Customer Agreement
IBM Digital Manufacturing Solutions (DMS)
Project Change Authorization
The purpose of this Project Change Authorization is to alter the existing
Statement of Work to include the installation of IBM IndustryView for AAP at the
Pinacor Cincinnati facility. The initial evaluation of IndustryView for AAP
installation at the Cincinnati site is a estimate of 60 hours at $200 per hour
totaling $12,000. Additionally, 2% of the total contract revenue will be billed
as an administrative fee and $3000 for travel.
Estimated Total Charges: $12,000 Additionally, 2% of the total contract revenue
will be billed as an Administrative Fee.
Estimated Total Expenses: $3000
Project Scope Addition:
1) The IndustryView team will assist Pinacor by working with the
customer team to perform the following: Perform a Requirements and
Design Study and prepare a Statement of Work for the Cincinnati
location.
Key Assumptions:
IBM's estimated charges and schedules to perform the following additions to the
existing Statement of Work are based on the following key assumptions.
Deviations that arise during the proposed project change request will be managed
through the procedure described in Project Change Control Procedure in Appendix
B of the original Statement of Work.
I All necessary Pinacor representatives are available for interview in each
subject area.
Modifications to Existing Statement of Work Dated March 16, 1999
Add the following to the IBM responsibilities section after 2.2.3:
2.2.3.1 Define and Validate Requirements and Develop Detail Design for the
IndustryView for AAP Cincinnati
Task Description: The purpose of this task is to define and validate that the
functions provided by the base application software and the required
enhancements will support the intended Cincinnati business environment. The
following functional requirements will be addressed in this task:
o MSTAR Interface Requirements
o EDI requirements
o Test server requirements
o Business rules requirements
o Routing requirements
o Administrative profile requirements
o Unique Cincinnati business and schedule requirement
o New reporting requirements
The sub tasks are:
1. Develop an interview procedure and checklist.
2. Develop an interview schedule and plan.
3. Develop documentation standards for interview results.
4. Conduct interviews of key Pinacor personnel to validate the requirements for
the Pinacor Cincinnati IndustryView installation.
5. Refine/identify the interfaces required between the IndustryView for
AAP and other systems.
6. Review requirements statement with the Pinacor IT and MSTAR support Team.
7. Document that the requirements identified are met by the application
software packages and the proposed design enhancements.
--------------------------------------------------------------------------------
Page 1
Customer Agreement
IBM Digital Manufacturing Solutions (DMS)
Project Change Authorization
8. Consult with Pinacor on identified interfaces and dependencies to existing
computer systems that are required to support the Cincinnati facility.
Completion Criteria: Documentation of the Pinacor requirements for the
integration of IndustryView for AAP into the Cincinnati facility will be
complete when the Pinacor Requirements Report and Design Report are delivered to
the Pinacor Project Executive.
Deliverables: The following item will be delivered to Pinacor as a result of
this task:
The IndustryView for AAP Cincinnati Design Report.
IndustryView for AAP Statement of Work for the Cincinnati Pinacor
Facility
This offer will expire on 5/30/99.
Both of us agree that the complete agreement between us about these Services
will consist of, (1) This Statement of Work, and (2) the IBM Customer Agreement
or IBM Customer Agreement - Project Support Services, as applicable (or any
equivalent agreement signed by both of us).
Agreed to: Agreed to:
Pinacor Corporation International Business Machines
Corporation
By: /s/ Xxx Xxxxx By:
------------------------------------ ---------------------------------
Authorized Signature Date Authorized Signature
Date
Authorized Name (print) Xxx Xxxxx
----------
Customer Number: 5816159 IBM Customer Agreement
Number. CFTG68A
Customer Address:
000 Xxxx Xxxxxxx
Xxxxx, Xxxxxxx 00000-1824 Office Number:
Project Name or Identifier:IV-AAP IBM Office Address:
Project Change Request Number: PCR # 2 1798 N.W. 40th Street
Boca Raton, Florida 33431
Estimated Start Date May 20,1999
Estimated End Date: June 4,1999
--------------------------------------------------------------------------------
Page 2