EXHIBIT 10.4
--------------------------------------------------------------------------------
AIA DOCUMENT A101
STANDARD FORM OF AGREEMENT BETWEEN
OWNER AND CONTRACTOR
WHERE THE BASIS OF PAYMENT IS A
STIPULATED SUM
1987 EDITION
THIS DOCUMENT HAS IMPORTANT LEGAL CONSEQUENCES; CONSULTATION WITH AN ATTORNEY
IS ENCOURAGED WITH RESPECT TO ITS COMPLETION OR MODIFICATION
THE 1987 EDITION OF AIA DOCUMENT A201, GENERAL CONDITIONS OF THE CONTRACT FOR
CONSTRUCTION, IS ADOPTED IN THIS DOCUMENT BY REFERENCE. DO NOT USE WITH
OTHER GENERAL CONDITIONS UNLESS THIS DOCUMENT IS MODIFIED.
This document has been approved and endorsed by The Associated General
Contractors of America.
--------------------------------------------------------------------------------
AGREEMENT
made as of the 1st day of August in the year of Nineteen Hundred and Ninety Five
BETWEEN the Owner: REPUBLIC NATIONAL BANK OF MIAMI
(NAME AND ADDRESS) 00 XX 00 Xxxxxx
Xxxxx, Xxxxxxx 00000
Attention:Xxxxxx X. Xxxxxxxx
and the Contractor: THE BARED COMPANY OF MIAMI, INC.
(NAME AND ADDRESS) 0000 XX 00 Xxxxxx
Xxxxx, Xxxxxxx 00000
The Project is: REPUBLIC NATIONAL BANK OF MIAMI
(NAME AND LOCATION) CORPORATE HEADQUARTERS
0000 Xxxxx xx Xxxx Xxxxxxxxx
Xxxxx Xxxxxx, Xxxxxxx 00000
The Architect is: XXXXXXX CANDELA & PARTNERS, INC.
(NAME AND ADDRESS) 000 Xxxxxxx Xxxxxxxx
Xxxxx Xxxxxx, Xxxxxxx 00000
The Owner and Contractor agree as set forth below.
ARTICLE 1
THE CONTRACT DOCUMENTS
The Contract Documents consist of this Agreement, Conditions of the Contract
(General, Supplementary and other Conditions), Drawings, Specifications, Addenda
issued prior to execution of this Agreement, other documents listed in this
Agreement and Modifications issued after execution of this Agreement; these form
the Contract, and are as fully a part of the Contract as if attached to this
Agreement or repeated herein. The Contract represents the entire and integrated
agreement between the parties hereto and supersedes prior negotiations,
representations or agreements, either written or oral. An enumeration of the
Contract Documents, other than Modifications, appears in Article 9.
ARTICLE 2
THE WORK OF THIS CONTRACT
The Contractor shall execute the entire work described in the Contract
Documents, except to the extent specifically indicated in the Contract Documents
to be the responsibility of others, of as follows:
The Mechanical Contractor acknowledges that Xxxxxx Construction Company
is the project general contractor and as such is responsible for the
supervision, scheduling, and coordination of the Mechanical Work, until
completion of the entire project, therefore the Mechanical Contractor
shall perform as if under direct contract with Xxxxxx Construction
Company. The Mechanical Work includes but is not limited to HVAC,
plumbing, and fire protection.
ARTICLE 3
DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION
3.1 The date of commencement is the date from which the Contract Time of
Paragraph 3.2 is measured, and shall be the date of this Agreement, as first
written above, unless a different date is stated below or provision is made for
the date to be fixed in a notice to proceed issued by the Owner. (INSERT THE
DATE OF COMMENCEMENT, IF IT DIFFERS FROM THE DATE OF THIS AGREEMENT OR, IF
APPLICABLE, STATE THAT THE DATE WILL BE FIXED IN A NOTICE TO PROCEED.)
Unless the date of commencement is established by a notice to proceed issued by
the Owner, the Contractor shall notify the Owner in writing not less than five
days before commencing the Work to permit the timely filing of mortgages,
mechanic's liens and other security interests.
3.2 (The Contractor shall achieve Substantial Completion of the entire Work not
later than (INSERT THE CALENDAR DATE OR NUMBER OF CALENDAR DAYS AFTER THE DATE
OF COMMENCEMENT. ALSO INSERT ANY REQUIREMENTS FOR EARLIER SUBSTANTIAL COMPLETION
OF CERTAIN PORTIONS OF THE WORK, IF NOT STATED ELSEWHERE IN THE CONTRACT
DOCUMENTS.)
Date of Substantial Completion for the mechanical scope of the Work shall be
fixed by Xxxxxx Construction Company to meet the overall project scope of the
Work of four hundred sixty (460) calendar days after date of commencement as
fixed in the Notice to Proceed issued to Xxxxxx Construction Company by the
Owner, subject to adjustments of this Contract Time as provided in the Contract
Documents.
(INSERT PROVISIONS, IF ANY, FOR LIQUIDATED DAMAGES RELATING TO FAILURE TO
COMPLETE ON TIME.)
Liquidated damages in the amount of three thousand four hundred
twenty-five dollars ($3,425.00) shall be assessed for each calendar day
required for the completion of all Work in excess of the number of
calendar days allotted for the Work.
