Exhibit 10(G)
SIERRA PACIFIC RESOURCES OPERATING
COMPANIES FERC ELECTRIC TARIFF,
FIRST REVISED VOLUME NO. 1
SERVICE AGREEMENT NO. 90
Effective: June 1, 2002
Sierra Pacific Resources Operating Companies
FERC Electric Tariff
First Revised Volume No. 1 Service Agreement No. 90
Open Access Transmission Tariff
--------------------------------------------------------------------------------
Page 1 of 4
Service Agreement For Long-Term
Firm Point-To-Point Transmission Service
1.0 This Service Agreement, dated as of July 5, 2001, is entered into,
------------
by and between Sierra Pacific Power Company and/or Nevada Power Company as
appropriate ("Transmission Provider"), and Reliant Energy Services, Inc.,
(Reliant - Bighorn) ("Transmission Customer").
2.0 The Transmission Customer has been determined by the Transmission Provider
to have a Completed Application for Firm Point-To-Point Transmission
Service under the Tariff.
3.0 The Transmission Customer has provided to the Transmission Provider an
Application deposit in accordance with the provisions of Section 17.3 of
the Tariff.
4.0 Service under this agreement shall commence on the later of (1) the
requested service commencement date, or (2) the date on which construction
of any Direct Assignment Facilities and/or Network Upgrades are completed,
or (3) such other date as it is permitted to become effective by the
Commission. Service under this agreement shall terminate on the actual
termination date or such date as mutually agreed upon by the parties.
5.0 Transmission Customer understands that it may not be possible to renew this
Agreement beyond its initial term without the construction of additional
Network Upgrades. Transmission Customer's right to renew this Agreement
beyond its initial term therefore is subject to there being adequate
available transmission capacity not allocated to an entity with a higher
priority to transmission capacity. If adequate capacity is not available,
Transmission Customer's right to renew this Agreement is subject to
Sections 19-21 of the Transmission Provider's Tariff and also is subject to
Transmission Customer's agreement to pay any costs of Network Upgrades that
Transmission Provider is authorized to charge to Transmission Customer in
accordance with Commission policy.
6.0 The Transmission Provider agrees to provide and the Transmission Customer
agrees to take and pay for Firm Point-To-Point Transmission Service in
accordance with the provisions of Part II of the Tariff and this Service
Agreement.
7.0 Any notice or request made to or by either Party regarding this Service
Agreement shall be made to the representative of the other Party as
indicated below.
--------------------------------------------------------------------------------
Sierra Pacific Resources Operating Companies
FERC Electric Tariff
First Revised Volume No. 1 Service Agreement No. 90
Open Access Transmission Tariff
--------------------------------------------------------------------------------
Page 2 of 4
8.0 If any event occurs that will materially affect the time for completion of
new facilities or the ability to complete them, Transmission Provider shall
promptly notify the Transmission Customer. A technical meeting between the
Parties shall be held to evaluate the alternatives available. If the
Transmission Provider and the Transmission Customer mutually agree that no
other reasonable alternatives exist and the requested service cannot be
provided out of existing capability under the conditions of Part II of the
Tariff, the obligation to provide the requested Firm Point-To-Point
Transmission Service shall terminate and any deposit made by the
Transmission Customer shall be returned with interest pursuant to
Commission regulations 35.19a(a)(2)(iii). However, the Transmission
Customer shall be responsible for all prudently incurred costs by the
Transmission Provider through the time construction was suspended.
Transmission Provider:
---------------------
Executive Director, Transmission Services
Sierra Pacific Power Company
P.O. Box 10100
Reno, Nevada 89520
and/or
Director, Regional Transmission
Nevada Power Company
P.O. Box 230
Las Vegas, NV 89151
Transmission Customer:
---------------------
West Trading Group - Transmission
Reliant Energy Services, Inc.
P.O. Box 4455
Houston, TX 77210-4455
9.0 The Tariff is incorporated herein and made a part hereof.
IN WITNESS WHEREOF, the Parties have caused this Service Agreement to be
executed by their respective authorized officials.
Transmission Provider:
---------------------
By:
----------------------------- --------------- ---------------
Name Title Date
Transmission Customer:
---------------------
By:
----------------------------- --------------- ---------------
Name Title Date
--------------------------------------------------------------------------------
Sierra Pacific Resources Operating Companies
FERC Electric Tariff
First Revised Volume No. 1 Service Agreement No. 90
Open Access Transmission Tariff
--------------------------------------------------------------------------------
Page 3 of 4
Specifications For Long-Term Firm Point-To-Point
------------------------------------------------
Transmission Service
--------------------
1.0 Term of Transaction: 10 Year(s)
----------
Start Date: 06-01-02
--------
Termination Date: 05-31-12
--------
2.0 Description of capacity and energy to be transmitted by Transmission
Provider including the electric Control Area in which the transaction
originates.
500 MW from Bighorn (Xxxx) 230 kV Substation in Nevada Power Company's
Control Area to Xxxx 230 kV Substation using the Contract Path Bighorn
230 kV - Arden 230 kV - Xxxx 230 kV.
3.0 Point of Receipt Delivering Party
Bighorn (Xxxx) 230 kV Substation Reliant Energy Services, Inc.
4.0 Point of Delivery Receiving Party
Xxxx 230 kV Substation Reliant Energy Services, Inc.
5.0 Maximum amount of capacity and energy to be transmitted (Reserved
Capacity): 500 MW
------
6.0 Designation of party(ies) subject to reciprocal service obligation:
None
----
7.0 Name(s) of any Intervening Systems providing transmission service:
None
----
--------------------------------------------------------------------------------
Sierra Pacific Resources Operating Companies
FERC Electric Tariff
First Revised Volume No. 1 Service Agreement No. 90
Open Access Transmission Tariff
--------------------------------------------------------------------------------
Page 4 of 4
8.0 Service under this Agreement may be subject to some combination of the
charges detailed below. (The appropriate charges for individual
transactions will be determined in accordance with the terms and conditions
of the Tariff.)
8.1 Transmission Charge: $1.21/kW-mo.
------------
8.2 System Impact and/or Facilities Study Charge(s):
Pending finalization, $30,000 deposit in place. Reliant will be
---------------------------------------------------------------
responsible for the final actual costs.
--------------------------------------
8.3 Direct Assignment Facilities Charge: None under this TSA. However,
-----------------------------
Direct Assignment Facilities will be required to provide the
------------------------------------------------------------
associated interconnection and are defined in the Interconnection &
-------------------------------------------------------------------
Operation Agreement.
-------------------
8.4 Ancillary Services Charges: As negotiated.
--------------
8.5. Power Factor Requirements: As defined in Interconnection and Operation
-------------------------------------------
Agreement.
---------
--------------------------------------------------------------------------------