GENERAL INSTRUCTIONSGeneral Instructions • February 14th, 2023
Contract Type FiledFebruary 14th, 2023Persons interested in submitting a Level 1 (20kW and less) Distributed Generator Facility (“DGF”) Interconnection Request, must complete the attached Mississippi Power Company (“MPC” or the “Company”) Distributed Generator Interconnection Application and Agreement (collectively referenced herein as the “Application”). This Application is required for new installations, modifications to existing interconnected DGF equipment, or changes of ownership or control of existing DGF equipment. Applications may be submitted by a new or existing MPC customer or on behalf of the MPC customer by a customer-authorized installer (“Installer”). If the DGF has a Nameplate Capacity greater than 20kW and less than 2 MW, the DGF Level 2 Interconnection Application must be completed and submitted to MPC. For a DGF with a Nameplate Capacity greater than 2 MW, the Level 3 Interconnection Application must be completed.