ARTICLE 4
CONTRACT SUM
4.1 The Owner shall pay the Contractor in current funds for the Contractor's
performance of the Contract the Contract Sum of THREE MILLION FOUR HUNDRED FIFTY
ONE THOUSAND Dollars ($3,451,000.00), subject to additions and deductions as
provided in the Contract Documents.
4.2 The Contract Sum is based upon the following alternates, if any, which are
described in the Contract Documents and are hereby accepted by the Owner:
(STATE THE NUMBERS OR OTHER IDENTIFICATION OF ACCEPTED ALTERNATES. IF DECISIONS
ON OTHER ALTERNATES ARE TO BE MADE BY THE OWNER SUBSEQUENT TO THE EXECUTION OF
THIS AGREEMENT, ATTACH A SCHEDULE OF SUCH OTHER ALTERNATES SHOWING THE AMOUNT
FOR EACH AND THE DATE UNTIL WHICH THAT AMOUNT IS VALID.)
4.2.1 Voluntary Alternate #2: Provide higher efficiency chiller of
0.57 KW/Ton: Add $22,000.00. All other design specifications
remain unchanged.
4.3 Unit prices, if any, are as follows:
------- NOT APPLICABLE-----
ARTICLE 5
PROGRESS PAYMENTS
5.1 Based upon Applications for Payment submitted to the Architect by the
Contractor and Certificates for Payment issued by the Architect, the Owner shall
make progress payments on account of the Contract Sum to the Contractor as
provided below and elsewhere in the Contract Documents.
5.2 The period covered by each Application for Payment shall be one calendar
month ending on the last day of the month, or as follows: ---NOT APPLICABLE---
5.3 Provided an Application for Payment is received by the Architect not later
than the twentieth calendar day of the following month. If an Application for
Payment is received by the Architect after the application date fixed above,
payment should be made by the Owner not later than twenty calendar days after
the Architect receives the Application for Payment.
5.4 Each Application for Payment shall be based upon the Schedule of Values
submitted by the Contractor in accordance with the Contract Documents. The
Schedule of Values shall allocate the entire Contract Sum among the various
portions of the Work and be prepared in such form and supported by such data to
substantiate its accuracy as the Architect may require. This Schedule, unless
objected to by the Architect, shall be used as a basis for reviewing the
Contractor's Applications for Payment.
5.5 Applications for Payment shall indicate the percentage of completion of each
portion of the Work as of the end of the period covered by the Application for
Payment.
5.6 Subject to the provisions of the Contract Documents, the amount of each
progress payment shall be computed as follows:
5.6.1 Take that portion of the Contract Sum properly allocable to
completed Work as determined by multiplying the percentage
completion of each portion of the Work by the share of the total
Contract Sum allocated to that portion of the Work in the
Schedule of Values, less retainage of TEN percent (10%). Pending
final determination of cost to the Owner of changes in the Work,
amounts not in dispute may be included as provided in
Subparagraph 7.3.7 of the General Conditions even though the
Contract Sum has not yet been adjusted by Change Order;
5.6.2 Add that portion of the Contract Sum properly allocable to
materials and equipment delivered and suitably stored at the site
for subsequent incorporation in the completed construction (or,
if approved in advance by the Owner, suitably stored off the site
at a location agreed upon in writing), less retainage of TEN
percent (10%);
5.6.3 Subtract the aggregate of previous payments made by the Owner;
and
5.6.4 Subtract amounts, if any, for which the Architect has withheld
or nullified a Certificate for Payment as provided in Paragraph
9.5 of the General Conditions.
5.7 The progress payment amount determined in accordance with Paragraph 5.6
shall be further modified under the following circumstances:
5.7.1 Add, upon Substantial Completion of the Work, a sum sufficient
to increase the total payments to NINETY percent (90%) of the
Contract Sum, less such amounts as the Architect shall determine
for incomplete Work and unsettled claims; and
5.7.2 Add, if final completion of the Work is thereafter materially
delayed through no fault of the Contractor, any additional
amounts payable in accordance with Subparagraph 9.10.3 of the
General Conditions.
5.8 Reduction or limitation of retainage, if any, shall be as follows: (IF IT IS
INTENDED PRIOR TO SUBSTANTIAL COMPLETION OF THE ENTIRE WORK, TO REDUCE OR LIMIT
THE RETAINAGE RESULTING FROM THE PERCENTAGES INSERTED IN SUBPARAGRAPHS 5.6.1 AND
5.6.2 ABOVE, AND THIS IS NOT EXPLAINED ELSEWHERE IN THE CONTRACT DOCUMENTS,
INSERT HERE PROVISIONS FOR SUCH REDUCTION OR LIMITATION.)
Each such statement shall be for an amount equal to an estimate of the
Cost of the Work completed and materials delivered, less all previous
payments and less a retainage of 10% of that portion of the Work; when
the Work is 50% complete and the Owner approves, there shall be no
further retainage withheld on subsequent payments; and the balance shall
be paid when the Work is 100% complete and accepted by the Architect and
Owner.
ARTICLE 6
FINAL PAYMENT
Final payment, constituting the entire unpaid balance of the Contract Sum, shall
be made by the Owner to the Contractor when (1) the Contract has been fully
performed by the Contractor except for the Contractor's
responsibility to correct nonconforming Work as provided in Subparagraph 12.2.2
of the General Conditions and to satisfy other requirements, if any, which
necessarily survive final payment; and (2) a final Certificate for Payment has
been issued by the Architect; such final payment shall be made by the Owner not
more than 30 days after the issuance of the Architect's final Certificate for
Payment, or as follows:
------ NOTHING FOLLOWS -------
ARTICLE 7
MISCELLANEOUS PROVISIONS
7.1 Where reference is made in this Agreement to a provision of the General
Conditions or another Contract Document, the reference refers to that provision
as amended or supplemented by other provisions of the Contract Documents.
