference and
to furnish such shop drawings or samples as may be required. Contractor agrees
to accept responsibility for all damage caused by the Contractor, to clean all
surfaces soiled by the Contractor, and to protect the work performed by the
Contractor, it being understood that the standards of protection shall not be
less than those specified in the attached Exhibit "B" - General Provisions or
required by law, and to be responsible for any defective or improper work or
material caused by its failure so to do. Contractor shall pay for appropriate
packaging, insurance shipping and transportation if required for the proper
execution of the Work.
6
13. Change Orders. The Owner or its authorized representative shall have
-------------
the right to order in writing the addition, deletion, alteration or modification
of any parts of the Work or materials; that fair adjustments shall be made in
the GMP and Work Schedule for changed Work. However, adjustments in the Fixed
Fee shall only be made pursuant to the provisions of paragraph 4 of this
Contract. The adjustment to the GMP shall be determined by the process set forth
in Exhibit "A." No extra work shall be allowed or changes made by the
Contractor, or paid by the Owner UNLESS AND UNTIL AUTHORIZED BY THE OWNER OR ITS
AUTHORIZED REPRESENTATIVE IN WRITING BEFORE THE WORK AND/OR CHANGES ARE BEGUN.
Contractor agrees to give notice to the Owner of all claims for extras, for
extensions of time and for damage for delays or otherwise, promptly and in
accordance with the General Provisions.
Owner and Contractor shall each appoint a representative with full authority to
act on behalf of each party. Owner's representative shall be Xxxxx XxXxxx or
Xxxxx X. Xxxxxx, Xx. Contractor's representative shall be Xxxxx Xxxx or
person(s) in such capacity if the named individual is unavailable for a time
frame which could impact the Work Schedule. The Owner's designee, Xxx Xxxxx, may
authorize minor variations in the project that do not involve an adjustment in
the Contract Sum of more than an amount of Ten Thousand Dollars ($10,000) or a
change in the contract schedule of more than three (3) days, and which are
consistent with the overall intent of the Contract Documents. All changes to the
Contract shall be only by Change Orders executed in accordance with this
paragraph 13. Communication between the parties shall, whenever possible, be
accomplished by the above representatives.
14. Performance Bond/Labor and Material Payment Bond. The Contractor
------------------------------------------------
shall, upon execution of this Agreement, obtain and furnish to the Owner, and
maintain in effect during the term of this agreement, a surety bond in form and
with sureties acceptable to the Owner in an amount equal to the Contract Price
conditioned upon and covering the faithful performance of and compliance with
all the terms, provisions and conditions of this Contract. The bond shall also
cover Contractor's obligation to promptly pay all persons supplying labor or
material in the performance of the Work and maintenance of the Work for one year
commencing on the Date of Substantial Completion. Contractor's failure to
furnish such bond shall be cause for the Owner to terminate this agreement.
The surety bond premium to be in addition to the Contract Price and therefore to
be paid by Owner in addition to the Contract Price.
Bond Requested X Bond not requested (Check one).
--------- --------------
Bond Amount: $ 12,143,701.00
--------------
15. Taxes, Permits, Fees and Bonds. Contractor shall pay all sales,
------------------------------
consumer, gross receipts, use and other similar taxes required by law and
imposed upon the labor and materials provided by Contractor or any of its
subcontractors as of the date of this Contract. Contractor shall be entitled to
an increase in the Contract Price to the extent that an increase in the
aggregate of such taxes payable by Contractor hereunder results from any change
in the laws creating such
7
taxes enacted after the date of this Contract. Contractor shall secure and pay
for the building permit and all other governmental permits (except zoning and
land use permits and fees), licenses and inspections necessary for the proper
execution and completion of the Work, which are legally required as of the date
of this Contract. Contractor shall not be required to pay any special assessment
charges for public improvements and other municipal charges for the payment of
capital improvements. Owner shall be responsible for any required platting or
subdivision and shall pay all fees in connection therewith; and Owner will also
be responsible for all permits, licenses and fees relating to the operation or
use (as opposed to the construction) of the Work, including (but not limited to)
storm water discharge permits for the operation of the facility, air emission
permits and indirect source permits. Owner shall provide any bonds, guarantees
or other relating to on-site or off-site improvements. Contractor shall assist
in obtaining the approvals required by regulatory agencies and advise Owner of
potential problems.
16. Compliance with Laws. Contractor agrees to comply with all
--------------------
Federal and State laws, codes, and regulations and all municipal ordinances and
regulations effective where the work under this Agreement is to be performed,
and to pay all costs, expenses, licenses, fees and taxes, including sales
connected with such compliance and use taxes, and also pay all taxes imposed by
any State or Federal law for any employment insurance, pensions, old age
retirement funds or any similar purpose and to furnish all necessary reports and
information to the appropriate federal, state and municipal agencies, with
respect to all of the foregoing, and to hold each other contractor and the Owner
harmless from any and all losses or damage occasioned by the failure of the
Contractor to comply with the terms of this paragraph.
