BACKGROUND:Second Delivery Point Agreement • September 19th, 2012
Contract Type FiledSeptember 19th, 2012The development of the second delivery point continues to move forward, and to date is on budget. City staff has opened bids on the transformer and most equipment needed for the substation. The total equipment recommended for purchase to date is $1,589,365. As part of the bid document, these bids are valid for 90 days. Staff will not be bringing forward a recommendation for awarding bids until we have the total project cost. The items that still need to be bid are two 34 kV overhead circuits, control house, construction and miscellaneous SCADA equipment. The engineering estimate for the remaining items is $900,000.