7.2 Payments due and unpaid under the Contract shall bear interest from the date
payment is due at the rate stated below, or in the absence thereof, at the legal
rate prevailing from time to time at the place where the Project is located.
(INSERT RATE OF INTEREST AGREED UPON, IF ANY.)
Payment due and unpaid under the Contract shall not bear interest from
the date payment is due for a grace period of thirty (30) days.
Following the grace period, payments due and unpaid under the Contract
shall bear interest at the rate of five percent (5%) per year simple
interest.
(USURY LAWS AND REQUIREMENTS UNDER THE FEDERAL TRUTH IN LENDING ACT, SIMILAR
STATE AND LOCAL CONSUMER CREDIT LAWS AND OTHER REGULATIONS AT THE OWNER'S AND
CONTRACTOR'S PRINCIPAL PLACES OF BUSINESS, THE LOCATION OF THE PROJECT AND
ELSEWHERE MAY AFFECT THE VALIDITY OF IBIS PROVISION. LEGAL ADVICE SHOULD BE
OBTAINED WITH RESPECT TO DELETIONS OR MODIFICATIONS, AND ALSO REGARDING
REQUIREMENTS SUCH AS WRITTEN DISCLOSURES OR WAIVERS.)
7.3 Other provisions:
By separate Agreement, the Owner has conveyed to Xxxxxx Construction
Company full responsibility for the supervision, scheduling, and
coordination of the Mechanical Work as described herein, until
completion of the entire project.
The Owner has advanced the Contractor a sum of EIGHT HUNDRED SIXTY TWO
THOUSAND SEVEN HUNDRED FIFTY DOLLARS toward the purchase of material and
equipment required for the Work. Said advance shall only be made upon
acceptance by the Owner of a fully rescindable Advance Payment Bond
naming the Owner as Obligee.
ARTICLE 8
TERMINATION OR SUSPENSION
8.1 The Contract may be terminated by the Owner or the Contractor as provided in
Article 14 of the General Conditions.
8.2 The Work may be suspended by the Owner as provided in Article 14 of the
General Conditions.
ARTICLE 9
ENUMERATION OF CONTRACT DOCUMENTS
9.1 The Contract Documents, except for Modifications issued after execution of
this Agreement, are enumerated as follows:
9.1.1 The Agreement is this executed Standard Form of Agreement
Between Owner and Contractor, AIA Document A101, 1987 Edition.
9.1.2 The General Conditions are the General Conditions of the
Contract for Construction, AIA Document A201, 1987 Edition.
9.1.3 The Supplementary and other Conditions of the Contract are those
contained in the Project Manual dated June 13, 1995, and are as
follows:
DOCUMENT TITLE PAGES
00020 Invitation to Bid 00020-1 AND 00020-2
00100 Instructions to Bidders 00100-1
00120 Supplementary Instructions to Bidders 00120-1 and 00120-2
00310 Bid Form 00310-1 thru 00310-3
00410 Bid Form 00410-1
00430 Subcontractors List 00430-1
00610 Performance Bond 00610-1 thru 00610-3
00620 Labor and Material Payment Bond 00620-1 and 00620-2
00710 General Conditions of the Contract 00710-1
00810 Supplementary Conditions 00810-1 thru 00810-21
00810 Appendix - Cash Flow Projection Form
9.1.4 The Specifications are those contained in the Project Manual
dated as in Subparagraph 9.1.3, and are as follows:
(EITHER LIST THE SPECIFICATIONS HERE OR REFER TO AN EXHIBIT ATTACHED TO THIS
AGREEMENT.)
SECTION TITLE PAGES
Refer to Exhibit A - Project Manual Table of Contents
9.1.5 The Drawings are as follows, and are dated ____________________
unless a different date is shown below:
(EITHER LIST THE DRAWINGS HERE OR REFER SO AN EXHIBIT ATTACHED TO IBIS
AGREEMENT.)
NUMBER TITLE DATE
Refer to Exhibit B - Index of Drawings
9.1.6 The Addenda, if any, are as follows:
NUMBER DATE PAGES
Addendum 1 June 30, 1995 Refer to Exhibit C for
complete listing of Addenda
pages
------- NOTHING FOLLOWS -------
Portions of Addenda relating to bidding requirements are not part of the
Contract Documents unless the bidding requirements arc also enumerated in this
Article 9.
9.1.7 Other documents, if any, forming Part of the Contract Documents
are as follows: (LIST HERE ANY ADDITIONAL DOCUMENTS WHICH ARE INTENDED TO FORM
PART OF THE CONTRACT DOCUMENTS. THE GENERAL CONDITIONS PROVIDE THAT BIDDING
REQUIREMENTS SUCH AS ADVERTISEMENT OR INVITATION TO BID, INSTRUCTIONS TO
BIDDERS, SAMPLE FORMS AND THE CONTRACTOR'S BID ARE NOT PART OF THE CONTRACT
DOCUMENTS UNLESS ENUMERATED IN THIS AGREEMENT. THEY SHOULD BE LISTED HERE ONLY
IF INTENDED TO BE PART OF THE CONTRACT DOCUMENTS.)