17. Royalties/Patent Indemnification. Contractor agrees to pay all
--------------------------------
royalties and license fees; to defend all suits or claims for infringement of
any patent rights or intellectual property rights involved in the work of the
Contractor under this Agreement; and to save the Owner and other contractors
harmless from loss, cost or expense on account of such use or infringement by
the Contractor.
18. Dispute Resolution. Any dispute arising between the Owner and
------------------
the Contractor under this Agreement, including the breach thereof, shall be
settled in accordance with the dispute resolution provisions of the General
Provisions.
19. Right to Exercise Set-off. If notification of any claims have
-------------------------
been made against the Contractor or the Owner arising out of labor or materials
furnished in connection with the Work or otherwise on account of any actions or
failures to act by the Contractor in the performance of this Contract, the Owner
may, at its discretion and upon written notification to Contractor, withhold
from such amounts otherwise due or to become due under this Contract, a sum
adequate to cover said claims and any costs or expenses arising or to arise in
connection therewith pending legal settlement thereof. This right of the Owner
shall be in addition to and not exclusive of any other rights of the Owner
provided pursuant to this Contract or available at law or in equity.
20. Authorized Representative. Owner agrees that except in an
-------------------------
emergency or to enforce safety requirements, it shall not issue or give any
instructions, orders or directions to any
8
employee or worker of the Contractor other than persons Contractor has
designated as the persons at the Project Site having supervisory responsibility
for the Contractor's work.
21. Substitutions. Any approved substitutions or alteration of the
-------------
requirements the Contract Documents are noted below (check one):
__X__ No substitutions or alterations ___Substitutions or alternations as
without Owner's prior written described in Exhibit ___ to this
approval. Agreement, incorporated herein by
this reference.
22. Independent Contractor. The Contractor shall at all times be an
----------------------
independent contractor, rather than a co-venturer, partner or employee of Owner.
Owner shall not make any payments or incur liability or expenses for any workers
compensation or unemployment compensation relating to the Contractor or
employees of the Contractor. The Contractor agrees that social security, income
taxes, premium for workers compensation and payments for unemployment
compensation taxes which may become due as a result of the payments for services
to the Contractor under this agreement shall be the sole responsibility of the
Contractor.
23. Order of Priority. In the event of any conflict between the printed
-----------------
provisions of this Construction Contract Agreement and the attached Exhibits,
the provisions of the Exhibits shall control.
24. Insurance.
---------
(a) Builder's Risk Insurance. Owner has purchased and shall maintain
------------------------
"all-risk" builder's risk insurance covering the Project naming
Xxxxxx Xxxx as general contractor, in an amount not less than
$17,000,000, and with a deductible amount not to exceed $10,000. The
risk associated with such deductible shall be borne entirely by
Owner. Such insurance shall be provided on a non-reporting, completed
value basis. A certificate of insurance showing such coverage to be
in force shall be furnished to Contractor prior to commencement of
construction.
(b) Liability Coverage. Contractor shall maintain liability coverage
------------------
in accordance with Exhibit B-General Provisions.
(c) Waiver of Subrogation. Owner and Contractor waive all rights
---------------------
against each other, and against their respective agents, employees
and subcontractors, for damages caused by perils covered by the
insurance to be maintained pursuant to this paragraph except such
rights as they may have to the proceeds of such insurance. If the
policy of insurance to be provided pursuant to this paragraph
requires an endorsement for continued coverage where there is a
waiver of subrogation, the party providing such insurance shall cause
such policy to be so endorsed.
9
(d) Notice of Cancellation. All insurance policies provided by either
----------------------
party to this Contract shall contain a provision requiring the
insurer to give a minimum of 30 days advance written notice to the
other party of cancellation or modification of the terms of the
policy.
24. Entire Agreement. This Contract represents the entire and integrated
----------------
agreement between Owner and Contractor pertaining to the Work, and supersedes
all prior negotiations, representations or agreements, whether written or oral.
This Contract may be amended only on a written instrument signed by both Owner
and Contractor.
25. Incorporation of Exhibits. The Contract Documents include, but are
-------------------------
not limited to, the following Exhibits (attached hereto or enclosed herewith)
which are made a part of the Contract Documents:
Exhibit A: Statement of Work
Exhibit B: General Provisions
Exhibit C: Master Project Schedule
Exhibit D: Additional Terms and Conditions
Xxxxxx Xxxx, Inc. Xxxxxx Xxxx L.C., Cedar Rapids
Federal Tax #42-1247654 Federal Tax #42-1449107
By: /s/ Xxxxxx X. Xxxx By: /s/ Xxxxxx X. Xxxx
---------------------------------- -----------------------------
Xxxxxx X. Xxxx, Vice President Xxxxxx X. Xxxx, President
McLeodUSA Incorporated
Federal Tax #42-1407240
/s/ Xxxxx X. Xxxxxx, Xx.
----------------------------
Xxxxx X. Xxxxxx, Xx., CFO
The exhibits and schedules to this Design/Build Construction Contract, which are
listed in the table of contents, are not included with this Registration
Statement on Form S-4. The Company will provide these exhibits and schedules
upon the request of the Securities and Exchange Commission.
10