INTERCONNECTION AGREEMENT AMONG THE
Interconnection Agreement • August 22nd, 2024 • New York
AutoNDA by SimpleDocs
INTERCONNECTION AGREEMENT AMONG THE NEW YORK INDEPENDENT SYSTEM OPERATOR, INC. NEW YORK STATE ELECTRIC & GAS CORPORATION, AND Broome Energy Resources, LLC Dated as of July 26, 2012
Interconnection Agreement • January 13th, 2021 • New York

Attachment 2 - Detailed Scope of Work, Including Description and Costs of the Small Generating Facility, Interconnection Facilities, and Metering Equipment 1

INTERCONNECTION AGREEMENT AMONG THE
Interconnection Agreement • January 23rd, 2019 • New York
INTERCONNECTION AGREEMENT AMONG THE
Interconnection Agreement • January 23rd, 2019 • New York
Contract
Interconnection Agreement • January 17th, 2019 • New York

New York Independent System Operator, Inc. - NYISO Agreements - Service Agreements - Agreement 1895 SGIA NYISO, NYSEG & Broome Energy Resources

Contract
Interconnection Agreement • January 17th, 2019 • New York

New York Independent System Operator, Inc. - NYISO Agreements - Service Agreements - Agreement 1895 SGIA NYISO, NYSEG & Broome Energy Resources

INTERCONNECTION AGREEMENT AMONG THE
Interconnection Agreement • September 17th, 2018 • New York

Milestone Date Responsible Party (1) Complete Engineering Design Completed, Oct 2010 Connecting Transmission Owner (2) Place Equipment Orders Completed, Oct 2010 Connecting Transmission Owner (3) Commence Small Generating Facility construction Completed, May 2010 Interconnection Customer (4) Complete Interconnection Customer’s Interconnection Facilities (SRS Substation) Completed, July 2010 Interconnection Customer (5) Complete Connecting Transmission Owner RTU upgrades Completed, Nov 2010 Connecting Transmission Owner (6) Complete Connecting Transmission Owner Energy Control Center Modeling Completed, Nov 2010 Connecting Transmission Owner (7) Testing and commissioning, Phase I – 8 MW Dec 2010 Interconnection Customer/Connecting Transmission Owner (8) In-Service Date, Phase I (8 MW) Dec 2010 Interconnection Customer (9) Relocation Work March 2011 Connecting Transmission Owner (10) Testing and commissioning, Phase II – 12 MW April 2011 Interconnection Customer

INTERCONNECTION AGREEMENT AMONG THE
Interconnection Agreement • September 17th, 2018 • New York

This Interconnection Agreement (“Agreement”) is made and entered into this 26th day of July 2012, by and among the New York Independent System Operator, Inc., a not-for-profit corporation organized and existing under the laws of the State of New York (“NYISO”) and New York State Electric & Gas Corporation, a corporation organized and existing under the laws of the State of New York (“Connecting Transmission Owner” or “NYSEG”), and Broome Energy Resources, LLC, a limited liability corporation organized and existing under the laws of the State of New York (“Interconnection Customer”) each hereinafter sometimes referred to individually as “Party” or referred to collectively as the “Parties.”

INTERCONNECTION AGREEMENT AMONG THE NEW YORK INDEPENDENT SYSTEM OPERATOR, INC. NEW YORK STATE ELECTRIC & GAS CORPORATION, AND Broome Energy Resources, LLC Dated as of July 26, 2012
Interconnection Agreement • September 17th, 2018 • New York

Attachment 2 - Detailed Scope of Work, Including Description and Costs of the Small Generating Facility, Interconnection Facilities, and Metering Equipment 1

SERVICE AGREEMENT NO. 1677 AMENDED AND RESTATED INTERCONNECTION AGREEMENT AMONG THE
Interconnection Agreement • March 24th, 2017 • New York

Milestone Date Responsible Party (1) Complete Engineering Design Completed Connecting Transmission Owner (2) Place Equipment Orders Completed Connecting Transmission Owner (3) Commence Small Generating Facility construction Completed Interconnection Customer (4) Complete Interconnection Customer’s Interconnection Facilities (SRS Substation) Completed Interconnection Customer (5) Complete Connecting Transmission Owner RTU upgrades Completed Connecting Transmission Owner (6) Complete Connecting Transmission Owner Energy Control Center Modeling Completed Connecting Transmission Owner (7) Testing and commissioning, Phase I – 8 MW Completed Interconnection Customer/Connecting Transmission Owner (8) In-Service Date, Phase I (8 MW) Completed Interconnection Customer (9) Line Relocation Work Completed Connecting Transmission Owner (10) Breaker Relocation Work Later of Feb 28, 2013 or 60 days following theclose of sale of Inteconnection Customer

INTERCONNECTION AGREEMENT AMONG THE
Interconnection Agreement • March 23rd, 2017 • New York
INTERCONNECTION AGREEMENT AMONG THE NEW YORK INDEPENDENT SYSTEM OPERATOR, INC. NEW YORK STATE ELECTRIC & GAS CORPORATION, AND Broome Energy Resources, LLC Dated as of July 26, 2012
Interconnection Agreement • March 23rd, 2017 • New York

Attachment 2 - Detailed Scope of Work, Including Description and Costs of the Small Generating Facility, Interconnection Facilities, and Metering Equipment 1

INTERCONNECTION AGREEMENT
Interconnection Agreement • July 26th, 2016 • New York

Attachment 2 Detailed Scope of Work, Including Description and Costs of the Small Generating Facility, Interconnection Facilities, and Metering Equipment

INTERCONNECTION AGREEMENT
Interconnection Agreement • July 26th, 2016 • New York

Attachment 2 Detailed Scope of Work, Including Description and Costs of the Small Generating Facility, Interconnection Facilities, and Metering Equipment

INTERCONNECTION AGREEMENT AMONG THE
Interconnection Agreement • August 3rd, 2012 • New York
INTERCONNECTION AGREEMENT AMONG THE
Interconnection Agreement • December 15th, 2010 • New York

Milestone Date Responsible Party (1) Complete Engineering Design Completed, Oct 2010 Connecting Transmission Owner (2) Place Equipment Orders Completed, Oct 2010 Connecting Transmission Owner (3) Commence Small Generating Facility construction Completed, May 2010 Interconnection Customer (4) Complete Interconnection Customer’s Interconnection Facilities (SRS Substation) Completed, July 2010 Interconnection Customer (5) Complete Connecting Transmission Owner RTU upgrades Completed, Nov 2010 Connecting Transmission Owner (6) Complete Connecting Transmission Owner Energy Control Center Modeling Completed, Nov 2010 Connecting Transmission Owner (7) Testing and commissioning, Phase I – 8 MW Dec 2010 Interconnection Customer/Connecting Transmission Owner (8) In-Service Date, Phase I (8 MW) Dec 2010 Interconnection Customer (9) Relocation Work March 2011 Connecting Transmission Owner (10) Testing and commissioning, Phase II – 12 MW April 2011 Interconnection Customer