Tri-Square Construction L.L.C.
This Agreement is made this 1st day of September, 2005 by and between
OWNER, Hydrogen Engine Center (HEC) by President Xxx Xxxxxxxxx and
-------------------------------------------------------------------
COTRACTOR, Tri-Square Construction LLC
-------------------------------------------------------------------
PROJECT: Hydrogen Engine Center
--------------------------------------------------------------------
ARCHITECT/ENGINEER: Architects Collaborative
-------------------------------------
1 THE WORK Contractor shall furnish construction administration and management
services and use Contractor's best efforts to perform the Work in an expeditious
manner consistent with the Contract Documents. Contractor shall provide all
labor , materials, equipment and services necessary to complete the Work, as
described in Exhibit A, all of which shall be provided in full accord with and
reasonably inferable from the Contract Documents as being necessary to produce
the indicated results.
2 CONTRACT PRICE As full compensation for performance by Contractor of the Work,
Owner shall pay Contractor the lump sum price of for Phase I work for
$1,200,000.00 which will be approved upon signing this contract and Phase II for
$680,466.00 which must be approved in writing before work can begin or money
released. Total contract is for One Million, Eight Hundred Eighty Thousand, Four
Hundred, and Sixty Six and 00/100 dollars ($1,880,466.00). The lump sum price is
hereinafter referred to as the Contract Price, which shall be subject to
increase or decrease as provided in this Agreement. A down payment of $60,000.00
is due upon the signing of this contract for material ordering and
contingencies. Price on Phase I and Phase II could change if start date is
extended past 6 months.
3 INSURANCE Prior to the start of the Work, Contractor shall purchase and
maintain insurance coverage and limits of liability as set forth in Exhibit E,
that will protect Contractor from claims arising out of Contractor operations
under this Agreement, whether the operations are by Contractor, or any of
Contractor's consultants or subcontractors or anyone directly or indirectly
employed by any of them, or by anyone for whose acts any of them may be liable.
4 BONDS Performance and Payment Bonds ______ are__X__are not required of
Contractor. Such bonds shall be issued by a surety licensed in the state of the
location of the Project and must be acceptable to Owner. The penal sum of the
Payment Bond shall equal the penal sum of the Performance Bond.
5 EXHIBITS The following Exhibits are incorporated by reference and made part of
this Agreement:
EXHIBIT A: The Work, Attached four (4) pages.
--------------------------------------------------
EXHIBIT B: Contract Documents (Attach a complete listing by title, date and
number of pages.)
EXHIBIT C: Progress Schedule, Attached one (1) pages.
--------------------------------------------------
EXHIBIT D: Alternates and Unit Prices, include dates when alternates and unit
prices no longer apply, N/A pages.
---------------
EXHIBIT E: Insurance Provisions, Attached one (1) pages.
----------------------------------------------
EXHIBIT : Other,
Phase I and Phase II cost breakdowns (5) pages.
--------------------------------------------------------------------------------
6 CONTRACTOR'S RESPONSIBILITIES Contractor shall be responsible for supervision
and coordination of the Work, including the construction means, methods,
techniques, sequences and procedures utilized, unless the Contract Documents
give other specific instructions.
6.1 Except for permits and fees that are the responsibility of the Owner
pursuant to this Agreement. Contractor shall obtain and pay for all necessary
permits, licenses, renewals pertaining to the Work.
6.2 Contractor shall pay all applicable taxes enacted when bids are received or
negotiations concluded for the Work provided by Contractor.
6.3 In the event that Owner elects to perform work at the Worksite directly or
by others retained by Owner, Contractor and Owner shall coordinate the
activities of all forces at the Worksite and shall agree upon fair and
reasonable schedules and operational procedures for Worksite activities. Owner
shall require each separate contractor to cooperate with Contractor and assist
with the coordination of activities and the review of construction schedules and
operations. The Contract Price and Contract Time shall be equitably adjusted, as
mutually agreed by the parties, for changes made necessary by the coordination
of construction activities, and the construction schedule shall be revised
accordingly.