------ NOTHING FOLLOWS -------
This Agreement is entered into as of the day and year first written above and is
executed in at least three original copies of which one is to be delivered to
the Contractor, one to the Architect for use in the administration of the
Contract, and the remainder to the Owner.
OWNER Republic National Bank of Miami CONTRACTOR The Bared Company of Miami, Inc.
/S/ XXXXX XXXXXXXX, XX. /S/ XXXX X. BARED
-------------------------------------- ---------------------------------------------
(SIGNATURE) (SIGNATURE
XXXXX XXXXXXXX, XX. PRESIDENT XXXX X. BARED VICE PRESIDENT
-------------------------------------- ---------------------------------------------
(PRINTED NAME AND TITLE) (PRINTED NAME AND TITLE)
EXHIBIT A
PROJECT MANUAL TABLE OF CONTENTS
Exhibit to OWNER AND CONTRACTOR AGREEMENT
PROJECT MANUAL
TABLE OF CONTENTS
FOR
MECHANICAL WORK
FOR
REPUBLIC NATIONAL BANK OF MIAMI
HEADQUARTERS BUILDING
CORAL GABLES, FLORIDA
A/E PROJECT NO C-0019 JUNE 20, 1995
--------------------------------------------------------------------------------
DIVISION SECTION TITLE
BIDDING REQUIREMENTS, CONTRACT FORMS, AND
CONDITIONS OF THE CONTRACT:
00020 Invitation to Bid
00100 Instructions to Bidders
00120 Supplementary Instructions to Bidders
00310 Bid Form
00410 Bid Bond
00430 Subcontractors List
00610 Performance Bond
00620 Labor and Material Payment Bond
00710 General Conditions of the Contract
00810 Supplementary Conditions
00810 Appendix-Cash Flow Projection Form
1. GENERAL REQUIREMENTS:
01010 Summary of Work
01043 Mechanical and Electrical General
Requirements
01200 Project Meetings
01311 Critical Path Method Scheduling
01340 Shop Drawings, Product Data and Samples
01410 Testing Laboratory Services
01500 Construction Facilities and Temporary
Controls
01600 Material and Equipment
01700 Contract Closeout
2. AND 14. NOT APPLICABLE
15. MECHANICAL:
15042 Test (HVAC)
15175 Tanks
15240 Vibration Isolation (HVAC)
15251 Thermal Insulation (HVAC
15260 Thermal Insulation (Plumbing)
15300 Fire Protection (General Requirements)
15330 Automatic Sprinkler Systems
15375 Standpipe and Hose Systems (Including
Horizontal Bulk Main Supply to Vertical
Standpipes)
15377 Fire Pump and Controls
15410 Piping (Plumbing)
15421 Drains and Cleanouts
15430 Valves, Cocks and Faucets (Plumbing)
15435 Piping Specialties (Plumbing)
15440 Plumbing Fixtures, Trim and Supports
15450 Plumbing Equipment
15483 Fuel Oil Systems
15505 Water Treatment Systems
15510 Piping (HVAC)
00000 Xxxxxx and Specialties (HVAQ)
15540 Pumping Equipment (HVAC)
15655 Cooling Towers
15680 Centrifugal Water Chillers
15855 Air Handling Equipment
15885 Air Filtration Equipment
15890 Ductwork
15910 Ductwork Accessories
15930 Air Terminals (HVAC)
15960 Energy Management and Control Systems (EMCS)
15970 Controls and Instrumentation
15990 Testing and Balancing (by Owner)
16. NOT APPLICABLE
APPENDIX:
Mechanical (HVAC) Description of Systems
Plumbing Systems for Republic National Bank Building
END
Project No. C - 0019
EXHIBIT B
INDEX OF DRAWINGS
PLUMBING
P.1.0 LEGEND AND GENERAL NOTES
P.2.0 GROUND LEVEL PLUMBING AND FIRE PROTECTION
P.2.2 MEZZANINE LEVEL PLUMBING AND FIRE PROTECTION
X.0.0 XXXXXXX XXXXXX XXXXX 0XX XXXX 0XX XXXXX PLUMBING AND FIRE PROTECTION
X.0.0 XXXXXX XXXXX 0XX XXXXX XXXXXXXX AND FIRE PROTECTION
P.2.5 OFFICE LEVEL 7TH FLOOR PLUMBING AND FIRE PROTECTION
P.2.6 TYPICAL OFFICE LEVEL 8TH THRU 14TH FLOOR PLUMBING AND FIRE PROTECTION
P.2.7 EXECUTIVE PENTHOUSE LEVEL 15TH FLOOR PLUMBING AND FIRE PROTECTION
P.2.8 MECHANICAL ROOM AND ROOF LEVEL 16TH FLOOR PLUMBING AND FIRE PROTECTION
P.3.0 DETAILS
P.4.1 SANITARY RISER PIPING DIAGRAM
P.4.2 WATER RISER PIPING DIAGRAM
P.4.3 FIRE STANDPIPE RISER PIPING DIAGRAM
P.4.4 STORM DRAINAGE RISER PIPING DIAGRAM
MECHANICAL
M.1.0 STANDARD SYMBOLS & LEGEND
M.2.1 GROUND LEVEL
M.2.2 MEZZ. LEVEL
M.2.3 XXX. XXXXXX XXXXX 0XX XXXX 0XX XX.