6.4 In order to facilitate its responsibilities for completion of the Work in
accordance with and as reasonably inferable from the Contract Documents, prior
to commencing the Work, Contractor shall examine and compare the drawings and
specifications with information furnished by Owner pursuant to Paragraph 7.2;
relevant field measurements made by Contractor; and any visible conditions at
the Worksite affecting the Work.
6.5 WARRANTY
6.5.1 The work shall be executed in accordance with the Contact Documents in a
workmanlike manner. Contractor warrants the all materials and equipment shall be
new unless otherwise specified, of good quality, in conformance with the
Contract Documents, and free from defective workmanship and materials.
Contractor further warrants that the Work will be free from material defects not
intrinsic in the design or materials required in the Contract Documents.
Contractor's warranty does not include remedies for defects or damages caused by
normal wear and tear during normal usage, use for a purpose for which the
Project was not intended, improper or insufficient maintenance, modifications
performed by Owner or others retained by Owner, or abuse.
6.5.2 If, prior to the Date of Substantial Completion and within one year after
the date of Substantial Completion of the Work, any portion of the Work is found
to be not in conformance with the Contract Documents ("Defective Work"), Owner
shall promptly notify Contractor in writing. Unless Owner provides written
acceptance of the condition, Contractor shall promptly correct the Defective
Work at its own cost and time and bear the expense of additional services
required for correction of any Defective Work for which it is responsible.
6.6 SAFETY Contractor shall have overall responsibility for safety precautions
and programs in the performance of the Work, except that Contractor's
subcontractors shall also be responsible for the safety of persons or property
in the performance of their work, and for compliance with the provisions of
applicable laws and regulations. Contractor shall seek to avoid injury, loss or
damage to persons or property by taking reasonable steps to protect its
employees and other persons at the Worksite; materials and equipment stored at
on-site or off-site locations for use in the Work; and property located at the
site and adjacent to Work areas, whether or not the property is part of the
Work.
-2-
6.7 HAZARDOUS MATERIALS A Hazardous Material is any substance or materials
identified now or in the future as hazardous under any federal, state or local
law or regulation, or any other substance or materials which may be considered
hazardous or otherwise subject to statutory or regulatory requirement governing
handling, disposal and/or clean-up. Contractor shall not be obligated to
commence or continue work until any Hazardous Material discovered at the
Worksite has been removed, or rendered or determined to be harmless by Owner as
certified by an independent testing laboratory and approved by the appropriate
government agency. If Contractor incurs additional costs and/or is delayed due
to the presence or remediation of Hazardous Material, Contractor shall be
entitled to an equitable adjustment in the Contract Price and/or the Contract
Time.
6.8 MATERIAL BROUGHT TO THE WORKSITE Contractor shall be responsible for the
proper delivery, handling, application, storage, removal and disposal of all
materials and substances brought to the Worksite by Contractor in accordance
with the Contract Documents and used or consumed in the performance of the Work.
6.9 SUBMITTALS Contractor shall submit to Owner and, if directed, to its
Architect/Engineer for review and approval all shop drawings, samples, product
data and similar submittals required by the Contract Documents. Contractor shall
be responsible to Owner for the accuracy and conformity f its submittals to the
Contract Documents. Contractor shall prepare and deliver its submittals to Owner
in a manner consistent with the Schedule of the Work and in such time and
sequence so as not to delay the performance of the Work or the work of Owner and
others retained by Owner. When Contractor delivers its submittals to Owner,
Contractor shall identify in writing for each submittal all changes, deviations
or substitutions from the requirements of the Contract Documents. The approval
of any Contractor submittal shall not be deemed to authorize deviations,
substitutions or changes in the requirements of the Contract Documents unless
express written approval is obtained from Owner specifically authorizing such
deviation, Substitution or change. Further, Owner shall not make any change,
deviation or substitution through the submittal process without specifically
identifying and authorizing such deviation to Contractor. Owner shall be
responsible for review and approval of submittals with reasonable promptness to
avoid causing delay. Contractor shall perform all Work strictly in accordance
with approved submittals. Owner's approval does not relieve Contract from
responsibility for Defective Work resulting from errors or omissions of any kind
on the approved Shop Drawings.
6.10 SITE CONDITIONS If the conditions at the Worksite are (a) subsurface or
other physical conditions which are materials different from those indicated in
the Contract Documents, or (b) unusual or unknown physical conditions which are
materially different from conditions ordinarily encountered and generally
recognized as inherent in Work provided for in the Contract Documents,
Contractor shall stop Work and give immediate written notice of the condition to
Owner and the Architect/Engineer. Contractor shall not be required to perform
any work relating to the unknown condition without the written mutual agreement
of the parties. Any change in the Contract Price and/or Contract Time as a
result of the unknown condition shall be made by Change Order.
6.11 CUTTING, FITTING AND PATCHING Contractor shall perform cutting, fitting and
patching necessary to coordinate the various parts of the Work and to prepare
its Work for the work of Owner or others retained by Owner.
6.12 CLEANING UP Contractor shall regularly remove debris and waste materials at
the Worksite resulting from the Work. Prior to discontinuing Work in an area,
Contractor shall clean the area and remove all rubbish and is construction
equipment, tools, machinery waste and surplus materials. Contractor shall
minimize and confine dust and debris resulting from construction activities. At
the completion of the Work, Contractor shall remove from the Worksite all
construction equipment, tools, surplus materials, waste materials and debris.
-3-
7 OWNER'S RESPONSIBILITIES Any information or services to be provided by Owner
shall provided in a timely manner so as not to delay the Work.
7.1 FINANCIAL INFORMATION Prior to commencement of the Work and thereafter at
the written request of Contractor, Owner shall provide Contractor with evidence
of Project financing. Evidence of such financing shall be a condition precedent
to Contractor's commencing or continuing the Work. Contractor shall be notified
prior to any material change in Project financing.
7.2 WORKSITE INFORMATION Owner shall provide at Owner's expense and with
reasonable promptness the following, which Contractor shall be entitled to rely
upon for its accuracy and completeness:
.1 information describing the physical characteristics of the site,
including surveys, site evaluations, legal descriptions, data or drawings
depicting existing conditions, subsurface and environmental studies, reports and
investigations;
.2 tests, inspection and other reports dealing with environmental
maters, hazardous material and other existing conditions, including structural,
mechanical and chemical tests, required by the Contract Documents or by law; and
.3 any other information or services requested in writing by Contractor
that are relevant to Contractor's performance of the Work and under Owner's
control.
The information required by this Paragraph shall be provided in reasonable
detail. Legal descriptions shall include easements, title restrictions,
boundaries, and zoning restrictions. Worksite descriptions shall include
existing buildings and other construction and all other pertinent site
conditions. Adjacent property descriptions shall include structures, streets,
sidewalks, allies, and other features relevant to the Work. Utility details
shall include available services, lines at the Worksite and adjacent thereto and
connection points. The information shall include public and private information,
subsurface information, grades, contours, and elevations, drainage data, exact
locations and dimensions, and benchmarks that can be used by Contractor in
laying out the Work.
7.3 BUILDING PERMIT, FEES AND APPROVALS Except for those required of Contractor
pursuant to this Agreement, Owner shall secure and pay for all other permits,
approvals, easements, assessments and fees required for the development,
construction, use or occupancy of permanent structures or for permanent changes
existing facilities, including the building permit.
8 SUBCONTRACTS Work not performed by Contractor with its own forces shall be
performed by subcontractors. Contractor agrees to bind every subcontractor and
materials supplier (and require every subcontractor to so bind its
subcontractors and material suppliers) to all the provisions of this Agreement
and Contractor Documents as they apply to the subcontractor's and materials
supplier's portions of the Work.
9 CONTRACT TIME September 1, 2005
9.1 DATE OF COMMENCEMENT The Date of Commencement is the date of this Agreement
as first written on page one of this Agreement, unless otherwise set forth
below: (Insert here any special provisions concerning notices to proceed and the
Data of Commencement.)