M.2.4 GARAGE LEVEL 6TH FL.
M.2.5 OFFICE LEVEL 7TH FL.
M.2.6 TYPICAL OFFICE LEVEL 8TH THRU 14TH FL.
M.2.7 EXECUTIVE PENTHOUSE LEVEL I5TH FL.
M.2.8 MECH. XX. XXXXX 00XX XX.
M.3.0 DETAILS
M.3.1 HVAC RISER DIAGRAMS
M.3.2 HVAC PIPING DIAGRAM
M.4.1 POINTS LIST & SEQUENCE OF OPERATIONS
M.4.2 HVAC SCHEDULES
Exhibit to OWNER AND CONTRACTOR AGREEMENT
EXHIBIT C
ADDENDA
Exhibit to OWNER AND CONTRACTOR AGREEMENT
ADDENDUM NO. 1
REPUBLIC NATIONAL BANK OF MIAMI
MECHANICAL WORK
FOR
HEADQUARTERS BUILDING
0000 Xxxxx xx Xxxx Xxxxxxxxx
Xxxxx Xxxxxx, Xxxxxxx
Project No. C0019
June 30, 1995
This addendum forms a part of the Contract Documents and modifies the original
Bidding Documents. Acknowledge receipt of this Addendum in the space provided on
the Bid Form. Failure to do so will subject the Bidder to disqualification.
CHANGES TO PROJECT MANUAL
Section 15680 - CENTRIFUGAL WATER CHILLERS
Page 15680-1, para. 1.03 A., shall read "Quality Assurance: Parts shall carry a
five year warranty."
Section 15960 - ENERGY MANAGEMENT AND CONTROL SYSTEM (EMCS)
DELETE in its entirety.
Section 15890 - DUCTWORK
DELETE in its entirety and REPLACE with new Section 15890, DUCTWORK.
END OF ADDENDUM
Project No. C-0019 ADDENDUM NO. 1 ADD NO. 1-1
Project No. C-0019 XXXXXXXX XX. 0 00000-00
XXXXXX XXXXX TOILETS GRAPH
Project No. C-0019 ADDENDUM NO. 1 15890-10
SECTION 15890 - DUCTWORK
PART I GENERAL
1.01 WORK INCLUDED
A. Acoustical Treatment (Lining).
B. Dampers/Splitters.
C. Ductwork - Standard.
D. Ductwork - Special.
E. Emergency Generator Ductwork.
F. Fittings.
G. Flexible Duct.
H. Hoods.
I. Installation of Automatic Dampers.
J. Louvers & Blank-Off Panels.
K. Medium & High Pressure Take-Offs.
L. Moisture Eliminators.
M. Plenums & Casings.
N. Sealing & Leaks Testing.
1.02 RELATED WORK
A. Section 10200 - Architectural Louvers.
B. Section 11400 - Kitchen Hoods.
C. Section 15251 - Mechanical Insulation.
D. Section 15910 - Ductwork Accessories.
1.03 QUALITY ASSURANCE
A. Acoustical Treatment
1. All acoustical duct linings shall meet Erosion Test
method described in U.L. Publication No. 81.
2. All acoustical duct lining materials shall have fire
and fuel contributed and smoke hazard ratings, as
tested by procedure ASTM E-84, not greater than:
Flame Spread - 25
Fuel Contributed & Smoke Developed - 50
B. Duct Construction
1. All ductwork shall meet the requirements of "HVAC Duct
Construction Standards" published by "Sheet Metal and Air
Conditioning Contractors National Association, Inc."
Project No. C-0019 ADDENDUM NO. 1 15890-11
1.04 SUBMITTALS
A. Shop Drawings, Product Data & Samples
1. Refer to Section 01043.
2. Prior to the installation of any work, the Trade
shall submit for review a ductwork brochure complete
with any required drawings indicating the exact
procedures, types of materials, sheet metal gauges,
types of joints, reinforcing, etc., that he intends
to use on this project.
3. Detailed ductwork layouts shall be drawn to a scale
of not less than1/4" equal to 1-0".
4. One copy of all shop drawings and product data shall
be forwarded to the Testing and Balancing Engineer
(Refer to Section 15990).
PART 2 PRODUCTS
2.01 ACCEPTABLE MANUFACTURERS
A. The following is a list of manufacturers' names of material
and equipment that are acceptable.
ITEM OR MATERIAL OR
EQUIPMENT MANUFACTURER
--------------------- ------------
Acoustical Treatment (Lining) Xxxxx Corning, Manville
Mechanical Insulation, Xxxxx.
Dampers, Splitter (Hardware) Vent Fabrics Co., Young,
Regulator Co
Ductwork
1. Round X.X. Xxxxxxxxx Co., United Sheet
Metal Corp., Semco
2. Oval X.X. Xxxxxxxxx Co., United Sheet
Metal Corp., Semco
3. Flexible Flexmaster, Thermaflex, Technaflex
2.02 ACOUSTICAL TREATMENT
A. Duct lining, where indicated, and/or as hereinafter specified
shall be equal to Manville 1" thick Permacote Linacoustic
fiberglass duct liner with factory applied edge coating.