9.2 TIME Substantial Completion of the Work for Phase I shall be achieved in Two
Hundred, Ninety Seven (297) days from the date of commencement. Phase II work
scheduled will be agreed on when approval to start is given. Unless otherwise
specified in the Certificate of Substantial Completion, the Work shall be
finally complete within __Thirty__ (30) days after the date of Substantial
Completion, subject to adjustments as provided for in the Contract Documents.
Time limits stated above are of the essence of the Agreement.
-4-
10 SCHEDULE OF THE WORK Before submitting the first application for payment,
Contractor shall submit, for review by the Architect/Engineer and approval by
Owner, a Schedule of the Work that shall show the dates on which Contractor
plans to begin and to complete various parts of Work, including dates on which
information and approvals are required from Owner.
11 DELAYS AND EXTENSIONS OF TIME
11.1 If Contractor is delayed at any time in the commencement or progress of the
Work by any cause beyond the control of Contractor, Contractor shall be entitled
to an equitable extension of the Contract Time. In addition, if Contractor
incurs addition, if Contractor incurs additional costs as a result of such
delay. Contractor shall be entitled to an equitable adjustment in the Contract
Price, subject to the mutual waiver of consequential damages herein. Examples of
causes beyond the control of Contractor include, but are not limited to, the
following: acts or omissions of Owner or others retained by Owner; Changes in
the Work or the sequencing of the Work ordered by Owner, or arising from
decisions of Owner; changes in the Work or the performance of the Work; labor
disputes not involving Contractor; fire; encountering Hazardous Materials;
adverse weather conditions not reasonably anticipated; concealed or unknown
conditions; delay authorized by Owner pending dispute resolution.
11.2 To the extent a delay in the progress of the Work is caused by adverse
weather conditions not reasonably anticipated, fire, unusual transportation
delays, general labor disputes impacting the Project but not specifically
related to the Worksite, governmental agencies, or unavoidable accidents or
circumstances, Contractor shall only be entitled to its actual costs without fee
and an extension of the Date of Substantial Completion and/or Final Completion.
11.3 In the event delays to the Work are encountered for any reason, Contractor
shall provide prompt written notice to Owner of the cause of such delays after
Contractor first recognizes first recognizes the delay. Owner and Contractor
agree to undertake reasonable steps to mitigate the effect of such delays.
11.4 NOTICE OF DELAY CLAIMS If contractor request an equitable extension of
Contact time and/or an equitable adjustment in Contract price as a result of
delay, Contactor shall give Owner written notice of the claim. If contractor
causes delay in the completion of the Work, Owner shall be entitled to recover
its additional cost, subject to the mutual waiver of the consequential damages
herein.
12 ALLOWANCES All allowances stated in the Contract Documents shall be included
in the Contact Price. While Owner may direct the amounts of, and particular
material suppliers of subcontractors for, specific allowance items, if
Contractor reasonably objects to a material supplier or subcontractor, it shall
not be required to contract with them. Owner shall select allowance items in a
timely manner so as not to delay the Work. Allowances shall include the costs of
materials and equipment delivered to the Worksite less applicable trade
discounts and including requisite taxes, unloading and handling at the Worksite,
and labor and installation, unless specifically stated otherwise. Contractor's
overhead and profit for the allowances shall be included in the Contract Price,
but not in the allowances. The Contract Price shall be adjusted by Change Order
to reflect the actual costs when they are greater than or less than the
allowances.
13 CHANGES
13.1 Contractor may request and/or Owner may order changes in the Work or the
timing or sequencing of performance of the Work that impacts the Contract Price
or the Contract Time. All such changes in the Work that affect Contract Time or
Contract Price shall be formalized in a Change Order.
-5-
13.2 Owner and Contractor shall negotiate in good faith an appropriate
adjustment to the Contract Price and/or the Contract Time and shall conclude
these negotiations as expeditiously as possible. Acceptance of the Change Order
and any adjustment in the Contract Price and/or Contract Time shall not be
unreasonably withheld.
13.3 COST OR CREDIT DETERMINATION
13.3.1 An increase or decrease in the Contract Price and/or the Contract Time
resulting from a change in the Work shall be determined by one or more of the
following methods:
.1 unit prices set forth in the Agreement or as subsequently agreed;
.2 a mutually accepted, itemized lump sum;
.3 costs calculated on a basis agreed upon by Owner and Contractor
plus a fee (either a lump sum or a fee based on a percentage of
cost) to which they agree; or
.4 by the method provided below:
13.4 UNIT PRICES If unit prices are included in the Contract Documents or are
subsequently agreed to by the parties, but the character or quantity of such
unity price items as originally contemplated is so different in a proposed
Change Order that the original unit prices will cause substantial inequity to
Owner or Contractor, such unit prices shall be equitably adjusted.
13.5 PERFORMANCE OF CHANGED WORK Contractor shall not be obligated to perform
Changed Work until a Change Order has been executed by Owner and Contractor.
14 PAYMENT
14.1 SCHEDULE OF VALUES Within twenty-one (21) days from the date of execution
of this Agreement. Contractor shall prepare and submit to Owner, and if
directed, its Architect/Engineer, a schedule of values apportioned to the
various divisions or phases of the Work. Each line item contained in the
schedule of values shall be assigned and monetary price such that the total of
all items shall equal the Contract Price.
14.2 PROGRESS PAYMENTS Contractor shall submit to Owner and, if directed, its
Architect/Engineer a monthly application for payment no later than the last day
of the calendar month for the preceding thirty (30) days. Contractor's
applications for payment shall be itemized and supported by Contractor's
schedule of values and any other substantiating data as required by this
Agreement. Payment applications shall pay the amount otherwise due on any
payment application, less any amounts as set forth below, no later than ten (10)
days after Contractor has submitted a complete and accurate payment application.
Owner may deduct, from any progress payment, such amounts as may be retained
pursuant to Paragraph 14.4.
14.3 RETAINAGE From each progress payment made prior to Substantial Completion
Owner may retain _three (3)__ percent (%) of the amount otherwise due after
deduction of any amounts as provided in Paragraph 14.4 of this Agreement.
14.4 ADJUSTMENT OF CONTRACTOR'S PAYMENT APPLICATION Owner may adjust or reject a
payment application or nullify a previously approved payment application, in
whole or in part, as may reasonably be necessary to protect Owner from loss or
damage based upon the following, to the extent that Contractor is responsible
therefore under this Agreement:
.1 Contractors's repeated failure to perform the Work as required b
the Contract Documents;
.2 loss or damage for which Owner may be liable arising out of or
relating to this Agreement and caused by Contractor to Owner or to
others retained by Owner;
-6-
.3 Contractor's failure to properly pay Subcontractors for labor,
materials or equipment furnished in connection with the Work
following receipt of such payment from Owner.
.4 Defective Work not corrected in timely fashion;
.5 reasonable evidence of delay in performance of the Work such that
the Work will not be completed within Contract Time, and
.6 reasonable evidence demonstrating that the unpaid balance of the
Contract Price is insufficient to fund the cost to complete the
Work.
Owner shall give written notice to Contractor at the time of disapproving or
nullifying an application for payment of the specific reasons therefore. When
the above reasons for disapproving or nullifying an application for payment are
removed, payment shall be made for the amounts previously withheld.
14.5 PAYMENT DELAY If for any reason not the fault of Contractor, Contractor
does not receive a progress payment from Owner within seven (7) days' written
notice to Owner, and without prejudice to and in addition to any other legal
remedies, may stop Work until payment of the full amount owing to Contractor has
been received. The Contract Price and Contract Time shall be equitably adjusted
by Change Order for reasonable cost and delay resulting from shutdown, delay and
start-up.