1. The liner shall meet the Life Safety Standards as
established by NFPA 90A and 90B. The duct liner shall
conform to the requirements of ASTM C1071, with an
Project No. C-0019 XXXXXXXX XX. 0 00000-00
XXX not less than 0.70 as tested per ASTM C423 using a Type A
mounting and a thermal conductivity no higher than 0.25 at
75(degree)F mean temperature.
2. All portions of duct designed to receive duct liner shall be
completely covered with 1" thick Permacote Linacoustic. The
smooth, black coated mat surfaces of the Permacote Linacoustic
shall face the air stream. All Permacote Linacoustic shall be cut
to assure tight, overlapped corner joints. The top pieces shall be
supported by the side pieces.
3. Permacote Linacoustic shall be adhered to the sheet metal with
full coverage of an approved adhesive, and all exposed leading
edges and transverse joints shall be neatly butted without gaps
and be coated with Permacote factory-applied edge coating.
4. When velocity exceeds 4000 fpm, use metal nosing on every
leading edge. Nosing may be formed on duct or be channel or zee
attached by screws, rivets or welds.
5. The Permacote Linacoustic shall be additionally secured with
mechanical fasteners either impact driven or weld-secured, spaced
per manufacturers recommendations.
B. Sound Absorption Coefficients (Type A Mounting) tested in
Accordance with ASTM C 423-81 and ASTM E 795.
(INSERT THICKNESS TABLE FROM HARD COPY PAGE 15890-3)
C. Ducts required to have acoustical treatment shall be lined
complete to air grille or diffuser, or to indicated termination
point.
Size on the Drawings represents actual finished inside duct
dimensions. In all cases where ducts are to he lined, the actual
finished sheet metal ductwork shall be increased by two times,
the thickness of lining applied.
EXAMPLE: Duct dimension 12" x 12" (assume 1" thick lining) actual metal
duct installed shall be 14" x 14".
D. All supply ductwork from VAV boxes or from VKV powered boxes and up
to air diffusers shall be acoustically lined.
2.03 DAMPERS, SPLITTERS, ETC.
A. Furnish and install all manual dampers, splitters, and deflectors
shown on the Drawings or wherever required for the proper air flow and balancing
of the air handling systems and as specified. Hardware shall be equal to
Ventfabrics Co.
Project No. C-0019 ADDENDUM NO. 1 15890-3
Project No. C-0019 ADDENDUM NO. 1 15890-13
1. Manual dampers and splitters in square or rectangular low pressure
ductwork shall be not less than No. 16 U.S.S. gauge galvanized sheet steel.
Provide manual dampers and splitters with adjustment means with fixing device.
Dampers shall be easy working and provided with steel shafts and No. 609 end
bearings.
2. Branch line balancing dampers in medium pressure ductwork shall be of
the butterfly type of No. 16 U.S.S. gauge galvanized sheet steel with rounded
edges and they shall be vibration free and shall have locking devices and
airtight packing glands where damper shafts extend thru ductwork.
3. Manual dampers in ductwork larger than 2 square feet shall be
opposed-blade volume dampers with maximum 8" blades. Provide No. 555 quadrant
control.
4. wherever damper fixing or locking devices are not exposed or
accessible thru access panels, provide Ventlok No. 677 or Young No. 315 key
operated regulators with prime coated adjustable covers.
2.04 FITTINGS
A. Elbows shall have an inside radius equal to a minimum of 3/4 the
width of the duct.
B. Radius elbows, 18" and larger, shall be provided with turning blades
at 1/3 and 1/2 the width of the duct from the inside radius. Turning vanes shall
be provided with hemmed ends.
C. Square elbows shall be used only where indicated or where required to
fit construction and only on low pressure systems. Provide all square elbows
with turning vanes.
D. Turning vanes 36" or less shall be single thickness and turning vanes
longer than 36" shall be double width.
2.05 FLEXIBLE DUCTWORK
A. Flexible ductwork shall be factory fabricated assembly of corrosion
resistant reinforcing wire helix permanently bonded and enclosed in reinforced
aluminum foil/polyester laminate. Duct shall be UL listed 181 Class I and shall
comply with NFPA 90A and 90B and all other Governmental Authorities having
jurisdiction. 1. Duct material shall be factory wrapped with fiberglass
insulation with a C factor of .23 or less. The insulation shall be encased in a
fire retardant vapor barrier jacket.
2. Flexible ductwork shall he installed for the following:
Project No. C-0019 XXXXXXXX XX. 0 00000-0
Xxxxxxx to supply outlets, where indicated. Runouts to exhaust inlets,
where indicated.
Project No. C-0019 ADDENDUM NO. 1 15890-14
3. Flexible ductwork shall be installed using extra heavy flexible duct
straps equal to those manufactured by Catamount Manufacturing Inc.
PART 3 EXECUTION
3.01 DAMPERS/SPLITTERS, ETC.
A. Damper Locations: Volume dampers and splitters shall be provided in
the following minimum locations and as additionally indicated on the Drawings.
1. Provide splitters for each supply branch.
2. Provide volume dampers for each horizontal supply and exhaust branch
from vertical risers serving 2 or more floors.
3. Provide volume dampers on supply and exhaust branches serving 2 or
more outlets where same is not provided with splitters.
3.02 DUCTWORK - STANDARD
A. materials
1. Unless otherwise specified, all xxxxxxxx, ductwork, casings,
connections, angles, stiffeners, access doors and frames, etc., shall be of hot
dipped galvanized prime quality steel. Sheet metal thicknesses, types of
permissible joints, spacing and stiffeners and/or transverse reinforcing, cross
breaking, etc., shall be as herein specified: Classification of duct systems
shall be as noted in the Fan Schedule on the Drawings and/or as hereinafter
specified.