14.6 SUBSTANTIAL COMPLETION When Substantial Completion of the Work or a
designated portion thereof is achieved, Contractor shall prepare a Certificate
of Substantial Completion that shall establish the date of Substantial
Completion, and the respective responsibilities of Owner and Contractor for
interim items such as security, maintenance, utilities, insurance and damage to
the Work, and fixing the time for completion of all items on the list
accompanying the Certificate. The Certificate of Substantial Completion shall be
submitted by Contractor to Owner for written acceptance of responsibilities
assigned in the Certificate. Unless otherwise provided in the Certificate of
Substantial Completion, warranties required by the Contract Documents shall
commence on the date of Substantial Completion of the Work or a designated
portion.
14.6.1 Upon acceptance by Owner of the Certificate of Substantial Completion,
Owner shall pay to Contractor the remaining retainage held by Owner for the Work
described in the Certificate of Substantial Completion less a sum equal to two
hundred percent (200%) of the estimated cost of completing or correcting
remaining items on that part of the Work, as agreed to by Owner and Contractor
as necessary to achieve final completion. Uncompleted items shall be completed
by Contractor in a mutually agreed time frame. Owner shall pay Contractor
monthly the amount retained for unfinished items is complete.
14.7 FINAL COMPLETION When final completion has been achieved, Contractor shall
prepare for Owner's acceptance a final application for payment stating that to
the best of Contractor' knowledge, and based on Owner's inspections, the Work
has reached final completion in accordance with the Contract Documents.
14.7.1 Final payment of the balance of the Contract Price shall be made to
Contractor within twenty (20) days after Contractor has submitted to the Owner a
complete and accurate application for final payment and the following
submissions:
.1 an affidavit declaring any indebtedness connected with the Work,
e.g. payrolls or invoices for materials or equipment, to have been
paid, satisfied or to be paid with the proceeds of final payment,
so as not to encumber Owner's property;
.2 as-built drawings, manuals, copies of warranties and all other
close-out documents required by the Contract Documents;
.3 release of any liens, conditioned on final payment being received;
.4 consent of any surely, if applicable; and
.5 a report of any accidents or injuries experienced by Contractor or
its Subcontractors at the Worksite.
-7-
14.8 Claims not reserved in writing with the making of final payment shall be
waived except for claims relating to liens or similar encumbrances, warranties,
Defective Work and latent defects.
14.9 LATE PAYMENT Payments due but unpaid shall bear interest from the date
payment is due at the prime rate prevailing at the place of the Project.
15 INDEMNITIES
15.1 To the fullest extent permitted by law, Contractor shall defend, indemnify
and hold Owner, Owner's officers, directors, members, consultants, agents and
employees and the Architect/Engineer harmless from all claims for bodily injury
and property damage, other than to the Work itself and other property insured un
Exhibit E, that may arise from the performance of the Work to the extent of the
negligence attributed to such acts or omissions by Contractor, subcontractors
or anyone employed directly or indirectly by any of them or by anyone for whose
acts any of them may be liable. Contractor shall not be required to defend,
indemnify or hold harmless Owner, Architect/Engineer or others retained by Owner
for any acts, omissions or negligence of Owner, Architect/Engineer or others
retained by Owner.
15.2 To the fullest extent permitted by law, Owner shall defend, indemnify and
hold harmless Contractor, its officers, directors or members, subcontractors or
anyone employed directly or indirectly by any of them or anyone for whose acts
any of them may be liable from all claims for bodily injury and property damage
other than property insured under Exhibit S, that may arise from the performance
of work by Owner, Architects/Engineer or others retained by Owner, to the extent
of the negligence attributed to such acts or omissions by Owner,
Architect/Engineer or others retained by Owner.
16 MUTUAL WAIVER OF CONSEQUENTIAL DAMAGES Owner and Contractor agree to waive
all claims against each other for any consequential damages that may arise out
of or relate to this Agreement. Owner agrees to waive damages including but not
limited to Owner's loss of use of the Project, any rental expenses incurred,
loss of income, profit or financing related to the Project as well as the loss
of business, loss of financing, principal office overhead and expenses, loss of
profits not related to this Project, or loss of reputation. Contractor agrees to
waive damages including but not limited to loss of business, loss of financing,
principal office overhead and expenses, loss of profits not related to this
Project, loss of bonding capacity or loss of reputation. This Paragraph shall
not be construed to preclude contractual provisions for liquidated damages when
such provisions relate to direct damages only. The provisions of this Paragraph
shall also apply to the termination of this Agreement and shall survive such
termination.
17 NOTICES TO CURE AND TERMINATION
17.1 NOTICE TO CURE A DEFAULT If Contractor persistently refuses or fails to
supply enough properly skilled workers, proper materials, and/or equipment to
maintain the approved Schedule of the Work in accordance with Article 6, or
fails to make a prompt payment to its workers, subcontractors, or materials
suppliers disregards laws, ordinances, rules, regulations or orders of any , O
authority having jurisdiction, or is otherwise guilty of a materials breach of a
provision of this Agreement, Contractor maybe deemed in default. If Contractor
fails within seven (7) working days after written notification to commence and
continue satisfactory correction of such default with diligence and promptness,
then Owner, without prejudice to any other rights or remedies, shall have the
right to take reasonable steps it deems necessary to correct deficiencies and
charge the cost to Contractor who shall be liable for such payments including
reasonable overhead, profit and attorney's fees.
-8-
17.2 TERMINATION BY OWNER If, within seven (7) days of receipt of a notice to
cure pursuant to Paragraph 17.1, Contractor fails to commence and satisfactorily
continue correction of the default set forth in the notice to cure, Owner may
notify Contractor that it intends to terminate this Agreement for default absent
appropriate corrective action within fourteen (14) additional days. After the
expiration of the additional fourteen (14) day period, Owner may terminate this
Agreement by written notice absent appropriate corrective action. Termination
for default is in addition to any other remedies available to Owner under
Paragraph 17.1 If Owner's costs arising out of Contractor's failure to cure,
including the cost of completing the Work and reasonable attorney Fees, exceed
the unpaid Contract Price, Contractor shall pay the difference to Contractor. In
the event Owner exercises its rights under this Paragraph, upon the request of
Contractor. In the event Owner exercises its rights under this Paragraph, upon
the request of the Contractor, Owner shall furnish to Contractor a detailed
accounting of the costs incurred by Owner.
17.3 TERMINATION BY CONTRACTOR Upon seven (7) days' written notice to Owner,
Contractor may terminate this Agreement if the Work has been stopped for thirty
(30) day period through no fault of Contractor for any of the following reasons:
.1 under court order or order of other governmental authorities
having jurisdiction;
.2 as a result of the declaration of a national emergency or other
governmental act during which, through no act or fault of
Contractor, materials are not available; or
17.4 In addition, upon seven (7) days' written notice to Owner, Contractor may
terminate the Agreement if Owner:
.1 fails to furnish reasonable evidence that sufficient funds are
available and committed for the entire cost of the Project in
accordance with Paragraph 7.1 or
.2 assigns this Agreement over Contractor's reasonable objection, or
.3 fails to pay Contractor in accordance with this Agreement and
Contractor has complied with the notice provisions of Paragraph
14.5, or
.4 otherwise materially breaches this Agreement.
17.5 Upon termination by Contractor pursuant to this Agreement, Contractor shall
be entitled to recover from Owner payment for all Work executed and for any
proven loss, cost or expense in connection with the Work, including all
demobilization costs plus reasonable overhead and profit.
17.6 OBLIGATIONS ARISING BEFORE TERMINATION Even after termination the
provisions of this Agreement still apply to any Work performed, payments made,
events occurring, costs charged or incurred or obligations arising before the
termination date.
18 CLAIMS AND DISPUTE RESOLUTION
18. CLAIMS FOR ADDITIONAL COST OR TIME Except as provided in Paragraphs 11.2 and
11.4 for any claim for an increase in the Contract Price and/or the Contract
Time, Contractor shall give Owner written notice of the claim within fourteen
(14) days after Contractor first recognizes the condition giving rise to the
claim, whichever is later. Except in an emergency, notice shall be given before
proceeding with the Work. Any change in the Contract Price and/or the Contract
Time resulting from such claim shall be authorized by Change Order.