B. Ductwork Classification
1. The largest side of a rectangular duct shall dictate the gauge and
reinforcement requirements for all four sides.
C. Duct Construction
1. All ductwork shall be constructed as specified in "HVAC Duct
Construction Standards" published by "Sheet Metal and Air Conditioning
Contractors National Association, Inc." for positive or negative static
pressures that meet the requirements of that portion of the system in which the
ductwork is installed.
a. All supply ductwork from the fan discharge to VAV Project No. C-0019
ADDENDUM NO. 1 15890-S or fan-powered box shall be constructed for positive
pressures of 3" w.g.
b. All branch supply ductwork from terminal unit to room outlet shall be
constructed for positive pressures of 1" w.g.
Project No. C-0019 XXXXXXXX XX. 0 00000-00
X. All exhaust/return air ductwork shall be constructed for positive or
negative pressures of 1" w.g.
d. All other ductwork shall be constructed for positive or negative
pressures of 2" x.x.
X. Rectangular Joints and Seams
1. The Trade Contractor may at his option incorporate proprietary
transverse duct connections on all ductwork 36 inches wide and larger. Certified
test results for the proprietary transverse duct connections must conform to the
entire sheet and joint deflection criteria included in Section VII of the 1985
SMACNA Manual, First Edition.
a. Subject to the above criteria, proprietary transverse joints shall be
as manufactured by Ductmate Industries, Mezlock, Nexus or WDCI.
b. Shop drawing submittals shall include certified test results,
material safety data sheets and applicable spec sheets.
2. Longitudinal seams shall be fabricated in accordance with SMACNA.
E. Miscellaneous instructions
1. All transverse joints, longitudinal seams, and duct wall penetrations
in low pressure ductwork (3" w.g. and below) except at companion angles, and
elsewhere as may be required shall be sealed with Xxxxxx 32-14 or 32-15 or
Ductmate #795 sealant (SMACNA Seal Class A). Sealant shall be pumped or painted
into joints, as required, after assembly. Sealant shall be allowed to set for 48
hours before any air pressure is put on system. All tie bars, bolts and rivets
shall be sealed with the specified sealant. Sealant as manufactured by Minnesota
Mining No. 800 or United Sheet Metal will be considered equal.
a. Both sides of all welds shall be painted with zinc chromate primer
for corrosion protection.
b. All reinforcing angles, joints, etc., shall be galvanized mild steel.
Project No. C-0019 ADDENDUM NO. 1 15890-6
Round and/or oval Ductwork
1. Round and/or oval ductwork systems shall be fabricated of prime
quality hot dipped, galvanized, zinc coated, sheet steel as specified in "HVAC
Duct Construction Standards" published by the "Sheet Metal and Air Conditioning
Contractors National Association, Inc." for the maxinum static pressure that
will be encountered.
a. Reducing fittings, tees, crosses, etc., shall be of conical type.
Project No. C-0019 ADDENDUM NO. 1 15890-16
b. All joints shall be painted with Xxxxxx 32-14 or 32-15 sealant
Minnesota Mining No. 800, or United Sheet Metal sealant after fabrication.
c. Both sides of all welds shall be painted with zinc chromate primer.
d. Sleeve joints shall be of same gauge as fittings and shall be
installed with sealant and sheet metal screws or rivets on 15" centers with a
minimum of 3 fasteners per joint. Paint with sealant after fabrication.
e. Allow sealants to set for 48 hours before any pressure is applied to
the systems.
f. Flanged joints shall be made with 5/16" bolts on 7" centers with
neoprene gasket or sealant between angles. Angles for flanged joints or
reinforcing shall be fastened to ductwork by welding.
3.03 DUCTWORK SPECIAL CONSTRUCTION
A. Acoustical Ductwork
1. Where shown on the Drawings, provide United Sheet Metal Co.
"Acousti-K27" or approved equal acoustical ductwork. Ductwork shall be of the
double wall zinc coated steel type spaced 1" apart and uniformly packed with
fiberglass insulation with effective thermal conductivity of .27
BTU/hr./sq./ft./degrees F. at 75 degrees F. mean temperature.
a. The pressure shell shall be of No. 24 gauge steel perforated with
hole size and spacing as recommended by the manufacturer.
b. Finish both ends of section with insulation ends provided by the
manufacturer.
Project No. C-0019 XXXXXXXX XX. 0 00000-0
X. Dishwasher Exhaust Ductwork
1. Ductwork from dishwasher and elsewhere, where indicated or specified
as stainless steel shall be entirely constructed of Type 316 stainless steel of
same gauges specified for galvanized ductwork. Ductwork shall be welded
watertight using compatible welding rod, 309-L or equal, and shall pitch
downward to dishwasher.
a. Ductwork shall have Type 2B mill finish where concealed from view.
b. Ductwork shall have Type 4 polished finish where exposed to view. All
welds shall be ground and polished.
D. Exterior Ductwork
Project No. C-0019 ADDENDUM NO. 1 15890-17
1. Exterior ductwork shall be the same as specified for low pressure
ductwork except that all joints, reinforcing angles, etc. shall be inside the
ductwork. Ductwork shall be lined as herein specified and provided with
counterflashing. See drawings for installation details. Secure ductwork to roof
slab with self-drilling expansion xxxxxxx and fasteners.