-9-
18.2 WORK CONTINUANCE AND PAYMENT Unless otherwise agreed in writing, Contractor
shall continue the Work and maintain the Schedule of the Work during any dispute
resolution proceedings. If Contractor continues to perform, Owner shall continue
to make payments in accordance with the Agreement.
18.3 INTIAL DISPUTE RESOLUTION PROCESSES If a dispute arises out of or relates
to this Agreement or its breach, the parties shall endeavor to settle the
dispute first through direct discussions. If the dispute cannot be settles
through direct discussions, the parties shall endeavor to settle the dispute by
mediation under the current Construction Industry Mediation Rules of the
American Arbitration Association before recourse to any binding dispute
resolution procedures.
18.4 OTHER DISPUTE PROCESSES If neither direct discussions nor mediation
successfully resolve the dispute, the parties agree that the following shall be
used to resolve the dispute.
(check one selection only)
___Arbitration Arbitration shall be pursuant to the Construction Industry Rules
of the American Arbitration Association unless the parties mutually agree
otherwise. A written demand for arbitration shall be filed with the American
Arbitration Association and the other party to the Agreement within a reasonable
time after the dispute or claim has arisen, but in no even after the applicable
statue of limitations for a legal or equitable proceeding has run. The
arbitration award shall be final. This agreement to arbitrate shall be governed
by the Federal Arbitration Act and judgment upon the award may be confirmed in
any court having jurisdiction.
___Litigation Action may be filed in the appropriate state, or federal court
located in the jurisdiction in which the Project is located.
18.5 COST OF DISPUTE RESOLUTION The prevailing party in any dispute arising out
of or relating to this Agreement or its breach that is resolved by a binding
dispute resolution process shall be entitled to recover from the other party
reasonable attorneys' fees, costs and expenses incurred by the prevailing party
in connection with such dispute resolution process.
19 ASSIGNMENT Neither Owner nor Contractor shall assign its interest in this
Agreement without the written consent of the other except as to the assignment
of proceeds. The terms and conditions of this Agreement shall be binding on both
parties, their partners, successors, assigns and legal representatives. Neither
party to this Agreement shall assign the Agreement as a whole without written
consent of the other.
20 GOVERNING LAW This Agreement shall be governed by the law in effect at the
location of the Project.
21 JOINT DRAFTING The parties expressly agree that this Agreement was jointly
drafted, and that they both had opportunity to negotiate terms and to obtain
assistance of counsel in reviewing terms prior to execution. This Agreement
shall be construed neither against nor in favor of either party, but shall be
construed in a neutral manner.
22 NOT INCLUDED
o No landscaping
o No removal of trees or brush that isn't required to do site work
o Nothing which is not specifically listed in this contract
o No specialty items for Dyno room for safety, fire code, gas
hook-ups, etc
o No exterior electrical or plumbing on site (all utilities are
figured to the buildings)
o Any changes that occur do to engineering or Fire Xxxxxxxx which
result in price increase
-11-
23 OPTIONS The following are options and are not included in Contract Prices for
Phase I and Phase II
23.A PHASE I
o Stairs and Storage above bathrooms,
boiler room, break room and office $9,863.00 extra
o In-floor heat in assembly building $54,684.00 extra
o Snow melt in loading ramp $18,329.00 extra
o If in-floor is put in assembly
building-don't need secondary heat $4,479.00 save
o Miscellaneous items to consider $67,311.00 extra
TOTAL CHANGES $145,708.00
23.B PHASE II
o In-floor heat in office building $12,800.00 save
o Asphalt instead of concrete
OWNER: Hydrogen Engine Center CONTRACTOR: Tri Square Construction
BY: /s/ Xxxxxxxx Xxxxxxxxx BY: /s/ Xxxxxx X. Xxxx
---------------------------- -------------------------------
PRINT NAME: Xxxxxxxx Xxxxxxxxx PRINT NAME: Xxxxxx X. Xxxx
PRINT TITLE: President PRINT TITLE: President
ATTEST: ______________________________________ATTEST: __________________________
-12-