E. Kitchen Exhaust Ductwork
1. Kitchen exhaust ductwork, shall be fabricated of No.14 gauge
galvanized steel, with bracing as specified for galvanized ductwork.
a. Fabricate and assemble the kitchen exhaust ductwork, of all
continuous welded seams and joints.
b. Both sides of all welds shall be painted with zinc chromate primer.
c. Provide access panels in ductwork at each change in direction and
every 50-0" on horizontal runs. In horizontal sections the lower edge of the
access panel shall be not less 1-1/2" from bottom of duct. Access panels shall
be of 14 gauge galvanized steel with 1/8" ceramic fiber insulation.
3.04 EMERGENCY GENERATOR DUCTWORK
A. Provide sheet metal connection between unit mounted radiator and
exhaust louvers with necessary flexible connections, access doors, etc.
Project No. C-0019 ADDENDUM NO. 1 15890-8
3.05 FITTINGS
A. Elbows, tapers, offsets branches, splitters, branch connections, test
hole connections, and like items, to be in accordance with recommendations of
the applicable SMACNA Duct Manual for Ventilating and Air Conditioning Systems
(latest issue) unless otherwise specified.
B. Offsets shall have inside radii equal to a minimum of 3/4 the width
of the duct. If the specified radius cannot be held separate, fittings shall be
used. Do not use close radius and barrel fittings.
C. Provide 45 degree branch and tee connections. Tee tap-ins at 90
degrees are not acceptable.
D. All branch or tee connections to medium pressure ductwork to be
expanded to 30 degrees on at least three sides.
3.06 FLEXIBLE DUCTWORK
A. Connections of flexible ductwork to sheet metal ductwork and/or
equipment shall be made in accordance with flexible ductwork manufacturer's
recommendations and instructions.
Project No. C-0019 ADDENDUM NO. 1 15890-18
1. Maximum length of flexible ductwork shall be W-O". 2. Flexible
ductwork shall not penetrate any wall without Architect's approval.
3.07 HOODS
A. Kitchen Range Hoods will be provided as specified in other Sections
of these specifications. The work under this Section shall include furnishing
and installing the exhaust ductwork and making final connections to the hood as
required.
B. All hood exhaust ductwork shall be constructed of material as
hereinafter specified for the intended service.
3.08 INSTALLATION OF AUTOMATIC DAMPERS
A. Install all automatic dampers furnished by and under the supervision
of the Automatic Temperature Control manufacturer.
1. All blank-off plates and conversions necessary to install smaller
than duct size dampers shall be the responsibility of the Air Handling System
Trade.
2. The Temperature Control Manufacturer shall submit a schedule of
damper sizes to the Air Handling Systems Trade, with a copy to the Architect,
within one-hundred twenty (120) days after being awarded the contract.
3.09 LOUVERS AND BLANK-OFF PANELS
D. Outdoor air intake and exhaust louvers are specified under
other sections. Provide 1-1/2" x 1-1/2" x 1/4" galvanized angle
frames all around the louver openings securely bolted to
construction with mastic caulking compound between angle and
construction. Ductwork, casings, etc., shall be riveted to the
outstanding leg of angle frames.
1. Blank-off panels where required shall be provided under
this Section of the specifications. Construction shall be
as follows:
a. Panels shall be fabricated from 1" thick
laminated of 0.063" thick aluminum skins both sides
of perlite board insulation secured and sealed to
back of unit. Provide 100% coverage of blank-off
panels and cut openings as required. Panels shall
be as manufactured by Xxxxx Industries, Inc.,
Energy Panel Structures, Inc. or Panels Plus.
2. Provide No. 2 (1/2" mesh) 0.063" diameter aluminum bird
screens with rewirable and removable extruded aluminum
frames on the interior face of all louvers and openings
used for supply or exhaust purposes.
3.10 MEDIUM AND HIGH PRESSURE CASING TAP-OFF
Project No. C-0019 ADDENDUM NO. 1 15890-19
A. Tap-off connections for medium and high pressure rectangular
supply ducts to be made by means of 1/8" angle frames with 3"
legs. Holes to be cut in the casing to receive the collars with
the outside leg of collars on the inside of casing. Collars to be
stagger riveted to the casing on 4" centers. Apply sealing
compound between legs of collars and casings before riveting in
place.
3.11 SEALING & LEAK TESTING
A. All ductwork shall be airtight before concealment and/or before
insulation is applied.
1. ALL LOW PRESSURE DUCT SYSTEMS (3"W.G. AND BELOW): The
corners of all joints, longitudinal seams, openings, etc.,
shall be sealed as hereinbefore specified. Particular care
shall be taken on all ductwork on the suction side of all
fans.
a. A duct system need not be completed before tests
are conducted. Sections may be temporarily blanked
off or suitably capped, etc., and such sections
individually tested as specified. All equipment,
portable blower, instruments, temporary
connections, blank-offs, etc., necessary to conduct
tests as specified shall be provided by the
Contractor, the costs of which shall be included in
the Contractor's original bid for the work, without
any additional costs to the Owner.
END OF SECTION 15890
Project No. C-0019 XXXXXXXX XX. 0 00000-0
Project No. C-0019 ADDENDUM NO. 1 15890-20